1. From: Brandon Valdez To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Office: Kansas City Lee Turner – OnGoal
Date: 9.8.2010 Andy Heitmann – Turner
Dave Dudzik - Turner
Re: Wizards Stadium Project
Update – Week of
9.6.2010
Current Activities this Week:
Underground Utilities:
Area 3 - Deep underground Plumbing continues.
on the east side of France Family Drive. Installation of
the gas service has commenced.
Foundations:
Area 4 Field Level – Upper Field wall forms are being Area 3 – Underground plumbing installation
installed. is ongoing at the lower dock area.
Concrete Flatwork:
Area 2 Concourse – Concrete placement for slab at
South Concession Buildings is complete to column line
15.
Structural Steel Erection:
Area 2 – Main Canopy Truss Erection are set to Column
Line 6. Area 4 – Structural Steel in Sequence 3-3 is
erected to column line 39. Area 2 – CMU wall installation has started at
Stage.
MEP Rough-in:
Area 3 – Shallow electrical and plumbing rough-in is
ongoing. Ductwork installation on Suite and Press Levels
are ongoing. Plumbing rough-in is ongoing on Suite and
Press Levels. Fire Protection rough-in is ongoing on
Suite and Press Levels. Electrical rough-in is ongoing on
Suite and Press Levels.
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels are ongoing. Exterior metal stud framing Area 4 – Structural Steel Erection Sequence
3-3 has been set to column line 39.
Building the Future
2. and sheathing installation is ongoing at Field, Suite, and
Press Levels.
Masonry:
Area 1 Field Level – Masonry wall installation is ongoing
in Areas E, F, G and H.
Area 1, 2 Concourse Level – Masonry wall installation at Area 3 – Canopy Truss erection is complete
Main Concourse Buildings are underway. in Sequence 2-2 (installation of Truss to 6
Line shown).
Curtainwall:
Area 1 – Curtainwall framing installation will continue
at West Elevation. Installation of Curtainwall glass is
ongoing.
Projected Activities occurring next Week:
Underground Utilities:
Deep Plumbing installation will continue in Area 3.
Foundations:
Area 4 Field Level – Foundation wall installation for Main
Stair will begin. Field Level Area 3 – Formwork of Main Stair
support walls are being set.
Concrete Flatwork:
Area 3 Field Level – Concrete placement for Slab-on
Grade at upper dock area will begin. Prep work for slab-
on-grade for lower dock area will begin.
Area 3 and 4 Field Level – Installation of on-grade seating
risers and intermediate stairs will continue.
Structural Steel Erection:
Area 2 – Canopy truss installation at East side of Stadium
will continue.
Area 1 – Filled and polished CMU Block walls
MEP Rough-in: at the Stair 4 and Restrooms.
MEP Rough-in at Suite and Press Levels will continue.
Ductwork installation on Press Level will continue. Fire
Sprinkler installation will continue on Suite and Press Levels.
Building the Future
3. Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels will continue. Exterior Framing and
sheathing installation will continue.
Curtainwall:
Area 1 – Curtain Framing and Glass installation will
continue.
Area 1 – Installation of curtainwall framing
and Glass at West Building is ongoing.
Area 1 – Shot of the west building showing
the progress of the canopy decking on
trusses.
Building the Future
4. Additional Photos:
Area 1 – Shot of Suite fronts from roof of Suite Level Area 1 – Shot looking through
Stadium Suite. the glass at Suite Level Club.
Concourse Level Area 1 – Masonry
Area 1 – Curtainwall framing installation at installation continues on Concourse
south face of Club Areas. Buildings.
Field Level Area 3 – Installation of cast-in- Field Level Area 3 – Upper dock slab edge
place risers continue on east side. formwork is installed.