SlideShare uma empresa Scribd logo
1 de 57
Baixar para ler offline
PL Safety and Essentials of Risk Assessment

Following the Essential Elements
Background




© Det Norske Veritas AS. All rights reserved.   2
© Det Norske Veritas AS. All rights reserved.
Kalamazoo River, 2010




                                                                   10ft creek

                                                   CoF: $1B
                                                   PoF: 1/1000yr

                                                   Expected Loss: $1M/yr for
                                                   ~3m of pipeline!


                            $1,000,000,000 spent

© Det Norske Veritas AS. All rights reserved.
Reality Check
                 RM is not new; requires RA
                 Risk-based decision-making is complex
                    - Because the real world is complex, measuring risk is
                      complex
                    - RM is even more complex than RA

                 Dealing with the complexity is worthwhile
                    -    increases understanding
                    -    shows full range of options; many opportunities to impact risk
                    -    cheaper than prescriptive ‘solutions’
                    -    Improves decision-making
                    -    the key to improving PL safety



© Det Norske Veritas AS. All rights reserved.
Reality Check, Part Two


                If you put tomfoolery into a computer, nothing comes out
                  of it but tomfoolery. But this tomfoolery, having passed
                  through a very expensive machine, is somehow
                  ennobled and no-one dares criticize it.
                   - Pierre Gallois




                                                The Illusion of Knowledge




© Det Norske Veritas AS. All rights reserved.
How good is PL RA now?


 Pockets of strengths
 But
 Weaknesses are apparent
      -   A complicated topic--incomplete understanding is common
      -   Lack of standardized RA approaches
      -   Errors in some industry standards
      -   New demands by regulators and other stakeholders
      -   Myths and misconceptions




© Det Norske Veritas AS. All rights reserved.   7
PL Risk Modeling Confusion

                                                ASME B31.8s
                                                •Subject Matter Experts
                     Qualitative
                                                •Relative Assessments
                     Quantitative
                                                •Scenario Assessments
                     Semi-quantitative
                                                •Probabilistic Assessments
                     Probabilistic
                     Deterministic




© Det Norske Veritas AS. All rights reserved.
Regulations: IMP Objectives vs RA Techniques
          Objectives
       (a) prioritization of pipelines/segments for scheduling integrity assessments and mitigating action
       (b) assessment of the benefits derived from mitigating action
       (c) determination of the most effective mitigation measures for the identified threats
       (d) assessment of the integrity impact from modified inspection intervals
       (e) assessment of the use of or need for alternative inspection methodologies
       (f) more effective resource allocation
                                                                                        Techniques
                                                                                   •   Subject Matter Experts
                                                                                   •   Relative Assessments
                                                                                   •   Scenario Assessments
                                                                                   •   Probabilistic
                                                                                       Assessments
          Numbers Needed
             •Failure rate estimates for each threat on each PL segment
             •Mitigation effectiveness for each contemplated measure
             •Time to Failure (TTF) estimates (time-dep threats)

© Det Norske Veritas AS. All rights reserved.
“Threat Interaction” Confusion
  Time Dependent Threats                             Stable Threats Potential Weaknesses
      - Corrosion                                     Manufacturing-related flaws in
          - External
                                                       - Pipe body
          - Internal
                                                       - Pipe seam
      - Cracking
          - Fatigue                                   Welding / Fabrication-caused flaws in
          - EAC                                        -   Girth welds
                                                       -   Fabrication welds
  Time Independent Threats                            -   Wrinkled / buckled bend
      -   Third party                                  -   Threads / couplings
      -   Geohazards                                  Defects present in equipment
      -   Incorrect operations                         -   Gaskets, O-rings
      -   Sabotage                                     -   Control / relief devices
                                                       -   Seals, packing
                                                       -   Other equipment




© Det Norske Veritas AS. All rights reserved.   10
Myths: Data Availability vs Modeling Rigor
 Myth:
  Some RA models are better able to accommodate low data availability


 Reality:
  Strong data + strong model = accurate results
  Weak data + strong model = uncertain results
  Weak data + weak model = meaningless results




                                                                         11
© Det Norske Veritas AS. All rights reserved.
Myth: QRA / PRA Requirements
 Myth:
  QRA requires vast amounts of incident histories


 Reality:
  QRA ‘requires’ no more data than other techniques
  All assessments work better with better information


  Footnotes:
      - Some classical QRA does over-emphasize history
      - Excessive reliance on history is an error in any methodology




                                                                       12
© Det Norske Veritas AS. All rights reserved.
© Det Norske Veritas AS. All rights reserved.
© Det Norske Veritas AS. All rights reserved.
© Det Norske Veritas AS. All rights reserved.
Removing the Weaknesses—The New Look of PL RA


                              PoF (len adjusted)

                        140

                        120

                        100
            Frequency




                        80

                        60                                                        PoF (unitized)

                        40                            12.0%

                        20                            10.0%

                                                      8.0%
                         0
                                                      6.0%
                        0. 0 1
                        0. 01
                        0. 04

                         0. 7


                        0. 13
                        0. 16
                        0. 19
                        0. 22
                        0. 25
                        0. 28

                                 1
                                e
                             00




                             03

                              or
                            00
                             0
                             0




                             0
                             0
                             0
                             0
                             0
                             0


                            M
                           00
                           00
                           00


                           00
                           00
                           00
                           00
                           00
                           00
                           00




                                                      4.0%
                        0.




                                                Bin   2.0%

                                                      0.0%
                                                              0   20000   40000   60000             80000   100000   120000   140000
                                                                                          station




© Det Norske Veritas AS. All rights reserved.
Essential Elements




© Det Norske Veritas AS. All rights reserved.   17
Essential Elements
  The Essential Elements are meant to
      - Minimize the weaknesses in current PL RA practice
      - Be common sense ingredients that make risk assessment meaningful, objective, and
        acceptable to all stakeholders
      - Be concise yet flexible, allowing tailored solutions to situation-specific concerns
      - Lead to smarter risk assessment


  The elements are meant to supplement, not replace, guidance, recommended
   practice, and regulations already in place




© Det Norske Veritas AS. All rights reserved.     18
The Essential Elements
                                                    Measurements in Verifiable Units


                                                 Proper Probability of Failure Assessment


                                                Characterization of Potential Consequences


                                                  Full Integration of Pipeline Knowledge


                                                          Sufficient Granularity


                                                            Bias Management


                                                             Profiles of Risk


                                                           Proper Aggregation


© Det Norske Veritas AS. All rights reserved.                                   19
Measure in Verifiable Units
                                    Probability of
        Measure in                                        Fully
                                       Failure                         Integrate     Incorporate
                                                      Characterize                                                     Profile the Risk    Unmask
         Verifiable                 Grounded in
                                                     Consequence of
                                                                        Pipeline      Sufficient    Control the Bias
                                                                                                                                          Aggregation
                                    Engineering                       Knowledge       Granularity                          Reality
           Units                                         Failure
                                     Principles




            Must include a definition of “Failure”
            Must produce verifiable estimates of PoF and CoF in
             commonly used measurement units
            PoF must capture effects of length and time
            Must be free from intermediate schemes (scoring, point
             assignments, etc)
                                                                                   “Measure in verifiable units” keeps the
                                                                                   process transparent by expressing risk
                                                                                   elements in understandable terms that
                                                                                        can be calibrated to reality


© Det Norske Veritas AS. All rights reserved.
Measure in
                                                                                 Verifiable
                                                                                   Units

 Risk Estimates as Measurements


         Risk = Frequency of consequence
              - Temporally
              - Spatially
                                                       TTF = time to failure
                         •Incidents per mile-year      remaining life estimates in
                                                       years
                         •fatalities per mile-year

                         •dollars per km-decade

                                 conseq         prob




© Det Norske Veritas AS. All rights reserved.
Measure in
                                                             Verifiable
                                                               Units

 Why measurements instead of scores?

           Direct measurements are efficient
            - Less subjective
            - Anchored in ‘real world’, able to capture real world
              phenomena
            - Defensible, auditable, transparent
            - Avoids need for standardization
            - Avoids erosion of score definitions
            - Allows calculation of costs and benefits
            - Supports better decisions

© Det Norske Veritas AS. All rights reserved.
Probability of Failure Grounded in Engineering Principles
                                    Probability of
        Measure in                                        Fully
                                       Failure                         Integrate   Incorporate
                                                      Characterize                                                   Profile the Risk    Unmask
         Verifiable                 Grounded in
                                                     Consequence of
                                                                        Pipeline    Sufficient    Control the Bias
                                                                                                                                        Aggregation
                                    Engineering                       Knowledge     Granularity                          Reality
           Units                                         Failure
                                     Principles




            All plausible failure mechanisms must be included in the
             assessment of PoF
            Each failure mechanism must have the following elements
             independently measured:
                    - Exposure
                    - Mitigation
                    - Resistance

            For each time dependent failure mechanism, a theoretical
             remaining life estimate must be produced



© Det Norske Veritas AS. All rights reserved.
Probability of
                                                                                     Failure Grounded
                                                                                      in Engineering
 Proper PoF Characterization                                                             Principles




 Independent Evaluations of:

  Exposure: likelihood and aggressiveness of a failure mechanism reaching the pipe when no

      mitigation applied (ATTACK)


  Mitigation: prevents or reduces likelihood or intensity of the exposure reaching the pipe

      (DEFENSE)


  Resistance: ability to resist failure given presence of exposure (SURVIVABILITY )




© Det Norske Veritas AS. All rights reserved.
Probability of
                                                                        Failure Grounded
                                                                         in Engineering
 Simple and Robust Relationships are Available                              Principles




     Probability of Failure (PoF) = Exposure x (1 - Mitigation) x (1 – Resistance)




                                                Probability of Damage


     TTF = exposure * (1 – mitigation) / resistance
     PoF = f (TTF)




© Det Norske Veritas AS. All rights reserved.
Probability of
                                                Failure Grounded
                                                 in Engineering
 Estimating Threat Exposure                         Principles




 Events per mile-year for time independent
  mechanism
      - third party
      - incorrect operations
      - weather & land movements

 MPY for degradation mechanisms
      - Ext corr
      - Int corr
      - Cracking (EAC / fatigue)




© Det Norske Veritas AS. All rights reserved.
Estimating Mitigation Measure Effectiveness
                         Strong, single measure
                                    Or
                     Accumulation of lesser measures


                                                      Cathodic                          Public           Maint Pigging
                                                      protection          Patrol        Education
                                                      system

                                                Coating            Depth of        Casing           Training &    Chem Inhibition
                                                system             cover                            Competency




            Exposure                                                                                                                Damage




                                                                                                                                    Slide 27
© Det Norske Veritas AS. All rights reserved.
Probability of
                                                                                 Failure Grounded

             Estimating Resistance                                                in Engineering
                                                                                     Principles




             Pipe spec (original)                       Required pipe strength
                                                         - Normal internal pressure
             Historical issues                          - Normal external loadings
                 -   Low toughness
                 -   Hard spots
                 -   Seam type
                 -   Manufacturing

             Pipe spec (current)
                 -   ILI measurements
                 -   Calcs from pressure test
                 -   Visual inspections
                 -   Effect of estimated degradations



© Det Norske Veritas AS. All rights reserved.
Probability of
                                                                                                             Failure Grounded
                                                                                                              in Engineering

       Best Estimate of Pipe Wall Today                                                                          Principles




         Adjust measurements for age and accuracy


                                                      Measurement error   Degradation Since Meas

                                                                                                         Current Estimate

    Press Test
    1992
                                                                             8 mpy x 21 yrs = 168 mils
                                         (inferred)         +/- 5%




      ILI
      2005
                                                                              8 mpy x 8 yrs = 64 mils
                                                             +/- 15%




© Det Norske Veritas AS. All rights reserved.
PoF: Critical Aspects




© Det Norske Veritas AS. All rights reserved.
Fully Characterize Consequence of Failure
                                    Probability of
        Measure in                                                     Fully
                                       Failure                                      Integrate   Incorporate
                                                                   Characterize                                                   Profile the Risk    Unmask
         Verifiable                 Grounded in
                                                                  Consequence of
                                                                                     Pipeline    Sufficient    Control the Bias
                                                                                                                                                     Aggregation
                                    Engineering                                    Knowledge     Granularity                          Reality
           Units                                                      Failure
                                     Principles




            Must identify and acknowledge the full range of possible
             consequence scenarios
            Must consider ‘most probable’ and ‘worst case’ scenarios


                                                                                                                       HCA




                                                     Spill path
                       PL                                                                                                               Hazard
                                                                                                                                        Zone




© Det Norske Veritas AS. All rights reserved.
Fully
                                                                                                                                                          Characterize
                                                                                                                                                          Consequence
 Consequence Estimation Overview                                                                                                                            of Failure




 Sequence of Analysis
 1. Chance of failure (threat models)
                                                              Probability
 2. Chance of failure hole size
 3. Spill size (considering leak detection and reaction scenarios)
     -        Volume Out
                                                                           2                                4                5                                       6
 4. Chance of ignition                           Product   Hole size
                                                                       Hole size
                                                                                     Ignition scenario
                                                                                                           Ignition
                                                                                                                        Distance     thermal
                                                                                                                        from source hazard
                                                                                                                                                  Contaminati
                                                                                                                                                  on hazard
                                                                                                                                                                Total
                                                                                                                                                                          probability
                                                                                                                                                                          of hazard
                                                                       probability                        probability                                           (ft)
     -        Immediate                                                              immediate ignition      5%
                                                                                                                        (ft)
                                                                                                                                   0
                                                                                                                                     zone (ft)
                                                                                                                                              400
                                                                                                                                                  zone (ft)
                                                                                                                                                              0       400
                                                                                                                                                                          zone
                                                                                                                                                                                0.2%
     -        Delayed                                      rupture           4%      delayed ignition
                                                                                     no ignition
                                                                                                             10%
                                                                                                             85%
                                                                                                                                 600
                                                                                                                                 600
                                                                                                                                              500
                                                                                                                                                0
                                                                                                                                                            400
                                                                                                                                                            900
                                                                                                                                                                     1100
                                                                                                                                                                     1500
                                                                                                                                                                                0.4%
                                                                                                                                                                                3.4%
     -        None                                                                   immediate ignition      2%                    0          200             0       200       0.3%
                                                 oil       medium            16%     delayed ignition        5%                  200          300           200       500       0.8%
                                                                                     no ignition             93%                 200            0           500       700      14.9%
 5. Spill dispersion                                                                 immediate ignition      1%                    0           50             0        50       0.8%
                                                                                     delayed ignition        2%                   80          100             0       180       1.6%
     -        Pipeline/product characteristics             small             80%
                                                                                     no ignition             97%                  80            0            80       160      77.6%
     -        Topography (if liquid release)
     -        Meteorology (if gaseous release)
 6. Hazard area size and probability (for each scenario)
 7. Chance of receptor(s) being in hazard area (counts, density, or area)
 8. Chance of various damage states to various receptor (including consequence mitigation)
 9. Calculate Expected Loss (Prob x Consequence $)


© Det Norske Veritas AS. All rights reserved.                               32
Integrate Pipeline Knowledge
                                    Probability of
        Measure in                                        Fully
                                       Failure                         Integrate   Incorporate
                                                      Characterize                                                   Profile the Risk    Unmask
         Verifiable                 Grounded in
                                                     Consequence of
                                                                        Pipeline    Sufficient    Control the Bias
                                                                                                                                        Aggregation
                                    Engineering                       Knowledge     Granularity                          Reality
           Units                                         Failure
                                     Principles




            The assessment must include complete, appropriate, and
             transparent use of all available information
            ‘Appropriate’ when model uses info as would an SME




© Det Norske Veritas AS. All rights reserved.
Integrate
                                                                                                                                                   Pipeline

 External Corrosion Model                                                                                                                        Knowledge



                                                                EC POF (prob/mile-yr)


                                                      EC TTF (Years –assuming a per mile basis )



           Available Pipe Wall (in)                                                                                Growth Rate (mpy)
           Estimate x Adjustment


Estimate (in)                  Adjustments (%)                                     Estimate (mpy)
                                                                              Total mpy x (1-Mitigation)                                       Measured (mpy)

Max based on:
                             Cumulative:
1. NOP                                               Environment (mpy)                                     Mitigation (%) based on Active
                             1. Joint Type                                                                                                    Direct measurements
2. Hydrotest                                                Sum                                                 Corrosion Locations
                             2. Reinforcements                                                                                                     adjusted by
3. NDE/ILI
                             3. Manuf & Const                                                                                                      Confidence
2&3 adjusted for
                             4. Pipe Type
mpy growth since                              1.    Above/Below Ground
                             5. Toughness                                             CP Gaps (Prob of gaps/ft)
measurement                                   2.    Atmospheric CGR (mpy)
                             6. Flaws                                         Sum of gaps/mi converted to probability             External Coating Holiday Rate
                             7. External Loads3.    Electrical Isolation (%)
                             8. Spans         4.    Soil based CGR (mpy)
                                                         1. Corrosivity
                                                         2. Moisture Content    CP Effectiveness     CP Interference                  Estimated (defects/mi)
                                                         3. MIC                                                                       1. Defects/mi adjusted by
                                                 5. Mitigated AC Induced                                                                  confidence
                                                    CGR (mpy)                Measured Gaps /mi      Locations/mi:                     Measured (defects/mi)
                                                                             1. CP Readings         1. DC Sources                     1. Defects/mi adjusted by
                                                                                 adjusted by            (mitigated)                       confidence and age
                                                                                 confidence         2. Coating
                                                                             Estimated Gaps/mi          Shielding
                                                                             1. Distance from       3. Casing
                                                                                 test station           Shielding
                                                                             2. PL Age
                                                                             3. Criteria
                                                                             4. Rectifier out of
                                                                                 service history
© Det Norske Veritas AS. All rights reserved.                                           34
Incorporate Sufficient Granularity
                                    Probability of
        Measure in                                        Fully
                                       Failure                         Integrate   Incorporate
                                                      Characterize                                                   Profile the Risk    Unmask
         Verifiable                 Grounded in
                                                     Consequence of
                                                                        Pipeline    Sufficient    Control the Bias
                                                                                                                                        Aggregation
                                    Engineering                       Knowledge     Granularity                          Reality
           Units                                         Failure
                                     Principles




            Risk assessment must divide the pipeline into segments
             where risks are unchanging
            Compromises involving the use of averages or extremes
             can significantly weaken the analysis and are to be avoided




© Det Norske Veritas AS. All rights reserved.
Incorporate
                                                                                                      Sufficient

 Dynamic Segmentation                                                                                Granularity




         Due to the numerous and constantly-varying factors
         effecting the risk to the pipeline, proper analysis will
         require at least 10 segments per mile
         (not uncommon to have thousands of segments per mile)

                      Steel Pipe wall 0.320”                                      Pipe wall 0.500”

                      1995                                                     1961
                                                Landslide Threat
                                                                   Population Class 3




© Det Norske Veritas AS. All rights reserved.
Control the Bias
                                    Probability of
        Measure in                                        Fully
                                       Failure                         Integrate   Incorporate
                                                      Characterize                                                   Profile the Risk    Unmask
         Verifiable                 Grounded in
                                                     Consequence of
                                                                        Pipeline    Sufficient    Control the Bias
                                                                                                                                        Aggregation
                                    Engineering                       Knowledge     Granularity                          Reality
           Units                                         Failure
                                     Principles




            Risk assessment must state the level of conservatism
             employed in all of its components
            Assessment must be free of inappropriate bias that tends to
             force incorrect conclusions




© Det Norske Veritas AS. All rights reserved.
Control the
                                                                Bias
 Certainty




                                    “Absolute certAinty is
                                     the privilege of fools
                                         And fAnAtics.”




© Det Norske Veritas AS. All rights reserved.
Control the

       Understanding Conservatism and Uncertainty                      Bias




         A way to measure and communicate conservatism in risk estimates
             - PXX
                  - P50
                  - P90
                  - P99.9
             Useful in conveying intended level of conservatism




© Det Norske Veritas AS. All rights reserved.
The Role of Historical Incidents                           Control the
                                                               Bias




  Problems:
   Historical data usefulness in current situation
   Small amount of data in rare-event situations
   Representative population
   Behavior of the individual vs population



                                                weightings

© Det Norske Veritas AS. All rights reserved.
Profile the Risk Reality
                                    Probability of
        Measure in                                        Fully
                                       Failure                         Integrate   Incorporate
                                                      Characterize                                                   Profile the Risk    Unmask
         Verifiable                 Grounded in
                                                     Consequence of
                                                                        Pipeline    Sufficient    Control the Bias
                                                                                                                                        Aggregation
                                    Engineering                       Knowledge     Granularity                          Reality
           Units                                         Failure
                                     Principles




            The risk assessment must be performed at all points along
             the pipeline
            Must produce a continuous profile of changing risks along
             the entire pipeline
            Profile must reflect the changing characteristics of the pipe
             and its surroundings




© Det Norske Veritas AS. All rights reserved.
Risk Profile: Passing the ‘Map Point’ Test
                                                Profile the
                                                Risk Reality




© Det Norske Veritas AS. All rights reserved.
Profile the


               Profile to Characterize Risk                                             Risk Reality




                           Scenario 1
                           100 km oil pipeline
                           widespread coating failure
                           river parallel
                           remote




                                                        Scenario 2
                                                        50 km gas pipeline
                                                        2 shallow cover locations
                                                        high population density
                                                        high pressure, large diameter




© Det Norske Veritas AS. All rights reserved.
Profile the
                                                                                Risk Reality

 Risk Characterization

                                                          Scenario 2
          Scenario 1                                      50 km gas pipeline
          100 km oil pipeline                             2 shallow cover locations
          widespread coating failure                      high population density
          river parallel                                  high pressure, large diameter
          remote location




                                                    EL
      EL




                                          km             km




                     Very different risk profiles


© Det Norske Veritas AS. All rights reserved.
System Profiles Compared




© Det Norske Veritas AS. All rights reserved.
Proper Aggregation
                                    Probability of
        Measure in                                        Fully
                                       Failure                         Integrate   Incorporate
                                                      Characterize                                                   Profile the Risk    Unmask
         Verifiable                 Grounded in
                                                     Consequence of
                                                                        Pipeline    Sufficient    Control the Bias
                                                                                                                                        Aggregation
                                    Engineering                       Knowledge     Granularity                          Reality
           Units                                         Failure
                                     Principles




            Proper process for aggregation of the risks from multiple
             pipeline segments must be included
            Summarization of the risks from multiple segments must
             avoid simple statistics or weighted statistics that mask the
             actual risks




© Det Norske Veritas AS. All rights reserved.
Unmask
                                                                                      Aggregation
 Aggregating Risks for Collection of Pipe Segments




           PoF total =                            PoF1 + PoF2 + PoF3 +     PoF4   + …. PoFn


                                                PoF total = 137% . . . ?



                    Simple sum only works when values are very
                     low.
                    Len-weighted avg masks ‘weak link in chain’

© Det Norske Veritas AS. All rights reserved.
Unmask

       Aggregating Risks                                                   Aggregation




                                      PoF total = Avg(PoF1, PoF2, …PoFn)


                                                Avg PoF = Avg PoF
                                                       But


    PoF                                                         PoF




                                                            ≠

                                                       KM                            KM



© Det Norske Veritas AS. All rights reserved.
Unmask

       Aggregating Risks                                                     Aggregation




                                        PoF total = Max(PoF1, PoF2, …PoFn)

                                                   Max PoF = Max PoF
                                                          But


     PoF                                                          PoF




                                                              ≠

                                                         KM                                KM




© Det Norske Veritas AS. All rights reserved.
Aggregating Risks


                                        PoF total = Max(PoF1, PoF2, …PoFn)

                                                   Max PoF = Max PoF
                                                          But


           PoF                                                    PoF




                                                              ≠

                                                         KM                  KM




© Det Norske Veritas AS. All rights reserved.
Unmask
                                                                                 Aggregation
 Aggregating Failure Probabilities



     Overall PoF is prob failure by [(thd pty) OR (corr) OR (geohaz)…]


     PoS = 1 - PoF


     Overall PoS is prob surviving [(thd pty) AND (corr) AND (geohaz)….]



     So…


     PoF overall = 1-[(1-pfthdpty) x (1-pfcorr) x (1-pfgeohaz) x (1-pfincops)]

© Det Norske Veritas AS. All rights reserved.
The Essential Elements
                                                    Measurements in Verifiable Units


                                                 Proper Probability of Failure Assessment


                                                Characterization of Potential Consequences


                                                  Full Integration of Pipeline Knowledge


                                                          Sufficient Granularity


                                                            Bias Management


                                                             Profiles of Risk


                                                           Proper Aggregation


© Det Norske Veritas AS. All rights reserved.                                   52
The New Look of PL RA


                              PoF (len adjusted)

                        140

                        120

                        100
            Frequency




                        80

                        60                                                        PoF (unitized)

                        40                            12.0%

                        20                            10.0%

                                                      8.0%
                         0
                                                      6.0%
                        0. 0 1
                        0. 01
                        0. 04

                         0. 7


                        0. 13
                        0. 16
                        0. 19
                        0. 22
                        0. 25
                        0. 28

                                 1
                                e
                             00




                             03

                              or
                            00
                             0
                             0




                             0
                             0
                             0
                             0
                             0
                             0


                            M
                           00
                           00
                           00


                           00
                           00
                           00
                           00
                           00
                           00
                           00




                                                      4.0%
                        0.




                                                Bin   2.0%

                                                      0.0%
                                                              0   20000   40000   60000             80000   100000   120000   140000
                                                                                          station




© Det Norske Veritas AS. All rights reserved.
Intended Outcomes




© Det Norske Veritas AS. All rights reserved.   54
Intended Outcomes of Application of EE’s
   Efficient and transparent risk modeling
   Accurate, verifiable, and complete results
   Improved understanding of actual risk
   Risk-based input to guide integrity decision-making: true risk management

   Optimized resource allocation leading to higher levels of public
    safety
   Appropriate level of standardization facilitating smoother regulatory audits
       - Does not stifle creativity
       - Does not dictate all aspects of the process
       - Avoids need for (high-overhead) prescriptive documentation

   Expectations of regulators, the public, and operators fulfilled




© Det Norske Veritas AS. All rights reserved.      55
If you don’t have a number,
                                 you don’t have a fact,
                                 you have an opinion.




© Det Norske Veritas AS. All rights reserved.
Safeguarding life, property
       and the environment

       www.dnv.com


       Kent Muhlbauer
       wkm@pipelinerisk.com




© Det Norske Veritas AS. All rights reserved.   57

Mais conteúdo relacionado

Semelhante a PL Safety and Essentials of Risk Assessment

Esd the broad impact and design challenges part1of2
Esd the broad impact and design challenges part1of2Esd the broad impact and design challenges part1of2
Esd the broad impact and design challenges part1of2
ASQ Reliability Division
 
general
generalgeneral
general
EKH
 
Sgs ind-ndt-hic-leaflet-en-11
Sgs ind-ndt-hic-leaflet-en-11Sgs ind-ndt-hic-leaflet-en-11
Sgs ind-ndt-hic-leaflet-en-11
mntahmaz
 
Nanometer Testing: Challenges and Solutions
Nanometer Testing: Challenges and SolutionsNanometer Testing: Challenges and Solutions
Nanometer Testing: Challenges and Solutions
DVClub
 
June event - Operational risk management - IT Career
June event - Operational risk management - IT CareerJune event - Operational risk management - IT Career
June event - Operational risk management - IT Career
Friends4Growth Group
 

Semelhante a PL Safety and Essentials of Risk Assessment (20)

Esd the broad impact and design challenges part1of2
Esd the broad impact and design challenges part1of2Esd the broad impact and design challenges part1of2
Esd the broad impact and design challenges part1of2
 
PACT-08-workshop-churn-p2p-ea
PACT-08-workshop-churn-p2p-eaPACT-08-workshop-churn-p2p-ea
PACT-08-workshop-churn-p2p-ea
 
Volta Storylines and Scenarios: A mouthpiece for interventions that enhance l...
Volta Storylines and Scenarios: A mouthpiece for interventions that enhance l...Volta Storylines and Scenarios: A mouthpiece for interventions that enhance l...
Volta Storylines and Scenarios: A mouthpiece for interventions that enhance l...
 
general
generalgeneral
general
 
[PH-Neutral 0x7db] Exploit Next Generation®
[PH-Neutral 0x7db] Exploit Next Generation®[PH-Neutral 0x7db] Exploit Next Generation®
[PH-Neutral 0x7db] Exploit Next Generation®
 
Risk Managers Of The Universe
Risk Managers Of The UniverseRisk Managers Of The Universe
Risk Managers Of The Universe
 
Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...
Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...
Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...
 
(R)isk Revolution - Current trends and challenges in Credit & Operational Risk
(R)isk Revolution - Current trends and challenges in Credit & Operational Risk(R)isk Revolution - Current trends and challenges in Credit & Operational Risk
(R)isk Revolution - Current trends and challenges in Credit & Operational Risk
 
Understanding and Managing Risk in Complex Supply Chain Projects
Understanding and Managing Risk in Complex Supply Chain ProjectsUnderstanding and Managing Risk in Complex Supply Chain Projects
Understanding and Managing Risk in Complex Supply Chain Projects
 
Beyond the Solar Module: Optimizing system performance and maximizing returns...
Beyond the Solar Module: Optimizing system performance and maximizing returns...Beyond the Solar Module: Optimizing system performance and maximizing returns...
Beyond the Solar Module: Optimizing system performance and maximizing returns...
 
Security, Economics, Technology and the Sustainability Paradox
Security, Economics, Technology and the Sustainability ParadoxSecurity, Economics, Technology and the Sustainability Paradox
Security, Economics, Technology and the Sustainability Paradox
 
Trepp Capital Adequacy Stress Testing
Trepp Capital Adequacy Stress TestingTrepp Capital Adequacy Stress Testing
Trepp Capital Adequacy Stress Testing
 
Sgs ind-ndt-hic-leaflet-en-11
Sgs ind-ndt-hic-leaflet-en-11Sgs ind-ndt-hic-leaflet-en-11
Sgs ind-ndt-hic-leaflet-en-11
 
Understanding halt application in desktop nb and server
Understanding halt application in desktop nb and serverUnderstanding halt application in desktop nb and server
Understanding halt application in desktop nb and server
 
Full stack vulnerability management at scale
Full stack vulnerability management at scaleFull stack vulnerability management at scale
Full stack vulnerability management at scale
 
Stamper Technology 2012 04-06
Stamper Technology 2012 04-06Stamper Technology 2012 04-06
Stamper Technology 2012 04-06
 
Nanometer Testing: Challenges and Solutions
Nanometer Testing: Challenges and SolutionsNanometer Testing: Challenges and Solutions
Nanometer Testing: Challenges and Solutions
 
Abraham q3 2008
Abraham q3 2008Abraham q3 2008
Abraham q3 2008
 
June event - Operational risk management - IT Career
June event - Operational risk management - IT CareerJune event - Operational risk management - IT Career
June event - Operational risk management - IT Career
 
ClinicalGradeMobileHealth mHIseminar.Beaulieu
ClinicalGradeMobileHealth mHIseminar.BeaulieuClinicalGradeMobileHealth mHIseminar.Beaulieu
ClinicalGradeMobileHealth mHIseminar.Beaulieu
 

Mais de IIR Conferenties & Trainingen

Presentatie Dylan Dresens van NHG - 22e Hypotheken Event 2013
Presentatie Dylan Dresens van NHG - 22e Hypotheken Event 2013Presentatie Dylan Dresens van NHG - 22e Hypotheken Event 2013
Presentatie Dylan Dresens van NHG - 22e Hypotheken Event 2013
IIR Conferenties & Trainingen
 
Presentatie Rick te Molder van de ABN AMRO Bank - Hypotheken Event 2013
Presentatie Rick te Molder van de ABN AMRO Bank - Hypotheken Event 2013Presentatie Rick te Molder van de ABN AMRO Bank - Hypotheken Event 2013
Presentatie Rick te Molder van de ABN AMRO Bank - Hypotheken Event 2013
IIR Conferenties & Trainingen
 
Presentatie van Dick-Jan Abbringh, Nadja Jungmann & Peter Wesdorp - Hypotheke...
Presentatie van Dick-Jan Abbringh, Nadja Jungmann & Peter Wesdorp - Hypotheke...Presentatie van Dick-Jan Abbringh, Nadja Jungmann & Peter Wesdorp - Hypotheke...
Presentatie van Dick-Jan Abbringh, Nadja Jungmann & Peter Wesdorp - Hypotheke...
IIR Conferenties & Trainingen
 
Presentatie van Christian Bouter van Advieskeuze.nl - Hypotheken Event 2013
Presentatie van Christian Bouter van Advieskeuze.nl - Hypotheken Event 2013Presentatie van Christian Bouter van Advieskeuze.nl - Hypotheken Event 2013
Presentatie van Christian Bouter van Advieskeuze.nl - Hypotheken Event 2013
IIR Conferenties & Trainingen
 
Presentatie van Fred van Raaij van de Tilburg University - Hypotheken Event 2013
Presentatie van Fred van Raaij van de Tilburg University - Hypotheken Event 2013Presentatie van Fred van Raaij van de Tilburg University - Hypotheken Event 2013
Presentatie van Fred van Raaij van de Tilburg University - Hypotheken Event 2013
IIR Conferenties & Trainingen
 
Presentatie Jacqueline Baardman Patiëntenfederatie NPCF - Hypotheken Event 2013
Presentatie Jacqueline Baardman Patiëntenfederatie NPCF - Hypotheken Event 2013Presentatie Jacqueline Baardman Patiëntenfederatie NPCF - Hypotheken Event 2013
Presentatie Jacqueline Baardman Patiëntenfederatie NPCF - Hypotheken Event 2013
IIR Conferenties & Trainingen
 
Presentatie Thomas Ploemen Obvion & Niels Kortleve van PGGM - Hypotheken Even...
Presentatie Thomas Ploemen Obvion & Niels Kortleve van PGGM - Hypotheken Even...Presentatie Thomas Ploemen Obvion & Niels Kortleve van PGGM - Hypotheken Even...
Presentatie Thomas Ploemen Obvion & Niels Kortleve van PGGM - Hypotheken Even...
IIR Conferenties & Trainingen
 
Presentatie Marcel van Brenk VODW - Hypotheken Event 2013
Presentatie Marcel van Brenk VODW - Hypotheken Event 2013Presentatie Marcel van Brenk VODW - Hypotheken Event 2013
Presentatie Marcel van Brenk VODW - Hypotheken Event 2013
IIR Conferenties & Trainingen
 
Presentatie Hans-Joachim Michel & Michel Kant van NIBC - 22e Hypotheken Event...
Presentatie Hans-Joachim Michel & Michel Kant van NIBC - 22e Hypotheken Event...Presentatie Hans-Joachim Michel & Michel Kant van NIBC - 22e Hypotheken Event...
Presentatie Hans-Joachim Michel & Michel Kant van NIBC - 22e Hypotheken Event...
IIR Conferenties & Trainingen
 

Mais de IIR Conferenties & Trainingen (20)

Uitbreiding Nederlands gasnetwerk
Uitbreiding Nederlands gasnetwerkUitbreiding Nederlands gasnetwerk
Uitbreiding Nederlands gasnetwerk
 
Paul van der meijs de hypotheker
Paul van der meijs   de hypothekerPaul van der meijs   de hypotheker
Paul van der meijs de hypotheker
 
Presentatie Dylan Dresens van NHG - 22e Hypotheken Event 2013
Presentatie Dylan Dresens van NHG - 22e Hypotheken Event 2013Presentatie Dylan Dresens van NHG - 22e Hypotheken Event 2013
Presentatie Dylan Dresens van NHG - 22e Hypotheken Event 2013
 
Presentatie Rick te Molder van de ABN AMRO Bank - Hypotheken Event 2013
Presentatie Rick te Molder van de ABN AMRO Bank - Hypotheken Event 2013Presentatie Rick te Molder van de ABN AMRO Bank - Hypotheken Event 2013
Presentatie Rick te Molder van de ABN AMRO Bank - Hypotheken Event 2013
 
Presentatie van Dick-Jan Abbringh, Nadja Jungmann & Peter Wesdorp - Hypotheke...
Presentatie van Dick-Jan Abbringh, Nadja Jungmann & Peter Wesdorp - Hypotheke...Presentatie van Dick-Jan Abbringh, Nadja Jungmann & Peter Wesdorp - Hypotheke...
Presentatie van Dick-Jan Abbringh, Nadja Jungmann & Peter Wesdorp - Hypotheke...
 
Presentatie Bouwe Kuik IG&H - Hypotheken Event 2013
Presentatie Bouwe Kuik IG&H - Hypotheken Event 2013Presentatie Bouwe Kuik IG&H - Hypotheken Event 2013
Presentatie Bouwe Kuik IG&H - Hypotheken Event 2013
 
Presentatie van Christian Bouter van Advieskeuze.nl - Hypotheken Event 2013
Presentatie van Christian Bouter van Advieskeuze.nl - Hypotheken Event 2013Presentatie van Christian Bouter van Advieskeuze.nl - Hypotheken Event 2013
Presentatie van Christian Bouter van Advieskeuze.nl - Hypotheken Event 2013
 
Presentatie van Fred van Raaij van de Tilburg University - Hypotheken Event 2013
Presentatie van Fred van Raaij van de Tilburg University - Hypotheken Event 2013Presentatie van Fred van Raaij van de Tilburg University - Hypotheken Event 2013
Presentatie van Fred van Raaij van de Tilburg University - Hypotheken Event 2013
 
Presentatie Jacqueline Baardman Patiëntenfederatie NPCF - Hypotheken Event 2013
Presentatie Jacqueline Baardman Patiëntenfederatie NPCF - Hypotheken Event 2013Presentatie Jacqueline Baardman Patiëntenfederatie NPCF - Hypotheken Event 2013
Presentatie Jacqueline Baardman Patiëntenfederatie NPCF - Hypotheken Event 2013
 
Presentatie Thomas Ploemen Obvion & Niels Kortleve van PGGM - Hypotheken Even...
Presentatie Thomas Ploemen Obvion & Niels Kortleve van PGGM - Hypotheken Even...Presentatie Thomas Ploemen Obvion & Niels Kortleve van PGGM - Hypotheken Even...
Presentatie Thomas Ploemen Obvion & Niels Kortleve van PGGM - Hypotheken Even...
 
Presentatie Marcel van Brenk VODW - Hypotheken Event 2013
Presentatie Marcel van Brenk VODW - Hypotheken Event 2013Presentatie Marcel van Brenk VODW - Hypotheken Event 2013
Presentatie Marcel van Brenk VODW - Hypotheken Event 2013
 
Presentatie Ewald Engelen - Hypotheken Event 2013
Presentatie Ewald Engelen - Hypotheken Event 2013Presentatie Ewald Engelen - Hypotheken Event 2013
Presentatie Ewald Engelen - Hypotheken Event 2013
 
Presentatie Guus Alfrink & Marianne Wansbeek - Hypotheken Event 2013
Presentatie Guus Alfrink & Marianne Wansbeek - Hypotheken Event 2013Presentatie Guus Alfrink & Marianne Wansbeek - Hypotheken Event 2013
Presentatie Guus Alfrink & Marianne Wansbeek - Hypotheken Event 2013
 
Presentatie Hans-Joachim Michel & Michel Kant van NIBC - 22e Hypotheken Event...
Presentatie Hans-Joachim Michel & Michel Kant van NIBC - 22e Hypotheken Event...Presentatie Hans-Joachim Michel & Michel Kant van NIBC - 22e Hypotheken Event...
Presentatie Hans-Joachim Michel & Michel Kant van NIBC - 22e Hypotheken Event...
 
Presentatie Johan Conijn - 22e Hypotheken Event 2013
Presentatie Johan Conijn - 22e Hypotheken Event 2013Presentatie Johan Conijn - 22e Hypotheken Event 2013
Presentatie Johan Conijn - 22e Hypotheken Event 2013
 
Risico's van buisleidingen
Risico's van buisleidingen Risico's van buisleidingen
Risico's van buisleidingen
 
21e Hypotheken Event - Hans van Breukelen
21e Hypotheken Event - Hans van Breukelen21e Hypotheken Event - Hans van Breukelen
21e Hypotheken Event - Hans van Breukelen
 
21e Hypotheken Event - Jan Donselaar
21e Hypotheken Event - Jan Donselaar21e Hypotheken Event - Jan Donselaar
21e Hypotheken Event - Jan Donselaar
 
21e Hypotheken Event - Marja Elsinga
21e Hypotheken Event - Marja Elsinga21e Hypotheken Event - Marja Elsinga
21e Hypotheken Event - Marja Elsinga
 
21e Hypotheken Event - Remco Polman
21e Hypotheken Event - Remco Polman21e Hypotheken Event - Remco Polman
21e Hypotheken Event - Remco Polman
 

PL Safety and Essentials of Risk Assessment

  • 1. PL Safety and Essentials of Risk Assessment Following the Essential Elements
  • 2. Background © Det Norske Veritas AS. All rights reserved. 2
  • 3. © Det Norske Veritas AS. All rights reserved.
  • 4. Kalamazoo River, 2010 10ft creek CoF: $1B PoF: 1/1000yr Expected Loss: $1M/yr for ~3m of pipeline! $1,000,000,000 spent © Det Norske Veritas AS. All rights reserved.
  • 5. Reality Check  RM is not new; requires RA  Risk-based decision-making is complex - Because the real world is complex, measuring risk is complex - RM is even more complex than RA  Dealing with the complexity is worthwhile - increases understanding - shows full range of options; many opportunities to impact risk - cheaper than prescriptive ‘solutions’ - Improves decision-making - the key to improving PL safety © Det Norske Veritas AS. All rights reserved.
  • 6. Reality Check, Part Two If you put tomfoolery into a computer, nothing comes out of it but tomfoolery. But this tomfoolery, having passed through a very expensive machine, is somehow ennobled and no-one dares criticize it. - Pierre Gallois The Illusion of Knowledge © Det Norske Veritas AS. All rights reserved.
  • 7. How good is PL RA now? Pockets of strengths But Weaknesses are apparent - A complicated topic--incomplete understanding is common - Lack of standardized RA approaches - Errors in some industry standards - New demands by regulators and other stakeholders - Myths and misconceptions © Det Norske Veritas AS. All rights reserved. 7
  • 8. PL Risk Modeling Confusion ASME B31.8s •Subject Matter Experts Qualitative •Relative Assessments Quantitative •Scenario Assessments Semi-quantitative •Probabilistic Assessments Probabilistic Deterministic © Det Norske Veritas AS. All rights reserved.
  • 9. Regulations: IMP Objectives vs RA Techniques Objectives (a) prioritization of pipelines/segments for scheduling integrity assessments and mitigating action (b) assessment of the benefits derived from mitigating action (c) determination of the most effective mitigation measures for the identified threats (d) assessment of the integrity impact from modified inspection intervals (e) assessment of the use of or need for alternative inspection methodologies (f) more effective resource allocation Techniques • Subject Matter Experts • Relative Assessments • Scenario Assessments • Probabilistic Assessments Numbers Needed •Failure rate estimates for each threat on each PL segment •Mitigation effectiveness for each contemplated measure •Time to Failure (TTF) estimates (time-dep threats) © Det Norske Veritas AS. All rights reserved.
  • 10. “Threat Interaction” Confusion  Time Dependent Threats  Stable Threats Potential Weaknesses - Corrosion  Manufacturing-related flaws in - External - Pipe body - Internal - Pipe seam - Cracking - Fatigue  Welding / Fabrication-caused flaws in - EAC - Girth welds - Fabrication welds  Time Independent Threats - Wrinkled / buckled bend - Third party - Threads / couplings - Geohazards  Defects present in equipment - Incorrect operations - Gaskets, O-rings - Sabotage - Control / relief devices - Seals, packing - Other equipment © Det Norske Veritas AS. All rights reserved. 10
  • 11. Myths: Data Availability vs Modeling Rigor Myth:  Some RA models are better able to accommodate low data availability Reality:  Strong data + strong model = accurate results  Weak data + strong model = uncertain results  Weak data + weak model = meaningless results 11 © Det Norske Veritas AS. All rights reserved.
  • 12. Myth: QRA / PRA Requirements Myth:  QRA requires vast amounts of incident histories Reality:  QRA ‘requires’ no more data than other techniques  All assessments work better with better information  Footnotes: - Some classical QRA does over-emphasize history - Excessive reliance on history is an error in any methodology 12 © Det Norske Veritas AS. All rights reserved.
  • 13. © Det Norske Veritas AS. All rights reserved.
  • 14. © Det Norske Veritas AS. All rights reserved.
  • 15. © Det Norske Veritas AS. All rights reserved.
  • 16. Removing the Weaknesses—The New Look of PL RA PoF (len adjusted) 140 120 100 Frequency 80 60 PoF (unitized) 40 12.0% 20 10.0% 8.0% 0 6.0% 0. 0 1 0. 01 0. 04 0. 7 0. 13 0. 16 0. 19 0. 22 0. 25 0. 28 1 e 00 03 or 00 0 0 0 0 0 0 0 0 M 00 00 00 00 00 00 00 00 00 00 4.0% 0. Bin 2.0% 0.0% 0 20000 40000 60000 80000 100000 120000 140000 station © Det Norske Veritas AS. All rights reserved.
  • 17. Essential Elements © Det Norske Veritas AS. All rights reserved. 17
  • 18. Essential Elements  The Essential Elements are meant to - Minimize the weaknesses in current PL RA practice - Be common sense ingredients that make risk assessment meaningful, objective, and acceptable to all stakeholders - Be concise yet flexible, allowing tailored solutions to situation-specific concerns - Lead to smarter risk assessment  The elements are meant to supplement, not replace, guidance, recommended practice, and regulations already in place © Det Norske Veritas AS. All rights reserved. 18
  • 19. The Essential Elements Measurements in Verifiable Units Proper Probability of Failure Assessment Characterization of Potential Consequences Full Integration of Pipeline Knowledge Sufficient Granularity Bias Management Profiles of Risk Proper Aggregation © Det Norske Veritas AS. All rights reserved. 19
  • 20. Measure in Verifiable Units Probability of Measure in Fully Failure Integrate Incorporate Characterize Profile the Risk Unmask Verifiable Grounded in Consequence of Pipeline Sufficient Control the Bias Aggregation Engineering Knowledge Granularity Reality Units Failure Principles  Must include a definition of “Failure”  Must produce verifiable estimates of PoF and CoF in commonly used measurement units  PoF must capture effects of length and time  Must be free from intermediate schemes (scoring, point assignments, etc) “Measure in verifiable units” keeps the process transparent by expressing risk elements in understandable terms that can be calibrated to reality © Det Norske Veritas AS. All rights reserved.
  • 21. Measure in Verifiable Units Risk Estimates as Measurements Risk = Frequency of consequence - Temporally - Spatially TTF = time to failure •Incidents per mile-year remaining life estimates in years •fatalities per mile-year •dollars per km-decade conseq prob © Det Norske Veritas AS. All rights reserved.
  • 22. Measure in Verifiable Units Why measurements instead of scores? Direct measurements are efficient - Less subjective - Anchored in ‘real world’, able to capture real world phenomena - Defensible, auditable, transparent - Avoids need for standardization - Avoids erosion of score definitions - Allows calculation of costs and benefits - Supports better decisions © Det Norske Veritas AS. All rights reserved.
  • 23. Probability of Failure Grounded in Engineering Principles Probability of Measure in Fully Failure Integrate Incorporate Characterize Profile the Risk Unmask Verifiable Grounded in Consequence of Pipeline Sufficient Control the Bias Aggregation Engineering Knowledge Granularity Reality Units Failure Principles  All plausible failure mechanisms must be included in the assessment of PoF  Each failure mechanism must have the following elements independently measured: - Exposure - Mitigation - Resistance  For each time dependent failure mechanism, a theoretical remaining life estimate must be produced © Det Norske Veritas AS. All rights reserved.
  • 24. Probability of Failure Grounded in Engineering Proper PoF Characterization Principles Independent Evaluations of:  Exposure: likelihood and aggressiveness of a failure mechanism reaching the pipe when no mitigation applied (ATTACK)  Mitigation: prevents or reduces likelihood or intensity of the exposure reaching the pipe (DEFENSE)  Resistance: ability to resist failure given presence of exposure (SURVIVABILITY ) © Det Norske Veritas AS. All rights reserved.
  • 25. Probability of Failure Grounded in Engineering Simple and Robust Relationships are Available Principles Probability of Failure (PoF) = Exposure x (1 - Mitigation) x (1 – Resistance) Probability of Damage TTF = exposure * (1 – mitigation) / resistance PoF = f (TTF) © Det Norske Veritas AS. All rights reserved.
  • 26. Probability of Failure Grounded in Engineering Estimating Threat Exposure Principles Events per mile-year for time independent mechanism - third party - incorrect operations - weather & land movements MPY for degradation mechanisms - Ext corr - Int corr - Cracking (EAC / fatigue) © Det Norske Veritas AS. All rights reserved.
  • 27. Estimating Mitigation Measure Effectiveness Strong, single measure Or Accumulation of lesser measures Cathodic Public Maint Pigging protection Patrol Education system Coating Depth of Casing Training & Chem Inhibition system cover Competency Exposure Damage Slide 27 © Det Norske Veritas AS. All rights reserved.
  • 28. Probability of Failure Grounded Estimating Resistance in Engineering Principles  Pipe spec (original)  Required pipe strength - Normal internal pressure  Historical issues - Normal external loadings - Low toughness - Hard spots - Seam type - Manufacturing  Pipe spec (current) - ILI measurements - Calcs from pressure test - Visual inspections - Effect of estimated degradations © Det Norske Veritas AS. All rights reserved.
  • 29. Probability of Failure Grounded in Engineering Best Estimate of Pipe Wall Today Principles Adjust measurements for age and accuracy Measurement error Degradation Since Meas Current Estimate Press Test 1992 8 mpy x 21 yrs = 168 mils (inferred) +/- 5% ILI 2005 8 mpy x 8 yrs = 64 mils +/- 15% © Det Norske Veritas AS. All rights reserved.
  • 30. PoF: Critical Aspects © Det Norske Veritas AS. All rights reserved.
  • 31. Fully Characterize Consequence of Failure Probability of Measure in Fully Failure Integrate Incorporate Characterize Profile the Risk Unmask Verifiable Grounded in Consequence of Pipeline Sufficient Control the Bias Aggregation Engineering Knowledge Granularity Reality Units Failure Principles  Must identify and acknowledge the full range of possible consequence scenarios  Must consider ‘most probable’ and ‘worst case’ scenarios HCA Spill path PL Hazard Zone © Det Norske Veritas AS. All rights reserved.
  • 32. Fully Characterize Consequence Consequence Estimation Overview of Failure Sequence of Analysis 1. Chance of failure (threat models) Probability 2. Chance of failure hole size 3. Spill size (considering leak detection and reaction scenarios) - Volume Out 2 4 5 6 4. Chance of ignition Product Hole size Hole size Ignition scenario Ignition Distance thermal from source hazard Contaminati on hazard Total probability of hazard probability probability (ft) - Immediate immediate ignition 5% (ft) 0 zone (ft) 400 zone (ft) 0 400 zone 0.2% - Delayed rupture 4% delayed ignition no ignition 10% 85% 600 600 500 0 400 900 1100 1500 0.4% 3.4% - None immediate ignition 2% 0 200 0 200 0.3% oil medium 16% delayed ignition 5% 200 300 200 500 0.8% no ignition 93% 200 0 500 700 14.9% 5. Spill dispersion immediate ignition 1% 0 50 0 50 0.8% delayed ignition 2% 80 100 0 180 1.6% - Pipeline/product characteristics small 80% no ignition 97% 80 0 80 160 77.6% - Topography (if liquid release) - Meteorology (if gaseous release) 6. Hazard area size and probability (for each scenario) 7. Chance of receptor(s) being in hazard area (counts, density, or area) 8. Chance of various damage states to various receptor (including consequence mitigation) 9. Calculate Expected Loss (Prob x Consequence $) © Det Norske Veritas AS. All rights reserved. 32
  • 33. Integrate Pipeline Knowledge Probability of Measure in Fully Failure Integrate Incorporate Characterize Profile the Risk Unmask Verifiable Grounded in Consequence of Pipeline Sufficient Control the Bias Aggregation Engineering Knowledge Granularity Reality Units Failure Principles  The assessment must include complete, appropriate, and transparent use of all available information  ‘Appropriate’ when model uses info as would an SME © Det Norske Veritas AS. All rights reserved.
  • 34. Integrate Pipeline External Corrosion Model Knowledge EC POF (prob/mile-yr) EC TTF (Years –assuming a per mile basis ) Available Pipe Wall (in) Growth Rate (mpy) Estimate x Adjustment Estimate (in) Adjustments (%) Estimate (mpy) Total mpy x (1-Mitigation) Measured (mpy) Max based on: Cumulative: 1. NOP Environment (mpy) Mitigation (%) based on Active 1. Joint Type Direct measurements 2. Hydrotest Sum Corrosion Locations 2. Reinforcements adjusted by 3. NDE/ILI 3. Manuf & Const Confidence 2&3 adjusted for 4. Pipe Type mpy growth since 1. Above/Below Ground 5. Toughness CP Gaps (Prob of gaps/ft) measurement 2. Atmospheric CGR (mpy) 6. Flaws Sum of gaps/mi converted to probability External Coating Holiday Rate 7. External Loads3. Electrical Isolation (%) 8. Spans 4. Soil based CGR (mpy) 1. Corrosivity 2. Moisture Content CP Effectiveness CP Interference Estimated (defects/mi) 3. MIC 1. Defects/mi adjusted by 5. Mitigated AC Induced confidence CGR (mpy) Measured Gaps /mi Locations/mi: Measured (defects/mi) 1. CP Readings 1. DC Sources 1. Defects/mi adjusted by adjusted by (mitigated) confidence and age confidence 2. Coating Estimated Gaps/mi Shielding 1. Distance from 3. Casing test station Shielding 2. PL Age 3. Criteria 4. Rectifier out of service history © Det Norske Veritas AS. All rights reserved. 34
  • 35. Incorporate Sufficient Granularity Probability of Measure in Fully Failure Integrate Incorporate Characterize Profile the Risk Unmask Verifiable Grounded in Consequence of Pipeline Sufficient Control the Bias Aggregation Engineering Knowledge Granularity Reality Units Failure Principles  Risk assessment must divide the pipeline into segments where risks are unchanging  Compromises involving the use of averages or extremes can significantly weaken the analysis and are to be avoided © Det Norske Veritas AS. All rights reserved.
  • 36. Incorporate Sufficient Dynamic Segmentation Granularity Due to the numerous and constantly-varying factors effecting the risk to the pipeline, proper analysis will require at least 10 segments per mile (not uncommon to have thousands of segments per mile) Steel Pipe wall 0.320” Pipe wall 0.500” 1995 1961 Landslide Threat Population Class 3 © Det Norske Veritas AS. All rights reserved.
  • 37. Control the Bias Probability of Measure in Fully Failure Integrate Incorporate Characterize Profile the Risk Unmask Verifiable Grounded in Consequence of Pipeline Sufficient Control the Bias Aggregation Engineering Knowledge Granularity Reality Units Failure Principles  Risk assessment must state the level of conservatism employed in all of its components  Assessment must be free of inappropriate bias that tends to force incorrect conclusions © Det Norske Veritas AS. All rights reserved.
  • 38. Control the Bias Certainty “Absolute certAinty is the privilege of fools And fAnAtics.” © Det Norske Veritas AS. All rights reserved.
  • 39. Control the Understanding Conservatism and Uncertainty Bias A way to measure and communicate conservatism in risk estimates - PXX - P50 - P90 - P99.9 Useful in conveying intended level of conservatism © Det Norske Veritas AS. All rights reserved.
  • 40. The Role of Historical Incidents Control the Bias Problems:  Historical data usefulness in current situation  Small amount of data in rare-event situations  Representative population  Behavior of the individual vs population weightings © Det Norske Veritas AS. All rights reserved.
  • 41. Profile the Risk Reality Probability of Measure in Fully Failure Integrate Incorporate Characterize Profile the Risk Unmask Verifiable Grounded in Consequence of Pipeline Sufficient Control the Bias Aggregation Engineering Knowledge Granularity Reality Units Failure Principles  The risk assessment must be performed at all points along the pipeline  Must produce a continuous profile of changing risks along the entire pipeline  Profile must reflect the changing characteristics of the pipe and its surroundings © Det Norske Veritas AS. All rights reserved.
  • 42. Risk Profile: Passing the ‘Map Point’ Test Profile the Risk Reality © Det Norske Veritas AS. All rights reserved.
  • 43. Profile the Profile to Characterize Risk Risk Reality Scenario 1 100 km oil pipeline widespread coating failure river parallel remote Scenario 2 50 km gas pipeline 2 shallow cover locations high population density high pressure, large diameter © Det Norske Veritas AS. All rights reserved.
  • 44. Profile the Risk Reality Risk Characterization Scenario 2 Scenario 1 50 km gas pipeline 100 km oil pipeline 2 shallow cover locations widespread coating failure high population density river parallel high pressure, large diameter remote location EL EL km km Very different risk profiles © Det Norske Veritas AS. All rights reserved.
  • 45. System Profiles Compared © Det Norske Veritas AS. All rights reserved.
  • 46. Proper Aggregation Probability of Measure in Fully Failure Integrate Incorporate Characterize Profile the Risk Unmask Verifiable Grounded in Consequence of Pipeline Sufficient Control the Bias Aggregation Engineering Knowledge Granularity Reality Units Failure Principles  Proper process for aggregation of the risks from multiple pipeline segments must be included  Summarization of the risks from multiple segments must avoid simple statistics or weighted statistics that mask the actual risks © Det Norske Veritas AS. All rights reserved.
  • 47. Unmask Aggregation Aggregating Risks for Collection of Pipe Segments PoF total = PoF1 + PoF2 + PoF3 + PoF4 + …. PoFn PoF total = 137% . . . ? Simple sum only works when values are very low. Len-weighted avg masks ‘weak link in chain’ © Det Norske Veritas AS. All rights reserved.
  • 48. Unmask Aggregating Risks Aggregation PoF total = Avg(PoF1, PoF2, …PoFn) Avg PoF = Avg PoF But PoF PoF ≠ KM KM © Det Norske Veritas AS. All rights reserved.
  • 49. Unmask Aggregating Risks Aggregation PoF total = Max(PoF1, PoF2, …PoFn) Max PoF = Max PoF But PoF PoF ≠ KM KM © Det Norske Veritas AS. All rights reserved.
  • 50. Aggregating Risks PoF total = Max(PoF1, PoF2, …PoFn) Max PoF = Max PoF But PoF PoF ≠ KM KM © Det Norske Veritas AS. All rights reserved.
  • 51. Unmask Aggregation Aggregating Failure Probabilities Overall PoF is prob failure by [(thd pty) OR (corr) OR (geohaz)…] PoS = 1 - PoF Overall PoS is prob surviving [(thd pty) AND (corr) AND (geohaz)….] So… PoF overall = 1-[(1-pfthdpty) x (1-pfcorr) x (1-pfgeohaz) x (1-pfincops)] © Det Norske Veritas AS. All rights reserved.
  • 52. The Essential Elements Measurements in Verifiable Units Proper Probability of Failure Assessment Characterization of Potential Consequences Full Integration of Pipeline Knowledge Sufficient Granularity Bias Management Profiles of Risk Proper Aggregation © Det Norske Veritas AS. All rights reserved. 52
  • 53. The New Look of PL RA PoF (len adjusted) 140 120 100 Frequency 80 60 PoF (unitized) 40 12.0% 20 10.0% 8.0% 0 6.0% 0. 0 1 0. 01 0. 04 0. 7 0. 13 0. 16 0. 19 0. 22 0. 25 0. 28 1 e 00 03 or 00 0 0 0 0 0 0 0 0 M 00 00 00 00 00 00 00 00 00 00 4.0% 0. Bin 2.0% 0.0% 0 20000 40000 60000 80000 100000 120000 140000 station © Det Norske Veritas AS. All rights reserved.
  • 54. Intended Outcomes © Det Norske Veritas AS. All rights reserved. 54
  • 55. Intended Outcomes of Application of EE’s  Efficient and transparent risk modeling  Accurate, verifiable, and complete results  Improved understanding of actual risk  Risk-based input to guide integrity decision-making: true risk management  Optimized resource allocation leading to higher levels of public safety  Appropriate level of standardization facilitating smoother regulatory audits - Does not stifle creativity - Does not dictate all aspects of the process - Avoids need for (high-overhead) prescriptive documentation  Expectations of regulators, the public, and operators fulfilled © Det Norske Veritas AS. All rights reserved. 55
  • 56. If you don’t have a number, you don’t have a fact, you have an opinion. © Det Norske Veritas AS. All rights reserved.
  • 57. Safeguarding life, property and the environment www.dnv.com Kent Muhlbauer wkm@pipelinerisk.com © Det Norske Veritas AS. All rights reserved. 57