From:    Brandon Valdez                  To: David Ficklin - OnGoal
                                                                          Rory O’Connor – OnGoal
                             Office: Kansas City                          Lee Turner – OnGoal
                             Date:    8.4.2010                            Andy Heitmann – Turner
                                                                          Dave Dudzik - Turner
                             Re:      Wizards Stadium Project
                                      Update – Week of
                                      8.2.2010



 Current Activities this Week:

 Mass Excavation:
 Backfilling of on-grade seating is ongoing in Area 2
 and Area 3.

 Site Utilities:
 Storm Sewer Installation (Line 6000) is ongoing             Area 3 – Installation of Storm Line 6000 is
 on the east side of France Family Drive.                    ongoing on the east side of France Family
                                                             Drive.
  Foundations:
 Area 3 Field Level – Foundation installation continues on
 the east side of the site. Currently to Column Line 1.

 Concrete Flatwork:
 Area 1 – Slab-on-grade is placed at field level to
 Column line 23. Prep for Slab-on grade is ongoing from
 Column lines 23-15.

 Structural Steel Erection:                                Field Level Area 3 – Foundations are
 Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-8). continuing on the East Side.
 Area 3 – Steel erection is ongoing in Sequence 3-2.
 ongoing.

 Precast Concrete:
 Area 2 – Precast erection has started.

 Underground MEP:
 Electrical Secondary Distribution is ongoing in Areas 2.


                                                             Area 2 – Precast erection has started on the
                                                             south elevation.

Building the Future
MEP Rough-in:
 Area 2 – Shallow electrical and plumbing rough-in is
 ongoing. Ductwork installation on Suite Level is ongoing.
 Plumbing rough-in is ongoing on Suite Level.

 Metal Stud Framing:
                                                                Field Level Area 3 – Steel Erection has
 Area 1 – Metal stud framing for Suite and Press
                                                                started in Sequence 3-2. Steel is currently
 Levels are ongoing. Metal stud framing is ongoing on           set to Column Line 4.
 Main Concourse West Building.

 Projected Activities occurring next Week:

 Mass Excavation:
 Backfilling of on-grade seating areas will continue in Area
 3. Grading in Area 3 (east of A-Line) will continue.

 Site Utilities:
 Installation of the Storm Line 6000 on the East Side (France
 Family Drive) of the site will be complete. Sanitary Sewer
 installation will begin at locations where Storm Line 6000
 is complete.
                                                                Area 1 – Shot of the West Building from the
 Deep Underground MEP:                                          south concourse.
 Deep Electrical Distribution installation will continue
 in Area 3.

 Foundations:
 Area 3 Field Level – Foundation installation will continue.

 Concrete Flatwork:
 Area 2 Field Level – Concrete placement for Slab-on-Grade
 will be completed to Column Line 15.

 Area 1 and 2 Field Level – Installation of on-grade seating
 risers will continue.
                                                                Field Level Area 1 – Masonry underway on
 Structural Steel Erection:                                     Field Level.
 Erection of Structural Steel in Sequence 3-2 will
 continue. Installation of columns for Canopy will begin.



Building the Future
Erection of the Canopy Trusses will continue in
 Sequence 1-8.

 Underground MEP:
 Electrical Secondary will continue in Area 3.

 MEP Rough-in:
 Plumbing and Electrical rough-in for Area 2 Field Level slab
 on grade will continue. MEP Rough-in at Suite Level will       Area 1 – First course of masonry going up on
 continue. Ductwork installation on Press Level will begin.     southwest restrooms.

 Metal Stud Framing:
 Area 1 – Metal stud framing for Concourse, Suite and Press
 Levels will continue.




                                                                Suite Level Area 1 – 80x34 return air duct
                                                                being installed at mechanical shaft at
                                                                Column Line 27.




Building the Future
Additional Photos:




Roof Level Area 1 – Roof curbs have arrived   Concourse Level Area 1 – Installation of
and are being set on roof.                    metal deck on platforms is complete.




                                              Field Level Area 1 – Slab-on-Grade prep
Concourse Level Area 1 – Terrace area         ongoing for next pour from Column Line 23-
taking shape.                                 15.




Area 1 – Players benches concrete is nearly   Suite Level Area 1 – Installation of plumbing
complete.                                     carriers is ongoing on Suite Level.




Building the Future

Mais conteúdo relacionado

Mais de Kansas City Wizards

Mais de Kansas City Wizards (12)

Memo wizards 08-25-2010
Memo wizards 08-25-2010Memo wizards 08-25-2010
Memo wizards 08-25-2010
 
Construction Update 07-28-2010
Construction Update 07-28-2010Construction Update 07-28-2010
Construction Update 07-28-2010
 
Unicorn Wizards Scouting
Unicorn Wizards ScoutingUnicorn Wizards Scouting
Unicorn Wizards Scouting
 
KC Soccer Stadium
KC Soccer Stadium KC Soccer Stadium
KC Soccer Stadium
 
Construction Update 7-6-2010
Construction Update 7-6-2010Construction Update 7-6-2010
Construction Update 7-6-2010
 
Weekly Construction Update 06-14-10
Weekly Construction Update 06-14-10Weekly Construction Update 06-14-10
Weekly Construction Update 06-14-10
 
Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010
 
Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010
 
Construction Update 5-5-2010
Construction Update 5-5-2010Construction Update 5-5-2010
Construction Update 5-5-2010
 
Construction Update 4-14-2010
Construction Update 4-14-2010Construction Update 4-14-2010
Construction Update 4-14-2010
 
Construction Update 4-7-2010
Construction Update 4-7-2010Construction Update 4-7-2010
Construction Update 4-7-2010
 
Construction Update 5-12-2010
Construction Update 5-12-2010Construction Update 5-12-2010
Construction Update 5-12-2010
 

Construction Update 8-04-2010

  • 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 8.4.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 8.2.2010 Current Activities this Week: Mass Excavation: Backfilling of on-grade seating is ongoing in Area 2 and Area 3. Site Utilities: Storm Sewer Installation (Line 6000) is ongoing Area 3 – Installation of Storm Line 6000 is on the east side of France Family Drive. ongoing on the east side of France Family Drive. Foundations: Area 3 Field Level – Foundation installation continues on the east side of the site. Currently to Column Line 1. Concrete Flatwork: Area 1 – Slab-on-grade is placed at field level to Column line 23. Prep for Slab-on grade is ongoing from Column lines 23-15. Structural Steel Erection: Field Level Area 3 – Foundations are Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-8). continuing on the East Side. Area 3 – Steel erection is ongoing in Sequence 3-2. ongoing. Precast Concrete: Area 2 – Precast erection has started. Underground MEP: Electrical Secondary Distribution is ongoing in Areas 2. Area 2 – Precast erection has started on the south elevation. Building the Future
  • 2. MEP Rough-in: Area 2 – Shallow electrical and plumbing rough-in is ongoing. Ductwork installation on Suite Level is ongoing. Plumbing rough-in is ongoing on Suite Level. Metal Stud Framing: Field Level Area 3 – Steel Erection has Area 1 – Metal stud framing for Suite and Press started in Sequence 3-2. Steel is currently Levels are ongoing. Metal stud framing is ongoing on set to Column Line 4. Main Concourse West Building. Projected Activities occurring next Week: Mass Excavation: Backfilling of on-grade seating areas will continue in Area 3. Grading in Area 3 (east of A-Line) will continue. Site Utilities: Installation of the Storm Line 6000 on the East Side (France Family Drive) of the site will be complete. Sanitary Sewer installation will begin at locations where Storm Line 6000 is complete. Area 1 – Shot of the West Building from the Deep Underground MEP: south concourse. Deep Electrical Distribution installation will continue in Area 3. Foundations: Area 3 Field Level – Foundation installation will continue. Concrete Flatwork: Area 2 Field Level – Concrete placement for Slab-on-Grade will be completed to Column Line 15. Area 1 and 2 Field Level – Installation of on-grade seating risers will continue. Field Level Area 1 – Masonry underway on Structural Steel Erection: Field Level. Erection of Structural Steel in Sequence 3-2 will continue. Installation of columns for Canopy will begin. Building the Future
  • 3. Erection of the Canopy Trusses will continue in Sequence 1-8. Underground MEP: Electrical Secondary will continue in Area 3. MEP Rough-in: Plumbing and Electrical rough-in for Area 2 Field Level slab on grade will continue. MEP Rough-in at Suite Level will Area 1 – First course of masonry going up on continue. Ductwork installation on Press Level will begin. southwest restrooms. Metal Stud Framing: Area 1 – Metal stud framing for Concourse, Suite and Press Levels will continue. Suite Level Area 1 – 80x34 return air duct being installed at mechanical shaft at Column Line 27. Building the Future
  • 4. Additional Photos: Roof Level Area 1 – Roof curbs have arrived Concourse Level Area 1 – Installation of and are being set on roof. metal deck on platforms is complete. Field Level Area 1 – Slab-on-Grade prep Concourse Level Area 1 – Terrace area ongoing for next pour from Column Line 23- taking shape. 15. Area 1 – Players benches concrete is nearly Suite Level Area 1 – Installation of plumbing complete. carriers is ongoing on Suite Level. Building the Future