Problem + Goals for Project
Problem-
1. Metal contaminate in paint shop pretreatment process that comes from the body shop.
2. Metal contaminates in the phosphate tanks can causes metal to deposit on the hood and
the entire body.
Goals for Summer Project-
1. Reduce the amount of metal debris in the phosphate process to improve quality of units
produced.
2. Implement a best practice as identified by FCA manufacturing engineering group for
phosphate.
3. Design and install the most effective device for collecting metal debris.
4. Install the magnet capsules during the week of summer shut down (July 16th).
5. Implement best practice as a cost reduction compared to Jefferson North Assembly Plant.
Pre-Design Consideration #1
Consideration #1 -
1. Easiness of cleaning and maintenance (Time)
NOK OK
Bare Magnet Housing Barrier
Testing Metal vs. PVC Housing
1. Now that housing was in mind for the project I had to decide if the magnets should be
placed into metal or PVC tubing.
• Initially it was thought that metal tubing would be the best choice because the
magnets would turn the metal tubing into one large magnet.
• The magnets were placed in both, PVC and steel, and the PVC had the largest
pull.
Metal housing attracts metal at 1.5” PVC housing attracts metal at 3”
Metal vs. PVC
NOK OK
Major Consideration- Method of Cleaning
1. Cleaning was a major thought when designing the magnet prototype. The time needed to
clean the design and return the design back into the system is important along with the
amount of material removed.
2. There are three methods considered for cleaning-
a. Metal or plastic tube that covers the magnets and another tube that is larger in
diameter to swipe down to remove material.
b. Bag over the magnets and remove the bag and replace with a new bag each time.
c. Metal or plastic tube that covers the magnets and just a swipe is needed for cleaning.
NOK
NOK
OK
Method C
Pre-Design Consideration #2
Consideration #2 -
1. Maximize the gauze of the rare earth magnets (Gauze)
Vertical Distance 3”Horizontal Distance 1.5”
NOK OK
Major Consideration- Maximizing Gauze
Time (Hours) Vertical Horizontal Percent Increase
1 10.2 16.8 64.7%
2 17.4 22.5 29.3%
4 28.4 36.3 27.8%
6 32.5 40.1 23.4%
8 35.7 43.3 21.3%
• To maximize the gauze of the magnets I changed the orientation of the magnets from horizontal to
vertical.
• This minor change can collect on average 33.3% more metal debris from the phosphate tanks.
0
5
10
15
20
25
30
35
40
45
50
1 2 3 4 5
GramsofMaterialRemoved
Time (Hours)
Maximizing Gauze
Prototypes #1-7 Overview
Prototype # Design Description Performance (Material Removed) Cost Analysis
1 Pendal-PVC Housing (Phosphate Bath) 0 grams $26.35
2 Pendal – Threaded Rod (Phosphate Bath) 0 grams $25.56
3 Bag- Threated Rod (Stage 0) Bag Failure - 0 grams $46.10
4 Threaded Rod- PVC Housing (Stage 0) 35.7 grams $48.24
5 PVC Housing- Magnet Orientation Rotated 90° (Stage 0) 43.3 grams $43.70
6 Square Flat Housing (Basket Strainer) Not Water Tight- 0 grams $6.34
7 PVC Housing – Magnet Orientation Rotated 90° (Basket Strainer) 28.4 grams $25.30
Prototype #1 Prototype #7
Selecting the Most Effective Design
Material Removed
(Grams- 8Hours)
N/A
N/A
N/A
35.7
43.3
N/A
20.1
Cost
$26.35
$25.56
$46.10
$48.24
$43.70
$6.34
$25.30
Prototype #
1
2
3
4
5
6
7
• Prototype #5 and #7 were chosen to more forward to mass produce during shut down because of
there results.
• Prototype #5 produced the most amount of material removed from the phosphate system
through the tanks (43.3 grams)
• Prototype #7 was selected because prototype 5 was not appropriate for basket strainers.
#5
#7
OK
OK
Material removed + $$$
Locations Deployed
1. Pendal
2. Tanks
3. Basket Strainer
NOK
OK
OK
Cost to Build
• The cost for the 12 capsules in phosphate is a total of $2,653.75
• These are the materials used to build the selected design
1. Stainless steel all thread (1/2”)
2. Stainless steel washers and nuts (1/2”)
3. Newspaper bags (21”long x 7-1/2” wide)
4. Rare earth magnets- Neodymium ring magnets N42(1.5” Diameter)
5. PVC tubing (1 ½” schedule 40)
6. PVC end caps (1 ½“)
7. PVC reducer cap (1 ½” to ½“)
Cost Comparison:
Toledo North Assembly- $2,654
Jefferson North Assembly- $250,000
Benefit of the Phosphate Install
With the install of the 12 capsules in phosphate the magnets will pull out 447.5 grams
each day from the tanks and basket strainers.
447.5 Grams = 1 Pound of Metal/day
1 Lb/day X 300 running days = 300 Pounds/Year
Magnet Design Overview- Phosphate Pretreatment
Prototypes that produced
results (#4,5,7) were selected
to move forward.
Install device #5 + #7 during
summer shutdown week
(installation: July 18th-22nd)
OK
NOK
OK
Mass produced the selected
prototypes.
Systematic Diagram
Prototype #2
Prototype #1
NOK
Prototype #3
Prototype #4
Prototype #5
Prototype #6
Prototype #7
NOK
NOK
OK
Prototypes #5 + #7 produce the best
results when considering cleaning
and material collected.

More Related Content

What's hot

Patil1999 versatility of chemical spray pyrolysis technique leer
Patil1999 versatility of chemical spray pyrolysis technique leerPatil1999 versatility of chemical spray pyrolysis technique leer
Patil1999 versatility of chemical spray pyrolysis technique leerheracliohu
 
IRJET- Utilization of Ceramic Waste in Grout
IRJET- Utilization of Ceramic Waste in GroutIRJET- Utilization of Ceramic Waste in Grout
IRJET- Utilization of Ceramic Waste in GroutIRJET Journal
 
L1 ndt versus mechanical testing &; overview of liquid penetrant test
L1 ndt versus mechanical testing &; overview of liquid penetrant testL1 ndt versus mechanical testing &; overview of liquid penetrant test
L1 ndt versus mechanical testing &; overview of liquid penetrant testkarthi keyan
 
Building Materials Testing - Exclusive Services for Infrastructure / Civil Se...
Building Materials Testing - Exclusive Services for Infrastructure / Civil Se...Building Materials Testing - Exclusive Services for Infrastructure / Civil Se...
Building Materials Testing - Exclusive Services for Infrastructure / Civil Se...Spectro Group of Companies
 
phosphate coating on alloys
phosphate coating on alloysphosphate coating on alloys
phosphate coating on alloysengrktk
 
experimental study on concrete using micro silica and nano silica
experimental study on concrete using micro silica and nano silicaexperimental study on concrete using micro silica and nano silica
experimental study on concrete using micro silica and nano silicaArmstra Junoly
 
Nano Technology & Nano Materials
Nano Technology & Nano MaterialsNano Technology & Nano Materials
Nano Technology & Nano MaterialsSLINTEC
 
2015 nurulainul sls mussel
2015 nurulainul sls mussel2015 nurulainul sls mussel
2015 nurulainul sls musselSidek Aziz
 
Both 2016 shanghai development of innovative ultra high temperature coatings ...
Both 2016 shanghai development of innovative ultra high temperature coatings ...Both 2016 shanghai development of innovative ultra high temperature coatings ...
Both 2016 shanghai development of innovative ultra high temperature coatings ...Yuguo Cui
 
internship report PCSIR
internship report PCSIRinternship report PCSIR
internship report PCSIRMuhammad Arif
 
Efficient growth techniques and properties of Benzophenone Single Crystals fo...
Efficient growth techniques and properties of Benzophenone Single Crystals fo...Efficient growth techniques and properties of Benzophenone Single Crystals fo...
Efficient growth techniques and properties of Benzophenone Single Crystals fo...Editor IJCATR
 
Design corrosion
Design   corrosion Design   corrosion
Design corrosion Ali Zamel
 

What's hot (18)

Lost Foam Casting (LFC) Process
Lost Foam Casting (LFC) ProcessLost Foam Casting (LFC) Process
Lost Foam Casting (LFC) Process
 
Patil1999 versatility of chemical spray pyrolysis technique leer
Patil1999 versatility of chemical spray pyrolysis technique leerPatil1999 versatility of chemical spray pyrolysis technique leer
Patil1999 versatility of chemical spray pyrolysis technique leer
 
IRJET- Utilization of Ceramic Waste in Grout
IRJET- Utilization of Ceramic Waste in GroutIRJET- Utilization of Ceramic Waste in Grout
IRJET- Utilization of Ceramic Waste in Grout
 
L1 ndt versus mechanical testing &; overview of liquid penetrant test
L1 ndt versus mechanical testing &; overview of liquid penetrant testL1 ndt versus mechanical testing &; overview of liquid penetrant test
L1 ndt versus mechanical testing &; overview of liquid penetrant test
 
Building Materials Testing - Exclusive Services for Infrastructure / Civil Se...
Building Materials Testing - Exclusive Services for Infrastructure / Civil Se...Building Materials Testing - Exclusive Services for Infrastructure / Civil Se...
Building Materials Testing - Exclusive Services for Infrastructure / Civil Se...
 
phosphate coating on alloys
phosphate coating on alloysphosphate coating on alloys
phosphate coating on alloys
 
2014 Poster_3_6
2014 Poster_3_62014 Poster_3_6
2014 Poster_3_6
 
Zircon Filters Data Sheet
Zircon Filters Data SheetZircon Filters Data Sheet
Zircon Filters Data Sheet
 
experimental study on concrete using micro silica and nano silica
experimental study on concrete using micro silica and nano silicaexperimental study on concrete using micro silica and nano silica
experimental study on concrete using micro silica and nano silica
 
Nano Technology & Nano Materials
Nano Technology & Nano MaterialsNano Technology & Nano Materials
Nano Technology & Nano Materials
 
2015 nurulainul sls mussel
2015 nurulainul sls mussel2015 nurulainul sls mussel
2015 nurulainul sls mussel
 
Both 2016 shanghai development of innovative ultra high temperature coatings ...
Both 2016 shanghai development of innovative ultra high temperature coatings ...Both 2016 shanghai development of innovative ultra high temperature coatings ...
Both 2016 shanghai development of innovative ultra high temperature coatings ...
 
Nano Concrete
Nano ConcreteNano Concrete
Nano Concrete
 
Presentation on Air Heater Inspection
Presentation on Air Heater Inspection Presentation on Air Heater Inspection
Presentation on Air Heater Inspection
 
Introduction to linings
Introduction to liningsIntroduction to linings
Introduction to linings
 
internship report PCSIR
internship report PCSIRinternship report PCSIR
internship report PCSIR
 
Efficient growth techniques and properties of Benzophenone Single Crystals fo...
Efficient growth techniques and properties of Benzophenone Single Crystals fo...Efficient growth techniques and properties of Benzophenone Single Crystals fo...
Efficient growth techniques and properties of Benzophenone Single Crystals fo...
 
Design corrosion
Design   corrosion Design   corrosion
Design corrosion
 

Similar to Phosphate Pretreatment Contaminant Reduction

Analysis and quantification of grain size in various dhp copper tubes manufac...
Analysis and quantification of grain size in various dhp copper tubes manufac...Analysis and quantification of grain size in various dhp copper tubes manufac...
Analysis and quantification of grain size in various dhp copper tubes manufac...Rautomead Limited
 
Final project ppt
Final project pptFinal project ppt
Final project pptAkhil Vas
 
32 field test at maine yankee independent spent fuel storage instillation gor...
32 field test at maine yankee independent spent fuel storage instillation gor...32 field test at maine yankee independent spent fuel storage instillation gor...
32 field test at maine yankee independent spent fuel storage instillation gor...leann_mays
 
RAPID TOOLING.pptx
RAPID TOOLING.pptxRAPID TOOLING.pptx
RAPID TOOLING.pptxjntuhcej
 
Investing and casting
Investing and castingInvesting and casting
Investing and castinghesham1964
 
Investing and casting
Investing and castingInvesting and casting
Investing and castinghesham1964
 
Microbial Fuel Cell Project
Microbial Fuel Cell ProjectMicrobial Fuel Cell Project
Microbial Fuel Cell ProjectKatherine Knight
 
Industrial training in Hi-Tech Castings & ANSYS Software Training
Industrial training in Hi-Tech Castings & ANSYS Software TrainingIndustrial training in Hi-Tech Castings & ANSYS Software Training
Industrial training in Hi-Tech Castings & ANSYS Software TrainingJASTINDER PAL SINGH
 
Noise Reduction for Internal Combustion Engines
 Noise Reduction for Internal Combustion Engines Noise Reduction for Internal Combustion Engines
Noise Reduction for Internal Combustion EnginesJauwadSyed
 
Sand casting
Sand castingSand casting
Sand castingSp Patel
 
RECOVERY OF METALS FROM ELECTRONIC WASTE (e-scrap).
RECOVERY OF METALS FROM ELECTRONIC WASTE (e-scrap).RECOVERY OF METALS FROM ELECTRONIC WASTE (e-scrap).
RECOVERY OF METALS FROM ELECTRONIC WASTE (e-scrap).suzi smith
 
Horizon 2020
Horizon 2020Horizon 2020
Horizon 2020Pomcert
 
Horizon 2020
Horizon 2020Horizon 2020
Horizon 2020Pomcert
 
PROC 2076 Assignment Report, Pipeline
PROC 2076 Assignment Report, PipelinePROC 2076 Assignment Report, Pipeline
PROC 2076 Assignment Report, PipelineSyafiq Dan
 
Strengthening of concrete columns made from recycled concrete aggregate
Strengthening of concrete columns made from recycled concrete aggregateStrengthening of concrete columns made from recycled concrete aggregate
Strengthening of concrete columns made from recycled concrete aggregatenada khaled
 
Metal casting Process
Metal casting ProcessMetal casting Process
Metal casting Processlaxtwinsme
 
Wetland methane flux chamber
Wetland methane flux chamberWetland methane flux chamber
Wetland methane flux chamberAlecPopichak
 

Similar to Phosphate Pretreatment Contaminant Reduction (20)

Seminor report
Seminor reportSeminor report
Seminor report
 
Analysis and quantification of grain size in various dhp copper tubes manufac...
Analysis and quantification of grain size in various dhp copper tubes manufac...Analysis and quantification of grain size in various dhp copper tubes manufac...
Analysis and quantification of grain size in various dhp copper tubes manufac...
 
Final project ppt
Final project pptFinal project ppt
Final project ppt
 
32 field test at maine yankee independent spent fuel storage instillation gor...
32 field test at maine yankee independent spent fuel storage instillation gor...32 field test at maine yankee independent spent fuel storage instillation gor...
32 field test at maine yankee independent spent fuel storage instillation gor...
 
RAPID TOOLING.pptx
RAPID TOOLING.pptxRAPID TOOLING.pptx
RAPID TOOLING.pptx
 
Investing and casting
Investing and castingInvesting and casting
Investing and casting
 
Investing and casting
Investing and castingInvesting and casting
Investing and casting
 
Microbial Fuel Cell Project
Microbial Fuel Cell ProjectMicrobial Fuel Cell Project
Microbial Fuel Cell Project
 
Industrial training in Hi-Tech Castings & ANSYS Software Training
Industrial training in Hi-Tech Castings & ANSYS Software TrainingIndustrial training in Hi-Tech Castings & ANSYS Software Training
Industrial training in Hi-Tech Castings & ANSYS Software Training
 
Noise Reduction for Internal Combustion Engines
 Noise Reduction for Internal Combustion Engines Noise Reduction for Internal Combustion Engines
Noise Reduction for Internal Combustion Engines
 
Mfg lab manual
Mfg lab manualMfg lab manual
Mfg lab manual
 
Sand casting
Sand castingSand casting
Sand casting
 
Biodegradation of nickel
Biodegradation of nickelBiodegradation of nickel
Biodegradation of nickel
 
RECOVERY OF METALS FROM ELECTRONIC WASTE (e-scrap).
RECOVERY OF METALS FROM ELECTRONIC WASTE (e-scrap).RECOVERY OF METALS FROM ELECTRONIC WASTE (e-scrap).
RECOVERY OF METALS FROM ELECTRONIC WASTE (e-scrap).
 
Horizon 2020
Horizon 2020Horizon 2020
Horizon 2020
 
Horizon 2020
Horizon 2020Horizon 2020
Horizon 2020
 
PROC 2076 Assignment Report, Pipeline
PROC 2076 Assignment Report, PipelinePROC 2076 Assignment Report, Pipeline
PROC 2076 Assignment Report, Pipeline
 
Strengthening of concrete columns made from recycled concrete aggregate
Strengthening of concrete columns made from recycled concrete aggregateStrengthening of concrete columns made from recycled concrete aggregate
Strengthening of concrete columns made from recycled concrete aggregate
 
Metal casting Process
Metal casting ProcessMetal casting Process
Metal casting Process
 
Wetland methane flux chamber
Wetland methane flux chamberWetland methane flux chamber
Wetland methane flux chamber
 

Phosphate Pretreatment Contaminant Reduction

  • 1. Contaminant Reduction- Phosphate Pretreatment Wrangler Paint- Maintenance Supervisor: Ryan Vicroy Justin Stevenor The University of Toledo Summer 2016
  • 2. Problem + Goals for Project Problem- 1. Metal contaminate in paint shop pretreatment process that comes from the body shop. 2. Metal contaminates in the phosphate tanks can causes metal to deposit on the hood and the entire body. Goals for Summer Project- 1. Reduce the amount of metal debris in the phosphate process to improve quality of units produced. 2. Implement a best practice as identified by FCA manufacturing engineering group for phosphate. 3. Design and install the most effective device for collecting metal debris. 4. Install the magnet capsules during the week of summer shut down (July 16th). 5. Implement best practice as a cost reduction compared to Jefferson North Assembly Plant.
  • 3. Pre-Design Consideration #1 Consideration #1 - 1. Easiness of cleaning and maintenance (Time) NOK OK Bare Magnet Housing Barrier
  • 4. Testing Metal vs. PVC Housing 1. Now that housing was in mind for the project I had to decide if the magnets should be placed into metal or PVC tubing. • Initially it was thought that metal tubing would be the best choice because the magnets would turn the metal tubing into one large magnet. • The magnets were placed in both, PVC and steel, and the PVC had the largest pull. Metal housing attracts metal at 1.5” PVC housing attracts metal at 3” Metal vs. PVC NOK OK
  • 5. Major Consideration- Method of Cleaning 1. Cleaning was a major thought when designing the magnet prototype. The time needed to clean the design and return the design back into the system is important along with the amount of material removed. 2. There are three methods considered for cleaning- a. Metal or plastic tube that covers the magnets and another tube that is larger in diameter to swipe down to remove material. b. Bag over the magnets and remove the bag and replace with a new bag each time. c. Metal or plastic tube that covers the magnets and just a swipe is needed for cleaning. NOK NOK OK Method C
  • 6. Pre-Design Consideration #2 Consideration #2 - 1. Maximize the gauze of the rare earth magnets (Gauze) Vertical Distance 3”Horizontal Distance 1.5” NOK OK
  • 7. Major Consideration- Maximizing Gauze Time (Hours) Vertical Horizontal Percent Increase 1 10.2 16.8 64.7% 2 17.4 22.5 29.3% 4 28.4 36.3 27.8% 6 32.5 40.1 23.4% 8 35.7 43.3 21.3% • To maximize the gauze of the magnets I changed the orientation of the magnets from horizontal to vertical. • This minor change can collect on average 33.3% more metal debris from the phosphate tanks. 0 5 10 15 20 25 30 35 40 45 50 1 2 3 4 5 GramsofMaterialRemoved Time (Hours) Maximizing Gauze
  • 8. Prototypes #1-7 Overview Prototype # Design Description Performance (Material Removed) Cost Analysis 1 Pendal-PVC Housing (Phosphate Bath) 0 grams $26.35 2 Pendal – Threaded Rod (Phosphate Bath) 0 grams $25.56 3 Bag- Threated Rod (Stage 0) Bag Failure - 0 grams $46.10 4 Threaded Rod- PVC Housing (Stage 0) 35.7 grams $48.24 5 PVC Housing- Magnet Orientation Rotated 90° (Stage 0) 43.3 grams $43.70 6 Square Flat Housing (Basket Strainer) Not Water Tight- 0 grams $6.34 7 PVC Housing – Magnet Orientation Rotated 90° (Basket Strainer) 28.4 grams $25.30 Prototype #1 Prototype #7
  • 9. Selecting the Most Effective Design Material Removed (Grams- 8Hours) N/A N/A N/A 35.7 43.3 N/A 20.1 Cost $26.35 $25.56 $46.10 $48.24 $43.70 $6.34 $25.30 Prototype # 1 2 3 4 5 6 7 • Prototype #5 and #7 were chosen to more forward to mass produce during shut down because of there results. • Prototype #5 produced the most amount of material removed from the phosphate system through the tanks (43.3 grams) • Prototype #7 was selected because prototype 5 was not appropriate for basket strainers. #5 #7 OK OK Material removed + $$$
  • 10. Locations Deployed 1. Pendal 2. Tanks 3. Basket Strainer NOK OK OK
  • 11. Cost to Build • The cost for the 12 capsules in phosphate is a total of $2,653.75 • These are the materials used to build the selected design 1. Stainless steel all thread (1/2”) 2. Stainless steel washers and nuts (1/2”) 3. Newspaper bags (21”long x 7-1/2” wide) 4. Rare earth magnets- Neodymium ring magnets N42(1.5” Diameter) 5. PVC tubing (1 ½” schedule 40) 6. PVC end caps (1 ½“) 7. PVC reducer cap (1 ½” to ½“) Cost Comparison: Toledo North Assembly- $2,654 Jefferson North Assembly- $250,000
  • 12. Benefit of the Phosphate Install With the install of the 12 capsules in phosphate the magnets will pull out 447.5 grams each day from the tanks and basket strainers. 447.5 Grams = 1 Pound of Metal/day 1 Lb/day X 300 running days = 300 Pounds/Year
  • 13. Magnet Design Overview- Phosphate Pretreatment Prototypes that produced results (#4,5,7) were selected to move forward. Install device #5 + #7 during summer shutdown week (installation: July 18th-22nd) OK NOK OK Mass produced the selected prototypes. Systematic Diagram Prototype #2 Prototype #1 NOK Prototype #3 Prototype #4 Prototype #5 Prototype #6 Prototype #7 NOK NOK OK Prototypes #5 + #7 produce the best results when considering cleaning and material collected.