1935
    • Original bridge
        Original bridge
        opened.
      • Cost: $1.5 million
1960
       • Second bridge
         opened.
       • Cost: $6.2 million
1970’s


• Iowa and Illinois took
  over ownership
• Toll Booths Removed.
• I-74 was connected.
Today
• 2010 traffic: 61,500
  vehicles per day
• 2035 estimated
  traffic: 98,500 VPD
• Poor geometrics for
  an interstate route
• The bridges are
  functionally obsolete
1998 Major Investment Study
  Needed Improvement Locations
I-74 Corridor Study
          Milestones
2000: I-74 Corridor Study began
2003: Draft Environmental Impact Study completed
2005: Preferred Alternative identified
2006: Main Span Bridge Type chosen
2007: Preliminary Engineering completed
2009: Final Environmental Impact Study, and
        Federal Highway Admin. Record of Decision
Corridor Study Limits
Mississippi River Crossing




      Preferred Alternative
Finalist Bridge Types
                              • Scheme 1 - Basket Handle True Arch Twin Bridge

•Aerial view                                                                         •River view




               •Bettendorf shoreline view




•Approach view                                                                   •Motorist’s view
Finalist Bridge Types
  •Scheme 2 - Modified Basket Handle Tied Arch Twin Bridges with Vertical Pier and Vertical Hangers

•Aerial view                                                                               •River view




               •Bettendorf shoreline view




•Approach view                                                                         •Motorist’s view
Finalist Bridge Types
        •Scheme 3 - Basket Handle Tied Arch Twin Bridges with Vertical Pier and Vertical Hangers

•Aerial view                                                                                 •River view




               •Bettendorf shoreline view




•Approach view                                                                           •Motorist’s view
Finalist Bridge Types
                 • Scheme 4 - Cable Stayed Single Bridge with Semi-Fan Stay Arrangement

•Aerial view                                                                                  •River view




               •Bettendorf shoreline view




•Approach view                                                                            •Motorist’s view
Selected Alternative: Basket
Handle True Arch Twin Bridge
I-74 Project Locations
Central Section Cost Estimate (YOE)
Central Section Design
Preliminary Design
• Completed in April 2009
• $9.1 Million in Consultant Services (Iowa share)
• $0.3 Million Iowa DOT Staff

Final Design
• $9.7 Million expended to date (Iowa Share)
• 71% Complete
• $13.0 Million Consultant Services funds to be
  expended (Iowa share)
• $5.5 Million Iowa DOT Staff funds to be
  expended
Iowa ROW Summary
ROW Purchased (Central & North Sections)
• 47 Parcels
• $6.9 Million

ROW to be Purchased (Central Section)
• 79 Parcels
• $16.9 Million
Illinois ROW Summary
ROW Purchased
• 7 Parcels
• $0.7 Million

ROW to be Purchased
• 59 Parcels
• $3.8 Million
Iowa Investment to Date

•   ROW              $ 6.9 Million
•   Design           $19.5 Million
•   Construction     $16.3 Million
•   Iowa DOT Staff   $ 2.1 Million
    Total            $44.8 Million
Iowa Cost Estimate
                 Phase I
                 2013-2017

ROW                               $16.9 M
Construction                      $13.7 M
Maintenance of Existing Bridges   $ 2.3 M
Iowa DOT Staff                    $ 5.5 M
Consultant Engineering (design)   $13.0 M
                                  $51.4 M
Iowa Cost Estimate
            Phase II – Central Section
                 Beyond 2017, $ in YOE
Main Span                             $118.2 M
Approach Span                         $123.1 M
Viaducts                              $128.9 M
Mainline Roadway                      $ 40.2 M
Bridge Demolition                     $ 15.3 M
Maintenance of Existing Bridges       $   3.5 M
Lighting, Signing, Landscaping, ITS   $ 23.5 M
Consultant Engineering (Constr.)      $ 40.9 M
Iowa DOT Staff                        $   1.0 M
                                      $494.6 M
Illinois Cost Estimate
          Phase II – Central Section
             Beyond 2017, $ in YOE

Main Span                            $118.2 M
Approach Span                        $123.1 M
Viaducts & Mainline Roadway          $356.1 M
Bridge Demolition                    $ 17.2 M
Lighting, Landscaping, ITS           $ 10.1 M
Consultant Engineering (Constr.)     $ 40.9 M
                                     $665.6 M
Central Section Cost Estimate
                YOE


      IOWA            ILLINOIS
     $494.6 M         $665.6 M
Iowa Cost Estimate

Totals
• Completed Work              $ 44.8 M
• Phase I                     $ 51.4 M
• Phase II                    $494.6 M
• Phase III (North Section)   $202.5 M
Total Cost                    $793.3 M
Anticipated Maintenance Cost (Iowa Share)

 Option 1 – In service until 2025
 • Main Bridge                    $ 3.0 M
 • Approach Bridges               $ 2.8 M
 • Total                          $ 5.8 M

 Option 2 – In service until 2035
 • Main Bridge                    $14.2 M
 • Approach Bridges               $ 8.7 M
 • Total                          $22.9 M
Corridor Federal Funding

• Earmarks             $74.6 Million
• Unobligated Amount   $ 7.2 Million
Questions?

Mais conteúdo relacionado

Mais procurados

Eastern market metro park project community meeting 07-22-2020
Eastern market metro park project community meeting  07-22-2020Eastern market metro park project community meeting  07-22-2020
Eastern market metro park project community meeting 07-22-2020RamaChilamkurthy
 
Aggieland Outfitters Rezoning on Fairview Avenue
Aggieland Outfitters Rezoning on Fairview AvenueAggieland Outfitters Rezoning on Fairview Avenue
Aggieland Outfitters Rezoning on Fairview AvenueCity of College Station
 
Emmp community meeting 04 07-31-2019
Emmp community meeting 04 07-31-2019Emmp community meeting 04 07-31-2019
Emmp community meeting 04 07-31-2019RamaChilamkurthy
 
Applicant Presentation -- Aggieland Outfitters Rezoning
Applicant Presentation -- Aggieland Outfitters RezoningApplicant Presentation -- Aggieland Outfitters Rezoning
Applicant Presentation -- Aggieland Outfitters RezoningCity of College Station
 
High path phase 4 7 webinar rev a-fc
High path phase 4 7 webinar rev a-fcHigh path phase 4 7 webinar rev a-fc
High path phase 4 7 webinar rev a-fcFiona Elton
 
Medical District Trunk Line Easement on Park Property
Medical District Trunk Line Easement on Park PropertyMedical District Trunk Line Easement on Park Property
Medical District Trunk Line Easement on Park PropertyCity of College Station
 
Foxhall w street community meeting-flyer
Foxhall w street  community meeting-flyerFoxhall w street  community meeting-flyer
Foxhall w street community meeting-flyerRamaChilamkurthy
 
Sherwood Close Phase 3 Ealing
Sherwood Close Phase 3 EalingSherwood Close Phase 3 Ealing
Sherwood Close Phase 3 EalingFiona Elton
 
Public cons boddingtons v10 fc
Public cons boddingtons v10 fcPublic cons boddingtons v10 fc
Public cons boddingtons v10 fcFiona Elton
 
2019 Comprehensive Plan and UDO Annual Review
2019 Comprehensive Plan and UDO Annual Review2019 Comprehensive Plan and UDO Annual Review
2019 Comprehensive Plan and UDO Annual ReviewCity of College Station
 
6620 Victoria Avenue Comp Plan Amendment
6620 Victoria Avenue Comp Plan Amendment6620 Victoria Avenue Comp Plan Amendment
6620 Victoria Avenue Comp Plan AmendmentCity of College Station
 
Planning Staff Report Elizabeth Ann Seton 2010 Oct 14
Planning Staff Report Elizabeth Ann Seton 2010 Oct 14Planning Staff Report Elizabeth Ann Seton 2010 Oct 14
Planning Staff Report Elizabeth Ann Seton 2010 Oct 14Adam Cohen
 

Mais procurados (19)

Item #3 PPT 320 Alta
Item #3  PPT 320 AltaItem #3  PPT 320 Alta
Item #3 PPT 320 Alta
 
Eastern market metro park project community meeting 07-22-2020
Eastern market metro park project community meeting  07-22-2020Eastern market metro park project community meeting  07-22-2020
Eastern market metro park project community meeting 07-22-2020
 
Aggieland Outfitters Rezoning on Fairview Avenue
Aggieland Outfitters Rezoning on Fairview AvenueAggieland Outfitters Rezoning on Fairview Avenue
Aggieland Outfitters Rezoning on Fairview Avenue
 
Emmp community meeting 04 07-31-2019
Emmp community meeting 04 07-31-2019Emmp community meeting 04 07-31-2019
Emmp community meeting 04 07-31-2019
 
Applicant Presentation -- Aggieland Outfitters Rezoning
Applicant Presentation -- Aggieland Outfitters RezoningApplicant Presentation -- Aggieland Outfitters Rezoning
Applicant Presentation -- Aggieland Outfitters Rezoning
 
Item #5 PPT Broadway Ellwood
Item #5   PPT Broadway EllwoodItem #5   PPT Broadway Ellwood
Item #5 PPT Broadway Ellwood
 
High path phase 4 7 webinar rev a-fc
High path phase 4 7 webinar rev a-fcHigh path phase 4 7 webinar rev a-fc
High path phase 4 7 webinar rev a-fc
 
Medical District Trunk Line Easement on Park Property
Medical District Trunk Line Easement on Park PropertyMedical District Trunk Line Easement on Park Property
Medical District Trunk Line Easement on Park Property
 
Foxhall w street community meeting-flyer
Foxhall w street  community meeting-flyerFoxhall w street  community meeting-flyer
Foxhall w street community meeting-flyer
 
Sherwood Close Phase 3 Ealing
Sherwood Close Phase 3 EalingSherwood Close Phase 3 Ealing
Sherwood Close Phase 3 Ealing
 
Beaufort-Sector1-Charrette-FinalPresentation
Beaufort-Sector1-Charrette-FinalPresentationBeaufort-Sector1-Charrette-FinalPresentation
Beaufort-Sector1-Charrette-FinalPresentation
 
Sectors 2 & 3 Charrette Closing Presentation
Sectors 2 & 3 Charrette Closing PresentationSectors 2 & 3 Charrette Closing Presentation
Sectors 2 & 3 Charrette Closing Presentation
 
Public cons boddingtons v10 fc
Public cons boddingtons v10 fcPublic cons boddingtons v10 fc
Public cons boddingtons v10 fc
 
2019 Comprehensive Plan and UDO Annual Review
2019 Comprehensive Plan and UDO Annual Review2019 Comprehensive Plan and UDO Annual Review
2019 Comprehensive Plan and UDO Annual Review
 
6620 Victoria Avenue Comp Plan Amendment
6620 Victoria Avenue Comp Plan Amendment6620 Victoria Avenue Comp Plan Amendment
6620 Victoria Avenue Comp Plan Amendment
 
Cc 5 14-13 - planning
Cc 5 14-13 - planningCc 5 14-13 - planning
Cc 5 14-13 - planning
 
Planning Staff Report Elizabeth Ann Seton 2010 Oct 14
Planning Staff Report Elizabeth Ann Seton 2010 Oct 14Planning Staff Report Elizabeth Ann Seton 2010 Oct 14
Planning Staff Report Elizabeth Ann Seton 2010 Oct 14
 
Civic master plan overview presentation - March 20, 2013
Civic master plan overview presentation - March 20, 2013Civic master plan overview presentation - March 20, 2013
Civic master plan overview presentation - March 20, 2013
 
CRED Apartments Rezoning
CRED Apartments RezoningCRED Apartments Rezoning
CRED Apartments Rezoning
 

Semelhante a May 8, 2012 Commission Presentation

Final acec design summit pres 2017
Final acec design summit pres 2017Final acec design summit pres 2017
Final acec design summit pres 2017melissanatech
 
SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)dgonano
 
Allen Road - Eglinton West Station: Preliminary Design Consultation
Allen Road - Eglinton West Station: Preliminary Design ConsultationAllen Road - Eglinton West Station: Preliminary Design Consultation
Allen Road - Eglinton West Station: Preliminary Design ConsultationCrosstown TO
 
Allen Road - Eglinton West Station: Preliminary Design Consultation
Allen Road - Eglinton West Station: Preliminary Design ConsultationAllen Road - Eglinton West Station: Preliminary Design Consultation
Allen Road - Eglinton West Station: Preliminary Design ConsultationCrosstown TO
 
Link And Place A Guide To Street Planning And Design By Prof Peter Jones
Link And Place   A Guide To Street Planning And Design By Prof Peter JonesLink And Place   A Guide To Street Planning And Design By Prof Peter Jones
Link And Place A Guide To Street Planning And Design By Prof Peter Jonesgueste0b5fe
 
Link And Place A Guide To Street Planning And Design By Prof Peter Jones
Link And Place   A Guide To Street Planning And Design By Prof Peter JonesLink And Place   A Guide To Street Planning And Design By Prof Peter Jones
Link And Place A Guide To Street Planning And Design By Prof Peter JonesEngineers Australia
 
Link And Place A Guide To Street Planning And Design By Prof Peter Jones
Link And Place   A Guide To Street Planning And Design By Prof Peter JonesLink And Place   A Guide To Street Planning And Design By Prof Peter Jones
Link And Place A Guide To Street Planning And Design By Prof Peter JonesEngineers Australia
 
I-75 / University Drive: An Interchange Under Pressure Becomes a Diamond
I-75 / University Drive: An Interchange Under Pressure Becomes a DiamondI-75 / University Drive: An Interchange Under Pressure Becomes a Diamond
I-75 / University Drive: An Interchange Under Pressure Becomes a DiamondOHM Advisors
 
Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...mecocca5
 
Bridge Asthetic Fundamentals.pptx
Bridge Asthetic Fundamentals.pptxBridge Asthetic Fundamentals.pptx
Bridge Asthetic Fundamentals.pptxecep nurali
 
Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016VDOT Northern Virginia
 
cost_corrosion corrosion resistancea.ppt
cost_corrosion corrosion resistancea.pptcost_corrosion corrosion resistancea.ppt
cost_corrosion corrosion resistancea.pptMohankumar612520
 
Rethinking Urban Highways
Rethinking Urban HighwaysRethinking Urban Highways
Rethinking Urban Highwayssneapa
 
Creating great neighborhoods along el camino real
Creating great neighborhoods along el camino realCreating great neighborhoods along el camino real
Creating great neighborhoods along el camino realgbeltalliance
 
module20120PPT.pdf
module20120PPT.pdfmodule20120PPT.pdf
module20120PPT.pdfRakeshH21
 

Semelhante a May 8, 2012 Commission Presentation (20)

Final acec design summit pres 2017
Final acec design summit pres 2017Final acec design summit pres 2017
Final acec design summit pres 2017
 
SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)
 
BIM-Pier5
BIM-Pier5BIM-Pier5
BIM-Pier5
 
Allen Road - Eglinton West Station: Preliminary Design Consultation
Allen Road - Eglinton West Station: Preliminary Design ConsultationAllen Road - Eglinton West Station: Preliminary Design Consultation
Allen Road - Eglinton West Station: Preliminary Design Consultation
 
Allen Road - Eglinton West Station: Preliminary Design Consultation
Allen Road - Eglinton West Station: Preliminary Design ConsultationAllen Road - Eglinton West Station: Preliminary Design Consultation
Allen Road - Eglinton West Station: Preliminary Design Consultation
 
Link And Place A Guide To Street Planning And Design By Prof Peter Jones
Link And Place   A Guide To Street Planning And Design By Prof Peter JonesLink And Place   A Guide To Street Planning And Design By Prof Peter Jones
Link And Place A Guide To Street Planning And Design By Prof Peter Jones
 
Link And Place A Guide To Street Planning And Design By Prof Peter Jones
Link And Place   A Guide To Street Planning And Design By Prof Peter JonesLink And Place   A Guide To Street Planning And Design By Prof Peter Jones
Link And Place A Guide To Street Planning And Design By Prof Peter Jones
 
Link And Place A Guide To Street Planning And Design By Prof Peter Jones
Link And Place   A Guide To Street Planning And Design By Prof Peter JonesLink And Place   A Guide To Street Planning And Design By Prof Peter Jones
Link And Place A Guide To Street Planning And Design By Prof Peter Jones
 
I-75 / University Drive: An Interchange Under Pressure Becomes a Diamond
I-75 / University Drive: An Interchange Under Pressure Becomes a DiamondI-75 / University Drive: An Interchange Under Pressure Becomes a Diamond
I-75 / University Drive: An Interchange Under Pressure Becomes a Diamond
 
Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...
 
Bridge Asthetic Fundamentals.pptx
Bridge Asthetic Fundamentals.pptxBridge Asthetic Fundamentals.pptx
Bridge Asthetic Fundamentals.pptx
 
DDI Presentation
DDI PresentationDDI Presentation
DDI Presentation
 
Bridge
BridgeBridge
Bridge
 
Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016
 
cost_corrosion corrosion resistancea.ppt
cost_corrosion corrosion resistancea.pptcost_corrosion corrosion resistancea.ppt
cost_corrosion corrosion resistancea.ppt
 
Ilia Mayer
Ilia MayerIlia Mayer
Ilia Mayer
 
Rethinking Urban Highways
Rethinking Urban HighwaysRethinking Urban Highways
Rethinking Urban Highways
 
Creating great neighborhoods along el camino real
Creating great neighborhoods along el camino realCreating great neighborhoods along el camino real
Creating great neighborhoods along el camino real
 
module20120PPT.pdf
module20120PPT.pdfmodule20120PPT.pdf
module20120PPT.pdf
 
successful applications of project visualization
successful applications of project visualizationsuccessful applications of project visualization
successful applications of project visualization
 

Mais de Iowa Department of Transportation

Mais de Iowa Department of Transportation (20)

Implements of Husbandry
Implements of HusbandryImplements of Husbandry
Implements of Husbandry
 
Cargo Securement Rules
Cargo Securement RulesCargo Securement Rules
Cargo Securement Rules
 
Legal weights and tonnage
Legal weights and tonnageLegal weights and tonnage
Legal weights and tonnage
 
Farm exemptions
Farm exemptionsFarm exemptions
Farm exemptions
 
What do I need?
What do I need?What do I need?
What do I need?
 
When is it a CV?
When is it a CV?When is it a CV?
When is it a CV?
 
I-74 Final Design - Corridor Wide Landscape
I-74 Final Design - Corridor Wide LandscapeI-74 Final Design - Corridor Wide Landscape
I-74 Final Design - Corridor Wide Landscape
 
I-74 Final Design - Aesthetics
I-74 Final Design - AestheticsI-74 Final Design - Aesthetics
I-74 Final Design - Aesthetics
 
I-29 Reconstruction 2014
I-29 Reconstruction 2014I-29 Reconstruction 2014
I-29 Reconstruction 2014
 
Water, Water Everywhere
Water, Water EverywhereWater, Water Everywhere
Water, Water Everywhere
 
Fuel Management
Fuel Management Fuel Management
Fuel Management
 
Thinking Outside the Box
Thinking Outside the BoxThinking Outside the Box
Thinking Outside the Box
 
Where Will the $$ Come From?
Where Will the $$ Come From?Where Will the $$ Come From?
Where Will the $$ Come From?
 
Water, Water Everywhere
Water, Water EverywhereWater, Water Everywhere
Water, Water Everywhere
 
Thinking Outside of the Box
Thinking Outside of the BoxThinking Outside of the Box
Thinking Outside of the Box
 
So You Want to Ship by Rail?
So You Want to Ship by Rail?So You Want to Ship by Rail?
So You Want to Ship by Rail?
 
Land of Two Rivers
Land of Two RiversLand of Two Rivers
Land of Two Rivers
 
Fuel Management
Fuel ManagementFuel Management
Fuel Management
 
So You Want to Ship by Rail?
So You Want to Ship by Rail?So You Want to Ship by Rail?
So You Want to Ship by Rail?
 
Land of Two Rivers
Land of Two Rivers Land of Two Rivers
Land of Two Rivers
 

May 8, 2012 Commission Presentation

  • 1. I-74 Iowa-Illinois Corridor Presentation to: Iowa DOT Commission May 8, 2012 Ames, Iowa Mitchell Dillavou– Director, Engineering Bureau
  • 2. 1935 • Original bridge Original bridge opened. • Cost: $1.5 million
  • 3. 1960 • Second bridge opened. • Cost: $6.2 million
  • 4. 1970’s • Iowa and Illinois took over ownership • Toll Booths Removed. • I-74 was connected.
  • 5. Today • 2010 traffic: 61,500 vehicles per day • 2035 estimated traffic: 98,500 VPD • Poor geometrics for an interstate route • The bridges are functionally obsolete
  • 6. 1998 Major Investment Study Needed Improvement Locations
  • 7. I-74 Corridor Study Milestones 2000: I-74 Corridor Study began 2003: Draft Environmental Impact Study completed 2005: Preferred Alternative identified 2006: Main Span Bridge Type chosen 2007: Preliminary Engineering completed 2009: Final Environmental Impact Study, and Federal Highway Admin. Record of Decision
  • 9. Mississippi River Crossing Preferred Alternative
  • 10. Finalist Bridge Types • Scheme 1 - Basket Handle True Arch Twin Bridge •Aerial view •River view •Bettendorf shoreline view •Approach view •Motorist’s view
  • 11. Finalist Bridge Types •Scheme 2 - Modified Basket Handle Tied Arch Twin Bridges with Vertical Pier and Vertical Hangers •Aerial view •River view •Bettendorf shoreline view •Approach view •Motorist’s view
  • 12. Finalist Bridge Types •Scheme 3 - Basket Handle Tied Arch Twin Bridges with Vertical Pier and Vertical Hangers •Aerial view •River view •Bettendorf shoreline view •Approach view •Motorist’s view
  • 13. Finalist Bridge Types • Scheme 4 - Cable Stayed Single Bridge with Semi-Fan Stay Arrangement •Aerial view •River view •Bettendorf shoreline view •Approach view •Motorist’s view
  • 14. Selected Alternative: Basket Handle True Arch Twin Bridge
  • 16. Central Section Cost Estimate (YOE)
  • 17.
  • 18. Central Section Design Preliminary Design • Completed in April 2009 • $9.1 Million in Consultant Services (Iowa share) • $0.3 Million Iowa DOT Staff Final Design • $9.7 Million expended to date (Iowa Share) • 71% Complete • $13.0 Million Consultant Services funds to be expended (Iowa share) • $5.5 Million Iowa DOT Staff funds to be expended
  • 19. Iowa ROW Summary ROW Purchased (Central & North Sections) • 47 Parcels • $6.9 Million ROW to be Purchased (Central Section) • 79 Parcels • $16.9 Million
  • 20. Illinois ROW Summary ROW Purchased • 7 Parcels • $0.7 Million ROW to be Purchased • 59 Parcels • $3.8 Million
  • 21. Iowa Investment to Date • ROW $ 6.9 Million • Design $19.5 Million • Construction $16.3 Million • Iowa DOT Staff $ 2.1 Million Total $44.8 Million
  • 22. Iowa Cost Estimate Phase I 2013-2017 ROW $16.9 M Construction $13.7 M Maintenance of Existing Bridges $ 2.3 M Iowa DOT Staff $ 5.5 M Consultant Engineering (design) $13.0 M $51.4 M
  • 23. Iowa Cost Estimate Phase II – Central Section Beyond 2017, $ in YOE Main Span $118.2 M Approach Span $123.1 M Viaducts $128.9 M Mainline Roadway $ 40.2 M Bridge Demolition $ 15.3 M Maintenance of Existing Bridges $ 3.5 M Lighting, Signing, Landscaping, ITS $ 23.5 M Consultant Engineering (Constr.) $ 40.9 M Iowa DOT Staff $ 1.0 M $494.6 M
  • 24. Illinois Cost Estimate Phase II – Central Section Beyond 2017, $ in YOE Main Span $118.2 M Approach Span $123.1 M Viaducts & Mainline Roadway $356.1 M Bridge Demolition $ 17.2 M Lighting, Landscaping, ITS $ 10.1 M Consultant Engineering (Constr.) $ 40.9 M $665.6 M
  • 25. Central Section Cost Estimate YOE IOWA ILLINOIS $494.6 M $665.6 M
  • 26. Iowa Cost Estimate Totals • Completed Work $ 44.8 M • Phase I $ 51.4 M • Phase II $494.6 M • Phase III (North Section) $202.5 M Total Cost $793.3 M
  • 27. Anticipated Maintenance Cost (Iowa Share) Option 1 – In service until 2025 • Main Bridge $ 3.0 M • Approach Bridges $ 2.8 M • Total $ 5.8 M Option 2 – In service until 2035 • Main Bridge $14.2 M • Approach Bridges $ 8.7 M • Total $22.9 M
  • 28. Corridor Federal Funding • Earmarks $74.6 Million • Unobligated Amount $ 7.2 Million

Notas do Editor

  1. The Draft EIS in 2003 included 3 river crossing options and 2 interchange configurations at each local service interchange. In January 2005, the DOTs along with the MPO Bi-State, identified at the Preferred Alternative. For each interchange location, the community where the interchange was located was consulted about their preferences for the local access configuration. In 2004, we undertook additional traffic and operational studies in Davenport, Bettendorf and Moline to confirm the interchange operations and gain a consensus on the preferred design. This was a key element and the DOTs and study team took great efforts to work with our local partners so each jurisdiction was in support of the Preferred Alternative. I-74 would be widened and reconstructed to 3 basic lanes in each direction, with auxilliary lanes in much of the corridor. I-74 would be widened and reconstructed to 3 basic lanes in each direction, with auxilliary lanes in much of the corridor.