SlideShare uma empresa Scribd logo
1 de 2
To: Trena Houp, English Professor at the University of Florida
From: Jessica Eagerton, Student
Date: August 8, 2014
Subject: Ethical Failings From the Hyatt Regency Hotel Collapse
The purpose of this memo is to inform you about the negligence and lack of ethical
responsibility that injured more than 200 people cost 114 people’s lives on July 17,1981.
The atrium ceiling collapse at the Hyatt Regency in Kanas City revealed a number of
unethical practices. Due to poor technical documentation and lack of professionalism in
the business place, hotel owner, Crown Center Redevelopment Corporation, and its hired
engineering firm are held accountable for this catastrophe. It is unfortunate that simply
acting ethically could have prevented this situation.
Unethical Practices from the Engineering Firm
The liability in this case falls on the engineering firm hired by the hotel owners to
reconstruct the atrium ceiling following its original collapse. After assessing what caused
the original constructional failure, the engineering firm found no structural flaws in the
design or the roof construction. However, after the tragedy that occurred that night and a
number of legal cases, a trial revealed that the engineer had not:
 Examined the new connection (steel-to-steel concrete connectors)
 Calculated the safety and load capacity of the new connections
I am compelled to express concern about how the documentation was handled during the
time of construction. The National Bureau of Standards, which investigated the accident,
found that the building was not properly constructed, used incorrect rod measurements
and did not meet building code regulations. In this case, the accident could have been
avoided if the engineer had used the preliminary documentation, which had the precise
and accurate information for the design of the ceiling. Another mishap that could have
helped prevent this ethical dilemma was the lack of documentation for the final
construction, which exposed the inadequate planning on the engineer’s behalf.
Unethical Practices from Crown Center Redevelopment Corporation
Ethical concerns after the incident also raised questions against the hotel owner. Rather
than addressing the situation in an open manner, the company chose to act secretively by
delaying external investigations. Crown Center’s conduct was also called upon during the
investigation when records from the Occupational Safety and Health Administration were
uncovered. These records showed that during construction a large section of the lobby
roof had caved in. However, these records were only found because inspectors were at
the site looking at an unrelated accident.
A Plan for the Future
The absence and disregard to professionalism and ethics in this case cost people their
lives and those who survived a horrifying memory never to be forgotten. It is my
recommendation that technical documentation is never to be skipped over and/ or kept
hidden.
Memo ENC

Mais conteúdo relacionado

Mais procurados

Teesing market flyer medical sector
Teesing market flyer medical sectorTeesing market flyer medical sector
Teesing market flyer medical sectorTeesing BV
 
OSHA record keeping update
OSHA record keeping  updateOSHA record keeping  update
OSHA record keeping updatevtsiri
 
Octavia Newton Resume 2016
Octavia Newton Resume 2016Octavia Newton Resume 2016
Octavia Newton Resume 2016Octavia Newton
 
Phase ii site assessments
Phase ii site assessmentsPhase ii site assessments
Phase ii site assessmentsfrenviro
 
Abdumalik Muse Pf Resume
Abdumalik Muse Pf Resume Abdumalik Muse Pf Resume
Abdumalik Muse Pf Resume Garaad M.
 
Eric-Nelson-Zugner-resume
Eric-Nelson-Zugner-resumeEric-Nelson-Zugner-resume
Eric-Nelson-Zugner-resumeEric Zugner
 
A balanced outlook on the law
A balanced outlook on  the lawA balanced outlook on  the law
A balanced outlook on the lawSKS
 

Mais procurados (8)

Teesing market flyer medical sector
Teesing market flyer medical sectorTeesing market flyer medical sector
Teesing market flyer medical sector
 
OSHA record keeping update
OSHA record keeping  updateOSHA record keeping  update
OSHA record keeping update
 
Octavia Newton Resume 2016
Octavia Newton Resume 2016Octavia Newton Resume 2016
Octavia Newton Resume 2016
 
Phase ii site assessments
Phase ii site assessmentsPhase ii site assessments
Phase ii site assessments
 
Abdumalik Muse Pf Resume
Abdumalik Muse Pf Resume Abdumalik Muse Pf Resume
Abdumalik Muse Pf Resume
 
Missouri S&T innovation Park
Missouri S&T innovation ParkMissouri S&T innovation Park
Missouri S&T innovation Park
 
Eric-Nelson-Zugner-resume
Eric-Nelson-Zugner-resumeEric-Nelson-Zugner-resume
Eric-Nelson-Zugner-resume
 
A balanced outlook on the law
A balanced outlook on  the lawA balanced outlook on  the law
A balanced outlook on the law
 

Destaque

Piezo electric effect & its applications.
Piezo electric effect & its applications.Piezo electric effect & its applications.
Piezo electric effect & its applications.The_Traveller
 
Historical monograph
Historical monographHistorical monograph
Historical monographashleighalece
 
조연심 온오프라인개인브랜드성공전략
조연심 온오프라인개인브랜드성공전략조연심 온오프라인개인브랜드성공전략
조연심 온오프라인개인브랜드성공전략JUNGEUN KANG
 
Lesson 07 Qualities of Christ
Lesson 07 Qualities of ChristLesson 07 Qualities of Christ
Lesson 07 Qualities of ChristMarvin McKenzie
 
Número de empresas com contas em atraso cresce 7,46% em abril
Número de empresas com contas em atraso cresce 7,46% em abrilNúmero de empresas com contas em atraso cresce 7,46% em abril
Número de empresas com contas em atraso cresce 7,46% em abrilSPC Brasil
 
Indian Writing in English
Indian Writing in EnglishIndian Writing in English
Indian Writing in Englishdavemayuri18
 
Syllabus informatica-i 2015-may-11
Syllabus informatica-i 2015-may-11Syllabus informatica-i 2015-may-11
Syllabus informatica-i 2015-may-11zarayesteban
 
UXPA 10 minute talk on shaping organizations
UXPA   10 minute talk on shaping organizations UXPA   10 minute talk on shaping organizations
UXPA 10 minute talk on shaping organizations Gregory Raiz
 
Newgen Business Partner Presentation
Newgen Business Partner PresentationNewgen Business Partner Presentation
Newgen Business Partner PresentationAjendra Mishra
 
Space systems engineering proexia
Space systems engineering proexiaSpace systems engineering proexia
Space systems engineering proexiaCONALEP 177
 
Final Foundation Portfolio Vasilis Ryziotis [A4] - http://vasileiosrs.wixsite...
Final Foundation Portfolio Vasilis Ryziotis [A4] - http://vasileiosrs.wixsite...Final Foundation Portfolio Vasilis Ryziotis [A4] - http://vasileiosrs.wixsite...
Final Foundation Portfolio Vasilis Ryziotis [A4] - http://vasileiosrs.wixsite...Vasileios Rs
 
486 qualitative disorders of wbc
486 qualitative disorders of wbc486 qualitative disorders of wbc
486 qualitative disorders of wbcNabin Chaudhary
 

Destaque (19)

Piezo electric effect & its applications.
Piezo electric effect & its applications.Piezo electric effect & its applications.
Piezo electric effect & its applications.
 
ISBI_poster
ISBI_posterISBI_poster
ISBI_poster
 
Natalys resume 2
Natalys resume 2Natalys resume 2
Natalys resume 2
 
Historical monograph
Historical monographHistorical monograph
Historical monograph
 
Kurt Catalog 2014
Kurt Catalog 2014Kurt Catalog 2014
Kurt Catalog 2014
 
조연심 온오프라인개인브랜드성공전략
조연심 온오프라인개인브랜드성공전략조연심 온오프라인개인브랜드성공전략
조연심 온오프라인개인브랜드성공전략
 
Lesson 07 Qualities of Christ
Lesson 07 Qualities of ChristLesson 07 Qualities of Christ
Lesson 07 Qualities of Christ
 
Número de empresas com contas em atraso cresce 7,46% em abril
Número de empresas com contas em atraso cresce 7,46% em abrilNúmero de empresas com contas em atraso cresce 7,46% em abril
Número de empresas com contas em atraso cresce 7,46% em abril
 
Curso taller lectura b
Curso taller lectura bCurso taller lectura b
Curso taller lectura b
 
Indian Writing in English
Indian Writing in EnglishIndian Writing in English
Indian Writing in English
 
Syllabus informatica-i 2015-may-11
Syllabus informatica-i 2015-may-11Syllabus informatica-i 2015-may-11
Syllabus informatica-i 2015-may-11
 
Economia2 (1)
Economia2 (1)Economia2 (1)
Economia2 (1)
 
UXPA 10 minute talk on shaping organizations
UXPA   10 minute talk on shaping organizations UXPA   10 minute talk on shaping organizations
UXPA 10 minute talk on shaping organizations
 
Newgen Business Partner Presentation
Newgen Business Partner PresentationNewgen Business Partner Presentation
Newgen Business Partner Presentation
 
Space systems engineering proexia
Space systems engineering proexiaSpace systems engineering proexia
Space systems engineering proexia
 
Final Foundation Portfolio Vasilis Ryziotis [A4] - http://vasileiosrs.wixsite...
Final Foundation Portfolio Vasilis Ryziotis [A4] - http://vasileiosrs.wixsite...Final Foundation Portfolio Vasilis Ryziotis [A4] - http://vasileiosrs.wixsite...
Final Foundation Portfolio Vasilis Ryziotis [A4] - http://vasileiosrs.wixsite...
 
Aa2 u1 arte antiguo
Aa2 u1 arte antiguoAa2 u1 arte antiguo
Aa2 u1 arte antiguo
 
486 qualitative disorders of wbc
486 qualitative disorders of wbc486 qualitative disorders of wbc
486 qualitative disorders of wbc
 
transferencia de calor 2
transferencia de calor 2transferencia de calor 2
transferencia de calor 2
 

Semelhante a Memo ENC

2011 Plc Introductory Client Presentation Final
2011 Plc Introductory Client Presentation Final2011 Plc Introductory Client Presentation Final
2011 Plc Introductory Client Presentation Finallennyalexander
 
Ethics in engineering profession kamal25
Ethics in engineering profession kamal25Ethics in engineering profession kamal25
Ethics in engineering profession kamal25Kamal Shahi
 
Example Ethics Case Solutions USE OF ALLEGED HAZARDOUS MAT.docx
Example Ethics Case Solutions USE OF ALLEGED HAZARDOUS MAT.docxExample Ethics Case Solutions USE OF ALLEGED HAZARDOUS MAT.docx
Example Ethics Case Solutions USE OF ALLEGED HAZARDOUS MAT.docxSANSKAR20
 
Capital Needs Assessment Example
Capital Needs Assessment ExampleCapital Needs Assessment Example
Capital Needs Assessment ExampleAdam Hoeksema
 
Engineering ethics & cases
Engineering ethics & casesEngineering ethics & cases
Engineering ethics & casesMugiwaraL
 
2010 Commissioning Of Bldg Fp Systems
2010 Commissioning Of Bldg Fp Systems2010 Commissioning Of Bldg Fp Systems
2010 Commissioning Of Bldg Fp Systemsandrewwcwong
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1Dan Caouette
 
ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2
ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2
ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2Anne Arundel Community College
 
ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2
ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2
ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2Anne Arundel Community College
 
Benefits of Mathematical Simulation
Benefits of Mathematical SimulationBenefits of Mathematical Simulation
Benefits of Mathematical SimulationBill ODonnell
 
Introduction to Engineering Ethics.pdf
Introduction to Engineering Ethics.pdfIntroduction to Engineering Ethics.pdf
Introduction to Engineering Ethics.pdfSaraMFaustin
 
Engineering Ethics: The Essence of Engineering Excellence | IEB 2019
Engineering Ethics: The Essence of Engineering Excellence | IEB 2019Engineering Ethics: The Essence of Engineering Excellence | IEB 2019
Engineering Ethics: The Essence of Engineering Excellence | IEB 2019Abdullah Al Moinee
 
ENGINEERING_ETHICS_CASE_STUDIES.pdf
ENGINEERING_ETHICS_CASE_STUDIES.pdfENGINEERING_ETHICS_CASE_STUDIES.pdf
ENGINEERING_ETHICS_CASE_STUDIES.pdfEmiNaito
 
Workplace Injuries and Fatalities | Bryson
Workplace Injuries and Fatalities | BrysonWorkplace Injuries and Fatalities | Bryson
Workplace Injuries and Fatalities | BrysonSatcy_Robinson
 
Mead Technical Paper_Oregon State
Mead Technical Paper_Oregon StateMead Technical Paper_Oregon State
Mead Technical Paper_Oregon StateJames Desmond
 
Michael Newman presentation
Michael Newman presentationMichael Newman presentation
Michael Newman presentationkeenwell
 
LitigationSupport 11
LitigationSupport 11LitigationSupport 11
LitigationSupport 11Clare Koehler
 

Semelhante a Memo ENC (20)

2011 Plc Introductory Client Presentation Final
2011 Plc Introductory Client Presentation Final2011 Plc Introductory Client Presentation Final
2011 Plc Introductory Client Presentation Final
 
Ethics in engineering profession kamal25
Ethics in engineering profession kamal25Ethics in engineering profession kamal25
Ethics in engineering profession kamal25
 
Example Ethics Case Solutions USE OF ALLEGED HAZARDOUS MAT.docx
Example Ethics Case Solutions USE OF ALLEGED HAZARDOUS MAT.docxExample Ethics Case Solutions USE OF ALLEGED HAZARDOUS MAT.docx
Example Ethics Case Solutions USE OF ALLEGED HAZARDOUS MAT.docx
 
Capital Needs Assessment Example
Capital Needs Assessment ExampleCapital Needs Assessment Example
Capital Needs Assessment Example
 
Engineering ethics & cases
Engineering ethics & casesEngineering ethics & cases
Engineering ethics & cases
 
2010 Commissioning Of Bldg Fp Systems
2010 Commissioning Of Bldg Fp Systems2010 Commissioning Of Bldg Fp Systems
2010 Commissioning Of Bldg Fp Systems
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1
 
ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2
ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2
ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2
 
ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2
ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2
ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2
 
Benefits of Mathematical Simulation
Benefits of Mathematical SimulationBenefits of Mathematical Simulation
Benefits of Mathematical Simulation
 
Introduction to Engineering Ethics.pdf
Introduction to Engineering Ethics.pdfIntroduction to Engineering Ethics.pdf
Introduction to Engineering Ethics.pdf
 
Engineering Ethics: The Essence of Engineering Excellence | IEB 2019
Engineering Ethics: The Essence of Engineering Excellence | IEB 2019Engineering Ethics: The Essence of Engineering Excellence | IEB 2019
Engineering Ethics: The Essence of Engineering Excellence | IEB 2019
 
Presentation10.pptx
Presentation10.pptxPresentation10.pptx
Presentation10.pptx
 
ENGINEERING_ETHICS_CASE_STUDIES.pdf
ENGINEERING_ETHICS_CASE_STUDIES.pdfENGINEERING_ETHICS_CASE_STUDIES.pdf
ENGINEERING_ETHICS_CASE_STUDIES.pdf
 
Workplace Injuries and Fatalities | Bryson
Workplace Injuries and Fatalities | BrysonWorkplace Injuries and Fatalities | Bryson
Workplace Injuries and Fatalities | Bryson
 
CIB Publication 405
CIB Publication 405CIB Publication 405
CIB Publication 405
 
Case Study - SE University
Case Study - SE UniversityCase Study - SE University
Case Study - SE University
 
Mead Technical Paper_Oregon State
Mead Technical Paper_Oregon StateMead Technical Paper_Oregon State
Mead Technical Paper_Oregon State
 
Michael Newman presentation
Michael Newman presentationMichael Newman presentation
Michael Newman presentation
 
LitigationSupport 11
LitigationSupport 11LitigationSupport 11
LitigationSupport 11
 

Memo ENC

  • 1. To: Trena Houp, English Professor at the University of Florida From: Jessica Eagerton, Student Date: August 8, 2014 Subject: Ethical Failings From the Hyatt Regency Hotel Collapse The purpose of this memo is to inform you about the negligence and lack of ethical responsibility that injured more than 200 people cost 114 people’s lives on July 17,1981. The atrium ceiling collapse at the Hyatt Regency in Kanas City revealed a number of unethical practices. Due to poor technical documentation and lack of professionalism in the business place, hotel owner, Crown Center Redevelopment Corporation, and its hired engineering firm are held accountable for this catastrophe. It is unfortunate that simply acting ethically could have prevented this situation. Unethical Practices from the Engineering Firm The liability in this case falls on the engineering firm hired by the hotel owners to reconstruct the atrium ceiling following its original collapse. After assessing what caused the original constructional failure, the engineering firm found no structural flaws in the design or the roof construction. However, after the tragedy that occurred that night and a number of legal cases, a trial revealed that the engineer had not:  Examined the new connection (steel-to-steel concrete connectors)  Calculated the safety and load capacity of the new connections I am compelled to express concern about how the documentation was handled during the time of construction. The National Bureau of Standards, which investigated the accident, found that the building was not properly constructed, used incorrect rod measurements and did not meet building code regulations. In this case, the accident could have been avoided if the engineer had used the preliminary documentation, which had the precise and accurate information for the design of the ceiling. Another mishap that could have helped prevent this ethical dilemma was the lack of documentation for the final construction, which exposed the inadequate planning on the engineer’s behalf. Unethical Practices from Crown Center Redevelopment Corporation Ethical concerns after the incident also raised questions against the hotel owner. Rather than addressing the situation in an open manner, the company chose to act secretively by delaying external investigations. Crown Center’s conduct was also called upon during the investigation when records from the Occupational Safety and Health Administration were uncovered. These records showed that during construction a large section of the lobby roof had caved in. However, these records were only found because inspectors were at the site looking at an unrelated accident. A Plan for the Future The absence and disregard to professionalism and ethics in this case cost people their lives and those who survived a horrifying memory never to be forgotten. It is my recommendation that technical documentation is never to be skipped over and/ or kept hidden.