SlideShare a Scribd company logo
1 of 4
Download to read offline
From:    Brandon Valdez                To: David Ficklin - OnGoal
                                                                         Rory O’Connor – OnGoal
                              Office: Kansas City                        Lee Turner – OnGoal
                              Date:    9.1.2010                          Andy Heitmann – Turner
                                                                         Dave Dudzik - Turner
                              Re:      Wizards Stadium Project
                                       Update – Week of
                                       8.30.2010



 Current Activities this Week:

 Mass Excavation:
 Backfilling of foundations is nearly complete in Area 3.

 Site Utilities:
 Tie in of domestic and fire line services are complete
 on the east side of France Family Drive. Installation of
 the gas service has commenced.                             Area 4 – North field wall complete to the
                                                            Crane Road.
 Foundations:
 Area 4 Field Level – Field wall installation up to the
 crane road is complete.

 Concrete Flatwork:
 Area 2 Concourse – Prep work for next slab pour for
 South Concession Buildings is nearly complete.
 Area 3 Field Level – Prep work for slab pour at upper
 dock is nearly complete.

 Structural Steel Erection:                                 Area 2 – Stage concrete slab placement is
 Area 2 – Main Canopy Truss Erection are set to Column      complete.
 Line 10.

 Structural Precast Concrete:
 Area 3 – Precast tread/riser erection complete.

 Underground MEP:
 Area 3 - Deep underground Plumbing is ongoing.



                                                            Area 3 – Precast tread/riser erection is
                                                            complete.
Building the Future
MEP Rough-in:
 Area 3 – Shallow electrical and plumbing rough-in is
 ongoing. Ductwork installation on Suite and Press Levels
 are ongoing. Plumbing rough-in is ongoing on Suite and
 Press Levels. Fire Protection rough-in is ongoing on
 Suite and Press Levels. Electrical rough-in is ongoing on
 Suite and Press Levels.

 Metal Stud Framing:                                              Area 2 – Canopy Truss erection is complete
 Area 1 – Metal stud framing for Field, Concourse, Suite          in Sequence 2-2 (installation of Truss to 10
 and Press Levels are ongoing. Exterior metal stud framing        Line shown).
 and sheathing installation is ongoing at Field, Suite, and
 Press Levels.

 Masonry:
 Area 1 Field Level – Masonry wall installation is ongoing
 in Areas F, G and H.

 Area 3 Concourse Level – Masonry wall installation at
 Main Concourse Buildings are underway.

 Curtainwall:
 Area 1 – Curtainwall framing installation will continue
                                                                  Area 1 – Shot of the West Building from the
 at West Elevation. Installation of Curtainwall glass is
                                                                  Stage (Field Level).
 ongoing.

 Projected Activities occurring next Week:

 Site Utilities:
 Gas Service installation will continue on France Family Drive.

 Deep Underground MEP:
 Deep Plumbing installation will continue in Area 3.

 Foundations:
 Area 4 Field Level – Foundation wall installation for Main
 Stair will begin.                                                Area 1 – Exterior Metal Stud Framing and
                                                                  sheathing installation ongoing at north side
                                                                  of Stadium Suite.




Building the Future
Concrete Flatwork:
 Area 2 Concourse Level – Concrete placement for Slab-on
 Grade for Main Concourse Buildings will begin.

 Area 1, 2 and 3 Field Level – Installation of on-grade seating
 risers and intermediate stairs will continue.

 Structural Steel Erection:
 Area 2 – Canopy truss installation at South side of Stadium       Area 1 – Installation of curtainwall framing
 will continue. Area 3 – Canopy Truss installation will begin.     and Glass at West Building is ongoing.

 Underground MEP:
 Deep underground plumbing will continue in Area 3.

 MEP Rough-in:
 MEP Rough-in at Suite and Press Levels will continue.
 Ductwork installation on Press Level will continue. Fire
 Sprinkler installation will continue on Suite and Press Levels.

 Metal Stud Framing:
 Area 1 – Metal stud framing for Field, Concourse, Suite
 and Press Levels will continue. Exterior Framing and              Roof Level Area 1 – Installation of decking
 sheathing installation will continue.                             on Canopy Trusses has started.

 Curtainwall:
 Area 1 – Curtain Framing and Glass installation will
 continue.




Building the Future
Additional Photos:




Field Level Area 1 – Curtainwall glass, metal
stud framing and exterior sheathing being
installation at and above Main Club             Area 2 – Shot looking south from roof above
Entrance.                                       Stadium Suite.




Concourse Level Area 1 – Masonry at Main
Concourse Level is underway (Stair 4            Field Level Area 1 – Subroof framing
shown).                                         installation is ongoing.




Field Level Area 3 – Upper Dock Formwork
and MEP rough-in is ongoing in preparation      Field Level Area 2 – Masonry installation at
for concrete slab placement.                    Field Level (underneath terrace seating).




Building the Future

More Related Content

More from Kansas City Wizards

More from Kansas City Wizards (6)

Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010
 
Weekly Construction Update 05-19-2010
Weekly Construction Update 05-19-2010Weekly Construction Update 05-19-2010
Weekly Construction Update 05-19-2010
 
Construction Update 5-5-2010
Construction Update 5-5-2010Construction Update 5-5-2010
Construction Update 5-5-2010
 
Construction Update 4-14-2010
Construction Update 4-14-2010Construction Update 4-14-2010
Construction Update 4-14-2010
 
Construction Update 4-7-2010
Construction Update 4-7-2010Construction Update 4-7-2010
Construction Update 4-7-2010
 
Construction Update 5-12-2010
Construction Update 5-12-2010Construction Update 5-12-2010
Construction Update 5-12-2010
 

Construction Update 09-1-2010

  • 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 9.1.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 8.30.2010 Current Activities this Week: Mass Excavation: Backfilling of foundations is nearly complete in Area 3. Site Utilities: Tie in of domestic and fire line services are complete on the east side of France Family Drive. Installation of the gas service has commenced. Area 4 – North field wall complete to the Crane Road. Foundations: Area 4 Field Level – Field wall installation up to the crane road is complete. Concrete Flatwork: Area 2 Concourse – Prep work for next slab pour for South Concession Buildings is nearly complete. Area 3 Field Level – Prep work for slab pour at upper dock is nearly complete. Structural Steel Erection: Area 2 – Stage concrete slab placement is Area 2 – Main Canopy Truss Erection are set to Column complete. Line 10. Structural Precast Concrete: Area 3 – Precast tread/riser erection complete. Underground MEP: Area 3 - Deep underground Plumbing is ongoing. Area 3 – Precast tread/riser erection is complete. Building the Future
  • 2. MEP Rough-in: Area 3 – Shallow electrical and plumbing rough-in is ongoing. Ductwork installation on Suite and Press Levels are ongoing. Plumbing rough-in is ongoing on Suite and Press Levels. Fire Protection rough-in is ongoing on Suite and Press Levels. Electrical rough-in is ongoing on Suite and Press Levels. Metal Stud Framing: Area 2 – Canopy Truss erection is complete Area 1 – Metal stud framing for Field, Concourse, Suite in Sequence 2-2 (installation of Truss to 10 and Press Levels are ongoing. Exterior metal stud framing Line shown). and sheathing installation is ongoing at Field, Suite, and Press Levels. Masonry: Area 1 Field Level – Masonry wall installation is ongoing in Areas F, G and H. Area 3 Concourse Level – Masonry wall installation at Main Concourse Buildings are underway. Curtainwall: Area 1 – Curtainwall framing installation will continue Area 1 – Shot of the West Building from the at West Elevation. Installation of Curtainwall glass is Stage (Field Level). ongoing. Projected Activities occurring next Week: Site Utilities: Gas Service installation will continue on France Family Drive. Deep Underground MEP: Deep Plumbing installation will continue in Area 3. Foundations: Area 4 Field Level – Foundation wall installation for Main Stair will begin. Area 1 – Exterior Metal Stud Framing and sheathing installation ongoing at north side of Stadium Suite. Building the Future
  • 3. Concrete Flatwork: Area 2 Concourse Level – Concrete placement for Slab-on Grade for Main Concourse Buildings will begin. Area 1, 2 and 3 Field Level – Installation of on-grade seating risers and intermediate stairs will continue. Structural Steel Erection: Area 2 – Canopy truss installation at South side of Stadium Area 1 – Installation of curtainwall framing will continue. Area 3 – Canopy Truss installation will begin. and Glass at West Building is ongoing. Underground MEP: Deep underground plumbing will continue in Area 3. MEP Rough-in: MEP Rough-in at Suite and Press Levels will continue. Ductwork installation on Press Level will continue. Fire Sprinkler installation will continue on Suite and Press Levels. Metal Stud Framing: Area 1 – Metal stud framing for Field, Concourse, Suite and Press Levels will continue. Exterior Framing and Roof Level Area 1 – Installation of decking sheathing installation will continue. on Canopy Trusses has started. Curtainwall: Area 1 – Curtain Framing and Glass installation will continue. Building the Future
  • 4. Additional Photos: Field Level Area 1 – Curtainwall glass, metal stud framing and exterior sheathing being installation at and above Main Club Area 2 – Shot looking south from roof above Entrance. Stadium Suite. Concourse Level Area 1 – Masonry at Main Concourse Level is underway (Stair 4 Field Level Area 1 – Subroof framing shown). installation is ongoing. Field Level Area 3 – Upper Dock Formwork and MEP rough-in is ongoing in preparation Field Level Area 2 – Masonry installation at for concrete slab placement. Field Level (underneath terrace seating). Building the Future