Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
I’m so efficient 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Good work! 
Keep it up. 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Everyone is busy 
but we seem to 
get nothing done! 
How are 
we doing? 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Håkan Forss 
Agile Coach 
@hakanforss
We make great games 
- More than 200 titles played in over 
200 countries around the world 
- 348 million average monthly unique 
users 
- More than 1.4 billion average daily 
game plays 
- Studios in Barcelona, Berlin, 
Bucharest, London, Malmo and 
Stockholm, Singapore 
As of Q3 2014 
About King 
© King.com Ltd 2014 – Commercially confidential
© King Digital Entertainment plc 2014 
Some of our games
Agile/Scrum/XP 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Lean, Kanban & Flow 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
I’m a huge LEGO fan! 
DISCLAIMER 
LEGO® is a trademark of the LEGO Group, 
which does not sponsor, authorize or 
endorse this presentation. 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
What is the difference? 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
A Question of Focus 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Which process is most expensive? 
≥ 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Niklas Modig 
Stockholm School of Economics 
@LeanOnMyself 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Strategy to increase utilization 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Strategy to fulfill needs a.s.a.p. 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Low utilization 
Short lead-times 
Low Work-In-Process 
Small batches 
Focus on customer value 
Little waiting for flow unit 
Fast to respond to change 
High utilization 
Long lead-times 
High Work-In-Process 
Large batches 
Focus on unit cost 
Lots of waiting for flow unit 
Slow to respond to change 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
We need to 
Shift our focus 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
BUSY WORKERS 
High Resource Efficiency 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
BUSY FLOW UNITS 
High Flow Efficiency 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Flow efficiency 
Touch time 
Total lead-time 
Flow efficiency = 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand Support team responds 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Flow efficiency 
Green + Yellow 
Green + Yellow + Red 
Flow efficiency = 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Flow efficiency in numbers 
Usually 1-5% value added of 
total lead-time 
20% value added is a high 
number 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
How many 
and 
bricks do you have? 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Use historical data 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
How to improve 
Flow Efficiency? 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Start with the bricks 
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand
Non value adding 
bricks: Wait time 
Waiting in a queue 
Waiting for a decision 
Waiting on dependency 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Then take on the bricks 
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Non value adding 
bricks: Required waste 
Over processing 
Backlog maintenance 
Reporting and status meetings 
Rework due to 
Defects 
Handovers 
Long feedback cycles (long lead-times) 
Lack of understanding the requirements 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Yes!! But how? 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
That which optimizes 
one part of the system 
necessarily undermines 
the system as a whole. 
Eric Ries 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
We need to 
Shift our focus 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
From local awareness… 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
..to global awareness 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
…to a shared and visual 
understanding of End-To-End flow 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
We need to 
Shift our focus 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Blockers and Impediments 
are like Gold and Gems 
for improving flow 
in your process 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
We are 
too busy 
No 
thanks! 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Lower planned utilization 
Time 
Capability 
100% 
Inspired by Mårten Pehrson 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Acts as an insurance policy for 
Lead-time Insurance 
Time 
Capability 
100% 
Utilization 
planed at 70% 
shorter lead-time 
Inspired by Mårten Pehrson 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Creates option to do the important 
things when you need it 
Options 
Time 
Capability 
100% 
Utilization 
planed at 70% 
Inspired by Mårten Pehrson 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Absorbs unwanted variation 
Time 
Capability 
100% 
Utilization 
planed at 70% 
Inspired by Mårten Pehrson 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Creates the time for increasing capability 
Time 
Capability 
100% 
Utilization 
planed at 70% 
Inspired by Mårten Pehrson 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Plan for less than 100% utilization 
Time 
Capability 
100% 
Utilization 
planed at 70% 
Inspired by Mårten Pehrson 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Improvements are experiments 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Puff 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Oh, I did NOT 
expect that! 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
The sound of learning 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Hypothesis 
Prediction 
Experiment 
Observation 
Learning 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Prediction 
Observation 
Observation 
Hypothesis 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Expect at least 50% of the 
experiments will not give the 
expected result 
This is when we REALLY learn! 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Actively encourage an 
experimentation culture 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
A/B test your 
Way of Working 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Build daily habits so you can keep it up 
If you don’t keep it up, the weeds will grow back 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Make improvements 
in small batches, Every Day! 
Daily work 
Delivering value 
Improving 
the work 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
I’m so efficient 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
See the bigger system 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Don’t be too busy to improve? 
We are 
too busy 
No 
thanks! 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Improve through Experimentation 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
“A bad system will beat a 
good person every time.” 
W. Edwards Deming 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Q & A 
Håkan Forss 
Mail: hakan.forss@king.com 
Twitter: @hakanforss 
Blog: http://hakanforss.wordpress.com 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
We are 
too busy 
No 
thanks! 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Don’t Be(e) a busy worker! 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
I’m so 
efficient 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Great work 
Maria! 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com 
Just a few 
more shots
Set WIP Limits on every 
process stage! 
Backpressure 
Stage 2 
Demand Stage 1 Stage 3 
WIP Limit WIP Limit 
WIP Limit 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Why Work-In-Process and 
not Work-in-Progress? 
Non value adding: Wait time 
Non value adding: Required waste 
Value adding: Actual demand 
You tell me! 
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com

Mais conteúdo relacionado

Mais procurados

Stop doing Retrospective and Start your Toyota Kata
Stop doing Retrospective and Start your Toyota KataStop doing Retrospective and Start your Toyota Kata
Stop doing Retrospective and Start your Toyota KataHåkan Forss
 
Toyota kata – habits for continuous improvements MIX IT 2014-04-29
Toyota kata – habits for continuous improvements MIX IT 2014-04-29Toyota kata – habits for continuous improvements MIX IT 2014-04-29
Toyota kata – habits for continuous improvements MIX IT 2014-04-29Håkan Forss
 
Toyota kata in knowledge work - European Lean Educator Conference 2014
Toyota kata in knowledge work - European Lean Educator Conference 2014Toyota kata in knowledge work - European Lean Educator Conference 2014
Toyota kata in knowledge work - European Lean Educator Conference 2014Håkan Forss
 
Busy Bee Paradox Krakow 2018-03-21
Busy Bee Paradox Krakow 2018-03-21Busy Bee Paradox Krakow 2018-03-21
Busy Bee Paradox Krakow 2018-03-21Håkan Forss
 
KATA - Habits for lean learning Agile Australia 2016
KATA - Habits for lean learning Agile Australia 2016KATA - Habits for lean learning Agile Australia 2016
KATA - Habits for lean learning Agile Australia 2016Håkan Forss
 
KataSummit 2015 Software Practitioners Panel
KataSummit 2015 Software Practitioners PanelKataSummit 2015 Software Practitioners Panel
KataSummit 2015 Software Practitioners PanelHåkan Forss
 
Toyota Kata - habits for continous learning. Shingo Institue European Confere...
Toyota Kata - habits for continous learning. Shingo Institue European Confere...Toyota Kata - habits for continous learning. Shingo Institue European Confere...
Toyota Kata - habits for continous learning. Shingo Institue European Confere...Håkan Forss
 
Kanban Kata - Lean Kanban European Conference Tour 2012
Kanban Kata - Lean Kanban European Conference Tour 2012Kanban Kata - Lean Kanban European Conference Tour 2012
Kanban Kata - Lean Kanban European Conference Tour 2012Håkan Forss
 
Make strategy happen with Hoshin Kanri and Toyota Kata Agile Australia
Make strategy happen with Hoshin Kanri and Toyota Kata Agile AustraliaMake strategy happen with Hoshin Kanri and Toyota Kata Agile Australia
Make strategy happen with Hoshin Kanri and Toyota Kata Agile AustraliaHåkan Forss
 
Make strategy happen with hoshin kanri and toyota kata lean agile brighton 20...
Make strategy happen with hoshin kanri and toyota kata lean agile brighton 20...Make strategy happen with hoshin kanri and toyota kata lean agile brighton 20...
Make strategy happen with hoshin kanri and toyota kata lean agile brighton 20...Håkan Forss
 
Make the invisible visible - Visual management in agile product development
Make the invisible visible - Visual management in agile product developmentMake the invisible visible - Visual management in agile product development
Make the invisible visible - Visual management in agile product developmentHåkan Forss
 
Toyota Kata Puzzle Experience Workshop
Toyota Kata Puzzle Experience WorkshopToyota Kata Puzzle Experience Workshop
Toyota Kata Puzzle Experience WorkshopHåkan Forss
 
Toyota kata – habits for continuous improvements by Hakan Forss
Toyota kata – habits for continuous improvements by Hakan ForssToyota kata – habits for continuous improvements by Hakan Forss
Toyota kata – habits for continuous improvements by Hakan ForssInstitut Lean France
 
Toyota kata – Agile saturday x 2014 02-15
Toyota kata – Agile saturday x 2014 02-15Toyota kata – Agile saturday x 2014 02-15
Toyota kata – Agile saturday x 2014 02-15Håkan Forss
 
Experimentation is King Lean Kanban Central Europe 2015
Experimentation is King Lean Kanban Central Europe  2015Experimentation is King Lean Kanban Central Europe  2015
Experimentation is King Lean Kanban Central Europe 2015Håkan Forss
 
Toyota Kata presented at DevoxxUK 2013
Toyota Kata presented at DevoxxUK 2013Toyota Kata presented at DevoxxUK 2013
Toyota Kata presented at DevoxxUK 2013Mattias Karlsson
 
Stop doing Retrospective and start your Toyota Kata - Devoxx 2013
Stop doing Retrospective and start your Toyota Kata - Devoxx 2013Stop doing Retrospective and start your Toyota Kata - Devoxx 2013
Stop doing Retrospective and start your Toyota Kata - Devoxx 2013Håkan Forss
 

Mais procurados (18)

Stop doing Retrospective and Start your Toyota Kata
Stop doing Retrospective and Start your Toyota KataStop doing Retrospective and Start your Toyota Kata
Stop doing Retrospective and Start your Toyota Kata
 
Toyota kata – habits for continuous improvements MIX IT 2014-04-29
Toyota kata – habits for continuous improvements MIX IT 2014-04-29Toyota kata – habits for continuous improvements MIX IT 2014-04-29
Toyota kata – habits for continuous improvements MIX IT 2014-04-29
 
Toyota kata in knowledge work - European Lean Educator Conference 2014
Toyota kata in knowledge work - European Lean Educator Conference 2014Toyota kata in knowledge work - European Lean Educator Conference 2014
Toyota kata in knowledge work - European Lean Educator Conference 2014
 
Busy Bee Paradox Krakow 2018-03-21
Busy Bee Paradox Krakow 2018-03-21Busy Bee Paradox Krakow 2018-03-21
Busy Bee Paradox Krakow 2018-03-21
 
KATA - Habits for lean learning Agile Australia 2016
KATA - Habits for lean learning Agile Australia 2016KATA - Habits for lean learning Agile Australia 2016
KATA - Habits for lean learning Agile Australia 2016
 
KataSummit 2015 Software Practitioners Panel
KataSummit 2015 Software Practitioners PanelKataSummit 2015 Software Practitioners Panel
KataSummit 2015 Software Practitioners Panel
 
Toyota Kata - habits for continous learning. Shingo Institue European Confere...
Toyota Kata - habits for continous learning. Shingo Institue European Confere...Toyota Kata - habits for continous learning. Shingo Institue European Confere...
Toyota Kata - habits for continous learning. Shingo Institue European Confere...
 
Kanban Kata - Lean Kanban European Conference Tour 2012
Kanban Kata - Lean Kanban European Conference Tour 2012Kanban Kata - Lean Kanban European Conference Tour 2012
Kanban Kata - Lean Kanban European Conference Tour 2012
 
Make strategy happen with Hoshin Kanri and Toyota Kata Agile Australia
Make strategy happen with Hoshin Kanri and Toyota Kata Agile AustraliaMake strategy happen with Hoshin Kanri and Toyota Kata Agile Australia
Make strategy happen with Hoshin Kanri and Toyota Kata Agile Australia
 
Make strategy happen with hoshin kanri and toyota kata lean agile brighton 20...
Make strategy happen with hoshin kanri and toyota kata lean agile brighton 20...Make strategy happen with hoshin kanri and toyota kata lean agile brighton 20...
Make strategy happen with hoshin kanri and toyota kata lean agile brighton 20...
 
Make the invisible visible - Visual management in agile product development
Make the invisible visible - Visual management in agile product developmentMake the invisible visible - Visual management in agile product development
Make the invisible visible - Visual management in agile product development
 
Toyota Kata Puzzle Experience Workshop
Toyota Kata Puzzle Experience WorkshopToyota Kata Puzzle Experience Workshop
Toyota Kata Puzzle Experience Workshop
 
Toyota kata – habits for continuous improvements by Hakan Forss
Toyota kata – habits for continuous improvements by Hakan ForssToyota kata – habits for continuous improvements by Hakan Forss
Toyota kata – habits for continuous improvements by Hakan Forss
 
Toyota kata – Agile saturday x 2014 02-15
Toyota kata – Agile saturday x 2014 02-15Toyota kata – Agile saturday x 2014 02-15
Toyota kata – Agile saturday x 2014 02-15
 
Experimentation is King Lean Kanban Central Europe 2015
Experimentation is King Lean Kanban Central Europe  2015Experimentation is King Lean Kanban Central Europe  2015
Experimentation is King Lean Kanban Central Europe 2015
 
Toyota Kata presented at DevoxxUK 2013
Toyota Kata presented at DevoxxUK 2013Toyota Kata presented at DevoxxUK 2013
Toyota Kata presented at DevoxxUK 2013
 
Stop doing Retrospective and start your Toyota Kata - Devoxx 2013
Stop doing Retrospective and start your Toyota Kata - Devoxx 2013Stop doing Retrospective and start your Toyota Kata - Devoxx 2013
Stop doing Retrospective and start your Toyota Kata - Devoxx 2013
 
How to use Dropbox
How to use DropboxHow to use Dropbox
How to use Dropbox
 

Mais de Håkan Forss

Handout to print on a3 - Toyota kata puzzle experience Lean Digital Summit Li...
Handout to print on a3 - Toyota kata puzzle experience Lean Digital Summit Li...Handout to print on a3 - Toyota kata puzzle experience Lean Digital Summit Li...
Handout to print on a3 - Toyota kata puzzle experience Lean Digital Summit Li...Håkan Forss
 
Kata experience experimentation form to print on a3
Kata experience experimentation form to print on a3Kata experience experimentation form to print on a3
Kata experience experimentation form to print on a3Håkan Forss
 
Reflection card to print on a4
Reflection card to print on a4Reflection card to print on a4
Reflection card to print on a4Håkan Forss
 
The red brick cancer - Modern Management Methods UK 2013 11-01
The red brick cancer - Modern Management Methods UK 2013 11-01The red brick cancer - Modern Management Methods UK 2013 11-01
The red brick cancer - Modern Management Methods UK 2013 11-01Håkan Forss
 
May the Forss be with you - Lean Kanban Centeral Europe 2012
May the Forss be with you - Lean Kanban Centeral Europe 2012May the Forss be with you - Lean Kanban Centeral Europe 2012
May the Forss be with you - Lean Kanban Centeral Europe 2012Håkan Forss
 
Lean lego – the red brick cancer
Lean lego – the red brick cancerLean lego – the red brick cancer
Lean lego – the red brick cancerHåkan Forss
 

Mais de Håkan Forss (7)

Handout to print on a3 - Toyota kata puzzle experience Lean Digital Summit Li...
Handout to print on a3 - Toyota kata puzzle experience Lean Digital Summit Li...Handout to print on a3 - Toyota kata puzzle experience Lean Digital Summit Li...
Handout to print on a3 - Toyota kata puzzle experience Lean Digital Summit Li...
 
Kata experience experimentation form to print on a3
Kata experience experimentation form to print on a3Kata experience experimentation form to print on a3
Kata experience experimentation form to print on a3
 
Reflection card to print on a4
Reflection card to print on a4Reflection card to print on a4
Reflection card to print on a4
 
The red brick cancer - Modern Management Methods UK 2013 11-01
The red brick cancer - Modern Management Methods UK 2013 11-01The red brick cancer - Modern Management Methods UK 2013 11-01
The red brick cancer - Modern Management Methods UK 2013 11-01
 
The two paths
The two pathsThe two paths
The two paths
 
May the Forss be with you - Lean Kanban Centeral Europe 2012
May the Forss be with you - Lean Kanban Centeral Europe 2012May the Forss be with you - Lean Kanban Centeral Europe 2012
May the Forss be with you - Lean Kanban Centeral Europe 2012
 
Lean lego – the red brick cancer
Lean lego – the red brick cancerLean lego – the red brick cancer
Lean lego – the red brick cancer
 

Último

Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxmavinoikein
 
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...Henrik Hanke
 
Early Modern Spain. All about this period
Early Modern Spain. All about this periodEarly Modern Spain. All about this period
Early Modern Spain. All about this periodSaraIsabelJimenez
 
miladyskindiseases-200705210221 2.!!pptx
miladyskindiseases-200705210221 2.!!pptxmiladyskindiseases-200705210221 2.!!pptx
miladyskindiseases-200705210221 2.!!pptxCarrieButtitta
 
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...漢銘 謝
 
Dutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular PlasticsDutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular PlasticsDutch Power
 
Quality by design.. ppt for RA (1ST SEM
Quality by design.. ppt for  RA (1ST SEMQuality by design.. ppt for  RA (1ST SEM
Quality by design.. ppt for RA (1ST SEMCharmi13
 
Event 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxEvent 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxaryanv1753
 
Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Escort Service
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Krijn Poppe
 
Anne Frank A Beacon of Hope amidst darkness ppt.pptx
Anne Frank A Beacon of Hope amidst darkness ppt.pptxAnne Frank A Beacon of Hope amidst darkness ppt.pptx
Anne Frank A Beacon of Hope amidst darkness ppt.pptxnoorehahmad
 
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.KathleenAnnCordero2
 
Genshin Impact PPT Template by EaTemp.pptx
Genshin Impact PPT Template by EaTemp.pptxGenshin Impact PPT Template by EaTemp.pptx
Genshin Impact PPT Template by EaTemp.pptxJohnree4
 
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.comSaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.comsaastr
 
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRachelAnnTenibroAmaz
 
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...marjmae69
 
PHYSICS PROJECT BY MSC - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC  - NANOTECHNOLOGYPHYSICS PROJECT BY MSC  - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC - NANOTECHNOLOGYpruthirajnayak525
 
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRRINDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRRsarwankumar4524
 
The Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationThe Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationNathan Young
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSebastiano Panichella
 

Último (20)

Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptx
 
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
 
Early Modern Spain. All about this period
Early Modern Spain. All about this periodEarly Modern Spain. All about this period
Early Modern Spain. All about this period
 
miladyskindiseases-200705210221 2.!!pptx
miladyskindiseases-200705210221 2.!!pptxmiladyskindiseases-200705210221 2.!!pptx
miladyskindiseases-200705210221 2.!!pptx
 
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
 
Dutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular PlasticsDutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
 
Quality by design.. ppt for RA (1ST SEM
Quality by design.. ppt for  RA (1ST SEMQuality by design.. ppt for  RA (1ST SEM
Quality by design.. ppt for RA (1ST SEM
 
Event 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxEvent 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptx
 
Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
 
Anne Frank A Beacon of Hope amidst darkness ppt.pptx
Anne Frank A Beacon of Hope amidst darkness ppt.pptxAnne Frank A Beacon of Hope amidst darkness ppt.pptx
Anne Frank A Beacon of Hope amidst darkness ppt.pptx
 
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
 
Genshin Impact PPT Template by EaTemp.pptx
Genshin Impact PPT Template by EaTemp.pptxGenshin Impact PPT Template by EaTemp.pptx
Genshin Impact PPT Template by EaTemp.pptx
 
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.comSaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
 
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
 
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...
Gaps, Issues and Challenges in the Implementation of Mother Tongue Based-Mult...
 
PHYSICS PROJECT BY MSC - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC  - NANOTECHNOLOGYPHYSICS PROJECT BY MSC  - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC - NANOTECHNOLOGY
 
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRRINDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
 
The Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationThe Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism Presentation
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
 

Håkan Forss Agile Coach Documents

  • 1. hakan.forss@king.com @hakanforss Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 2. I’m so efficient Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 3. Good work! Keep it up. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 4. Everyone is busy but we seem to get nothing done! How are we doing? Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 5. Håkan Forss Agile Coach @hakanforss
  • 6. We make great games - More than 200 titles played in over 200 countries around the world - 348 million average monthly unique users - More than 1.4 billion average daily game plays - Studios in Barcelona, Berlin, Bucharest, London, Malmo and Stockholm, Singapore As of Q3 2014 About King © King.com Ltd 2014 – Commercially confidential
  • 7. © King Digital Entertainment plc 2014 Some of our games
  • 8. Agile/Scrum/XP Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 9. Lean, Kanban & Flow Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 10. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 11. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 12. I’m a huge LEGO fan! DISCLAIMER LEGO® is a trademark of the LEGO Group, which does not sponsor, authorize or endorse this presentation. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 13. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 14. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 15. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 16. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 17. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 18. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 19. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 20. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 21. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 22. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 23. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 24. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 25. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 26. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 27. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 28. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 29. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 30. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 31. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 32. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 33. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 34. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 35. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 36. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 37. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 38. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 39. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 40. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 41. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 42. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 43. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 44. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 45. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 46. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 47. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 48. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 49. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 50. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 51. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 52. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 53. What is the difference? Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 54. A Question of Focus Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 55. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 56. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 57. Which process is most expensive? ≥ Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 58. Niklas Modig Stockholm School of Economics @LeanOnMyself Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 59. Strategy to increase utilization Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 60. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 61. Strategy to fulfill needs a.s.a.p. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 62. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 63. Low utilization Short lead-times Low Work-In-Process Small batches Focus on customer value Little waiting for flow unit Fast to respond to change High utilization Long lead-times High Work-In-Process Large batches Focus on unit cost Lots of waiting for flow unit Slow to respond to change Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 64. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 65. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 66. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 67. We need to Shift our focus Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 68. BUSY WORKERS High Resource Efficiency Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 69. BUSY FLOW UNITS High Flow Efficiency Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 70. Flow efficiency Touch time Total lead-time Flow efficiency = Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 71. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Support team responds Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 72. Flow efficiency Green + Yellow Green + Yellow + Red Flow efficiency = Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 73. Flow efficiency in numbers Usually 1-5% value added of total lead-time 20% value added is a high number Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 74. How many and bricks do you have? Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 75. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 76. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 77. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 78. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 79. Use historical data Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 80. Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 81. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 82. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 83. How to improve Flow Efficiency? Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 84. Start with the bricks Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand
  • 85. Non value adding bricks: Wait time Waiting in a queue Waiting for a decision Waiting on dependency Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 86. Then take on the bricks Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 87. Non value adding bricks: Required waste Over processing Backlog maintenance Reporting and status meetings Rework due to Defects Handovers Long feedback cycles (long lead-times) Lack of understanding the requirements Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 88. Yes!! But how? Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 89. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 90. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 91. That which optimizes one part of the system necessarily undermines the system as a whole. Eric Ries Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 92. We need to Shift our focus Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 93. From local awareness… Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 94. ..to global awareness Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 95. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 96. …to a shared and visual understanding of End-To-End flow Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 97. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 98. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 99. We need to Shift our focus Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 100. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 101. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 102. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 103. Blockers and Impediments are like Gold and Gems for improving flow in your process Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 104. We are too busy No thanks! Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 105. Lower planned utilization Time Capability 100% Inspired by Mårten Pehrson Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 106. Acts as an insurance policy for Lead-time Insurance Time Capability 100% Utilization planed at 70% shorter lead-time Inspired by Mårten Pehrson Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 107. Creates option to do the important things when you need it Options Time Capability 100% Utilization planed at 70% Inspired by Mårten Pehrson Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 108. Absorbs unwanted variation Time Capability 100% Utilization planed at 70% Inspired by Mårten Pehrson Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 109. Creates the time for increasing capability Time Capability 100% Utilization planed at 70% Inspired by Mårten Pehrson Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 110. Plan for less than 100% utilization Time Capability 100% Utilization planed at 70% Inspired by Mårten Pehrson Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 111. Improvements are experiments Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 112. Puff Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 113. Oh, I did NOT expect that! Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 114. The sound of learning Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 115. Hypothesis Prediction Experiment Observation Learning Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 116. Prediction Observation Observation Hypothesis Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 117. Expect at least 50% of the experiments will not give the expected result This is when we REALLY learn! Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 118. Actively encourage an experimentation culture Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 119. A/B test your Way of Working Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 120. Build daily habits so you can keep it up If you don’t keep it up, the weeds will grow back Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 121. Make improvements in small batches, Every Day! Daily work Delivering value Improving the work Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 122. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 123. I’m so efficient Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 124. See the bigger system Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 125. Don’t be too busy to improve? We are too busy No thanks! Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 126. Improve through Experimentation Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 127. “A bad system will beat a good person every time.” W. Edwards Deming Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 128. Q & A Håkan Forss Mail: hakan.forss@king.com Twitter: @hakanforss Blog: http://hakanforss.wordpress.com Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 129. We are too busy No thanks! Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 130. Don’t Be(e) a busy worker! Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 131. I’m so efficient Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 132. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 133. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 134. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 135. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 136. Great work Maria! Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com Just a few more shots
  • 137. Set WIP Limits on every process stage! Backpressure Stage 2 Demand Stage 1 Stage 3 WIP Limit WIP Limit WIP Limit Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 138. Why Work-In-Process and not Work-in-Progress? Non value adding: Wait time Non value adding: Required waste Value adding: Actual demand You tell me! Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
  • 139. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com