2. Introduction
This presentation highlights some of
the retrofits that can be applied to
• Improve efficiency
• Increase production
Safety
Efficiency
Reliability
Throughput
Environment
3. Introduction
Why consider a retrofit?
Limitations
Options for retrofits
Problems and Pitfalls
GBHE Catalysts and Retrofits
Conclusions
4. Why Consider a Retrofit?
Plant is
• Inefficient
• Has poor economics
• Production can be increased by
elimination of bottlenecks
Retrofits generally are more cost
effective than new plant builds
8. Plant Limitations
Six main areas that can limit plant
performance
Primary
Convection Section
Air Compressor
and Secondary
Cooling, Shifts
and CO2 Removal
9. Plant Limitations
Six main areas that can limit plant
performance
Primary
Convection Section
Air Compressor
and Secondary
Cooling, Shifts
and CO2 Removal
Compression
10. Plant Limitations
• Six main areas that can limit plant performance
Primary
Convection Section
Air Compressor
and Secondary
Cooling, Shifts
and CO2 Removal
Compression
Ammonia
Synthesis
11. Pre-Reformers
Installation of pre-reformer helps to
de bottleneck
• The primary reformer - reduced box
duty
• The convection section - heat removal
• Eliminates heavies/ poisons
Can increase plant rate by up to
11%
Will affect steam balance
12. Change Catalyst Shape and
Size
By optimizing catalyst size can
• Reduce pressure drop by up to 33%
• Reduce carbon formation potential
By changing to VULCAN VSG-Z101 can
• Reduce ATE/CH4 slip
• Reduce Tube Wall Temperatures
• Reduce carbon formation potential
• Optimize catalyst loading even further
13. Primary Reformer Re-Tube
By re-tubing reformer can generate
large benefits
• Reduce pressure drop by 20%
• Improve radiant efficiency
• Reduce tube wall temperature
• Increased plant rate by 3.5%
• Further optimize catalyst loading to
generate even more benefits
14. Combustion Air Pre-heat
Installed on many modern plants
Has been retrofitted to many plants
Must have high stack temperature
Allows for large improvements in radiant
efficiency
• Use less fuel
Can allow for plant increases
Will increase NOx levels
• May require NOx reduction system
15. Options for Secondary Reformers
Install High Intensity
Burner Gun
Install improved
catalyst
• Reduce installed
volume - up to 45%
• Increase mixing volume
Add excess process air
• Requires H2 recovery in
loop
16. VULCAN SG Delta Retrofit for Shift
Vessels
By installing a specialized support
system we can reduce pressure drop
significantly
GBHE can offer the VULCAN SG Delta
which can reduce pressure drop by 50%
Allows plant rate increases of up to
0.5%
17. CO2 Removal Retrofits
Can uprate CO2 removal by
• Changing packing
• Use more efficient solution
Either will help to reduce reboiler duties
• In turn allows reduction in steam to carbon
ratio
GBH Enterprises range of catalysts are
designed to operate under these lower
steam to carbon conditions
18. Water Removal from Synthesis
Gas
Use either molecular sieves or ammonia
washing
Can feed synthesis gas to converter inlet
• Reduces ammonia content of gas inlet
converter therefore increases production
• Reduced refrigeration load
• No loss of reactants in purge gas
19. Converter Retrofits
Convert to axial-radial or radial flow
Utilize smaller catalyst
• Since reaction is diffusion limited
increases reaction rate and therefore
increased production
• Can improve efficiency by 0.5-1.0 GJ/t
• Must look at rest of plant
Converter exit piping and exchangers
20. Converter Retrofits
Often link with modifications to circulator
• Reduce circulation rate and hence power
requirement
If converter already modified then can
• Modify converter again
Use heat exchange rather than quench
• Install high activity catalyst
VULCAN Series VSG-A101 low pressure
synthesis
Can be utilized up to 150 bara
21. Converter Retrofits
Further Options
• Add a booster converter
Utilize when main converter has reached limit
Can achieve up to 30% capacity increases
Will need modifications to rest of the plant
• Add a synthesis gas converter - for example as
done in the Uhde DPUP
Utilize when main converter has reached limit
Can achieve up to 30% capacity increases
Will need modifications to rest of the plant
22. Hydrogen Recovery
Can increase plant capacity by up to 5%
with no other modifications
Either
• Cryogenic
• Membrane
If adding excess air to the secondary then
must install hydrogen recovery
• Even greater capacity increases are achievable
since methane slip has been reduced
23. Other Retrofits
Addition of Saturator
Fuel gas preheat
Synthesis gas machine suction
chilling
Modification of synthesis gas
machine internals
Install AGHR in parallel to existing
Waste Heat Boiler
Upgrade utilities
24. Other Options
There are other options
There are a number of operational
modifications that will improve plant
performance for no cost
• Reduction in steam to carbon
• Raising primary exit temperature
• Reduce excess air/oxygen in reformer
Energy Audits will help to identify these
areas and the benefits of changing
process parameters
25. Plant Revamp Selector
Ammonia – Capacity Increases
What capacity
increase is required ?
>15%
Front End
Catalyst change
Re-tube
New burner gun
VULCAN SG Delta
<5%
Front End
SC Reduction
Pre-reformer
5-15%
Compression/Loop
Syn gas drying
High activity catalyst
H2 recovery
Chill Syn Gas
Front End
Parallel AGHR
Re-tube
Loop
Booster converter
MUG converter
26. Plant Revamp Selector
Ammonia – Efficiency Improvements
What efficiency improvement
is required ?
>1 GJ/t<0.1 GJ/t
Front End
SC Reduction
Fuel preheat
CO2 solution change
Saturator
Chill syngas
0.1-1 GJ/t
Front End
Combustion air
preheat
None
27. Problems and Pitfalls
Contractor and Contract
Must carefully select partners
• Must have domain knowledge
Design and operations
• Must have correct tools
• Must be able to supply correct level of detail
for study
Must select appropriate contract type
• LSTK or Reimbursable
• Both have advantages and disadvantages
28. Problems and Pitfalls
Modelling Capability
Must use correct tools
Model the whole plant using a
flowsheeting package
• Must include all unit operations
• Must develop a robust base case
• Must validate against plant data
• Must understand deviations
• Then develop the retrofit case
29. Problems and Pitfalls
Retrofit Details
The customer and engineering contractor
must determine
• Precise scope for retrofit
• Responsibilities
• Key deliverables
• A detailed and consistent design basis
• Time scale and milestones
• Review schedules
Summarize as Good Project Management
30. Problems and Pitfalls
Design Basis
Engineering contractor must conduct on
site visit
• Must work with client
• Collect representative plant data
• Model and understand plant data
• Discuss discrepancies and eliminate
• Identify bottlenecks
• Identify opportunities for improvement
These form the core of the design basis
31. Problems and Pitfalls
HAZOPs and Commissioning
Must use systematic review method to highlight
potential problems with retrofit
• HAZOPs are a well proven system
• Requires time and buy in from all parties
• Results as good as quality of people !
Retrofit will change plant parameters
• Must update PFDs and P&IDs
• Must update operating instructions
• Must take additional care during start up
32. What Can GBHE Catalysts Offer?
GBHE Catalysts Process Technology has
developed a detailed flowsheeting package
GBHE Modelling for AMMONIA includes
• Detailed primary reformer model
• Models for secondary reformers, shifts, methanation and
ammonia synthesis
• Can model in detail the synthesis gas machine
Unified, consistent and intelligent process
model
33. What Can GBHE Catalyst Process
Technology Offer?
Detail catalyst unit operation models such as the
Industry leading VULCAN REFSIM program
• Also models for other catalyst unit operations
Detail non-catalyst unit operation models such as
• Heat exchange programs
• Finite Element Analysis
• CFD modelling
One stop shop
34. What Can GBHE Catalysts
Offer?
Domain Knowledge
• Operations
Many staff have operations
background
Troubleshooting clients plants
• Design
Many staff have detailed
engineering background
Engineers work on design daily
Work with leading contractors
on front end and detailed
design issues
Catalysts
Consulting
Services
Domain
Knowledge
35. What Can GBHE Catalysts
Offer?
Can supply any level of detail for
retrofit
Scoping studies
• Front End
• What are the best options
Front End Engineering
• Flowsheets and design of key components
Detailed Engineering
• Design of all components of retrofit
A one stop shop for all your revamp
requirements
36. One Stop Shop Case Study
Re-tube – Present Model
Plant
Operator
Concept
Engineer
Tube
Supplier
Catalyst
Vendor
Tube
Installer
Catalyst
Handler
No Communication
Detailed
Engineer
37. One Stop Shop Case Study
Re-tube – “One Stop Shop” Model
Plant
Operator
GBHE
Concept Engineer
Tube
Supplier
Tube
Installer
Catalyst
Handler
Detailed
Engineer
Seamless
Minimum Cost
Maximum Benefit
38. Case Study - How GBHE Works
Strong position due to credibility from previous
work
Uprate projects
• Feasibility Process Uprate study on Naphtha
115%, 130% or 150% cases
• FEEP (Front End Engineering Package, what
would be needed?)
115% FEEP adopted
• Option evaluations and natural gas feed
conversion
Followed by full Engineering Detail Design
Also additional design work on Desulfurization
Design Study
39. Conclusions
Many options for retrofitting an ammonia
plant
Must select correct options based on
• Require capacity increase
• Present bottlenecks
Must select the right contractor
GBHE has all the right expertise and
knowledge to develop and design retrofits