1. The Syspro (ERP) implementation at Tranter Rock Drills (TRD) Division of Labour The project was based on the roll-out executed at TRD. I acted as the facilitator to involve other group members to perform certain duties. Arno & Jan: Retail & Training. Gerrit & Werner: Manufacturing & Supply Chain. Overall consolidation & technical: Group. Group 6 MBA Modular (A) 2010Members:1. Gerrit Kamper Student #: 163993582. Jan van der Berg Student #: 163888013. Arno van der Merwe Student #: 163406124. Werner Botha Student #: 16396510
2. Tranter Rock Drills – A Business Introduction Tranter Rock Drills (TRD) is a leading manufacturer of percussive rock drill tools (products) and services to the natural resources industry. In addition we serve the construction, environmental, quarrying industries and industrial markets worldwide. Used in narrow vein stoping operations where the operator is usually in a crouched posture.
3. BOM Snapshot and Component Classification M – Manufactured B – Bought Out OUTP – Sub-Contracting FRONTHEAD MUFFLE BOX THROTTLE VALVE HANDLE STEEL RETAINER CYLINDER Bill of Material BACKHEAD AIR BEND
4. MXP & The Changeover The Changeover 1st July 2009 Tranter Rock Drills Negatives & Management issues No Executive Dashboard. Time Consuming. Could not perform Average Costing. “Flat” Rate costing system for Manufactured items. Implementation Time: Aug – Sep 2009 The Time Line
6. The Data & Rollout A snapshot of the upload format for SQL Phase 001 - The Data Integrity, Software & Hardware Phase 002 - Sales & Finance Phase 003 - Operations & Supply Chain Phase 004 - Research & Development Phase 005 - Dashboards, Individualised Reports & Close-out The Roll-out Plan Phase 001 Phase 002 Phase 003 The TRD IT infrastructure Phase 004 Training Test Company Train in the environment “Shadow” the users Phase 005 The Time Line Aug – Sep 2009
7. MXP & Syspro, the then and now High Cost COST RATE OF ALL WORK CENTRES IS R359.04 per hour Low Cost High Cost 2 3 1 Low Cost