1. From: Brandon Valdez To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Office: Kansas City Lee Turner – OnGoal
Date: 6.9.2010 Andy Heitmann – Turner
Dave Dudzik - Turner
Re: Wizards Stadium Project
Update – Week of
6.7.2010
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating is ongoing in Area 1,
Area 2 and Area 3.
Site Utilities:
Storm Sewer installation (Line 6000) is ongoing on Field Level Area 1 – Shallow Underground
east side of France Family Drive. plumbing pipe installation has started at
Men’s Field Toilet 01.32.02.
Sanitary Sewer Line E installation has started on east
side of France Family Dive.
Foundations:
Area 2 Concourse Level – E-Line footing installation is
ongoing and E-Line wall installation is ongoing.
Area 3 Field Level – A-Line footing (to column line 1) and
wall installation (to column line 4) is ongoing.
Area 3 Field Level – Installation of Drilled Piers
Field Level Area 3 – A-Line footing and wall
are complete.
installation is ongoing up to Column Line 1.
Area 4 Mezzanine Level – D-Line grade beam installation
is ongoing and wall forms are being set.
Concrete Flatwork:
Area 1 Mezzanine – North slab on metal deck at VIP
Entry concrete is placed.
Area 1 Concourse – Structural Slab is placed from
Column lines 33-23.
Mezzanine Level Area 1 – Concrete Slab on
Metal Deck at VIP Entry is placed.
Building the Future
2. Structural Steel Erection:
Area 1 – Steel Erection in sequence 1-5 is nearly complete
is currently to Column Line 23. Seven raker pieced remain.
Decking/Detailing/Studs/Edge Angle is ongoing in
sequence 1-2, 1-4 and 1-5.
Underground MEP: Concourse Level Area 1 – Concrete
Deep Sanitary installation is ongoing in Area 3. installation taking place from Column Lines
C – 33.
Electrical Secondary is ongoing in Area 2
MEP Rough-in:
Plumbing and Electrical rough-in for concrete decks are
ongoing Suite Level. Shallow plumbing rough-in has
started at Area 1 Field Level.
Projected Activities occurring next Week:
Mass Excavation:
Backfilling of on-grade seating areas will continue in Area
3.
Area 1 – Structural Steel Erection at West
Site Utilities: Building is nearly complete from Column
Installation of the Storm Line 6000 on the East Side (France Line 33 – 23.
Family Drive) of the site will continue. Storm Line 5000 and
4000 will begin. Installation of Sanitary Line E will continue.
Deep Underground Plumbing:
Deep Sanitary installation in Area 3 will continue.
Foundations:
Area 2 Concourse Level – Footing and wall installation
will continue.
Area 3 Field Level – A-Line wall placement will continue.
Field Level Area 2 – Backfill of on-grade
Area 4 Mezzanine Level – Foundation Wall installation will seating area between column lines 21-18 is
ongoing.
continue.
Building the Future
3. Concrete Flatwork:
Area 1 Suite Level – Concrete placement will begin.
Structural Steel Erection:
Erection of Structural Steel in Sequence 1-3 will
begin.
Decking/Detailing/Studs/Edge Plates will continue in
Sequence 1-5. Field Level Area 2 – Isolated footing C12
reinforcing steel being installed.
Underground MEP:
Deep Sanitary installation will continue in Area 3.
Electrical Secondary will continue in Area 2
MEP Rough-in:
Plumbing and Electrical rough-in for concrete decks will
begin at Press Level. Shallow plumbing rough-in will
continue at Area 1 Field Level. Shallow electrical will
begin at Area 1 Field Level.
Suite Level Area 1 – Concrete slab
reinforcing being installed in preparation for
upcoming pour.
Building the Future
4. Additional Photos:
Area 1 – Shot looking south showing the
field walls, foundations walls, rakers and Field Level Area 2/3 – Shot looking northeast
west building. showing foundations from column line 15-1.
Field Level Area 1 – Secondary electrical
underground is ongoing near column line Concourse Level Area 2 – Footing excavation
21. for E-Line footing is ongoing.
Field Level Area 2 – Shot looking south
showing southeast vomitory, south on-grade Field Level Area 1 – Electrical manhole MH-1
seating, stage and southwest vomitory. is installed.