2. 2010 BOND PROGRAM UPDATE
TABLE OF CONTENTS
East View High School Phase 2 Additions, Package 1 3
East View High School Phase 2 Additions, Package 2 7
New Warehouse Facility 9
Annie Purl Elementary School Roof and HVAC Modifications 12
Georgetown High School Additions and Renovations 13
Huckabee
Georgetown Independent School District 2
3. 2010 BOND PROGRAM UPDATE General Contractor
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 1
Contract Amount: $5,321,000
Mezzanine
Mechanical
Storage
Weight Room
Junior Varsity Football
Locker Room
Main
B Mech.
Elec.
Storage Meeting Room
D Office Training
C Stor.
Laundry
A
Head AV IDF
Coach Stor. Elec.
A. New Football Field House Secre-
Lockers Jan. Freshman Football
B. New Concession/Restroom Bldg Varsity Football Locker Room tary Coaches Locker Room
C. New Grandstands for 2,500
D. New Field Events
Site Plan Football Field House - Floor Plan
Mechanical Electrical
Storage
Storage Storage
Concession
Women Men
Ticket-
In Out
ing
In Out
Family
RR
Stadium Restroom/Concession - Floor Plan
Conceptual 3D Rendering Huckabee
Georgetown Independent School District 3
4. 2010 BOND PROGRAM UPDATE General Contractor
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 1
PROGRESS REPORT
SITE
MILESTONE DATES
• The final grading has started on the East side of the site and progress will Schematic Design Presentation November 11, 2010
continue to be made towards the South side of the site.
• The sport light poles have been installed. Architect Signs Documents November 24, 2010
Pre-Proposal Meeting December 8, 2010
CONCESSION BUILDING
• The exterior masonry is complete and the interior is 80 percent complete. The Proposal Part A Due December 21, 2010
plumbing and electrical work will continue. Proposal Part B Due December 22, 2010
• The metal roof material has been installed and the trim installation has started.
Proposal Evaluations January 4, 2011
FIELD HOUSE
General Contractor Recommendation to School Board January 10, 2011
• The metal building is being installed and the placement of the roof has started.
• The interior masonry walls for the mezzanine are complete. First Owner/CO Meeting February 15, 2011
• The plumbing and electrical are currently being installed.
Construction Start Date February 18, 2011
FIELD/TRACK Building Permit Issued March 16, 2011
• The field has been laser graded. The liner and base stone have been installed
along with the field drainage system.
Substantial Completion (Field/Track and Bleachers) August 1, 2011
• The inside and outside track curbs are complete. Substantial Completion (Buildings) August 15, 2011
• The track base is being installed and the asphalt for the running surface will be
installed this week.
• The approved turf layout has been sent to the manufacturer. It will be two to four
weeks until the turf delivery.
BLEACHERS & PRESS BOX
• Overall, the grandstands are 90 percent complete. The grandstand piers are
complete. The press box framing is scheduled to begin in two weeks.
Huckabee
Georgetown Independent School District 4
5. 2010 BOND PROGRAM UPDATE
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 1
Parking Football
Field House
High Jump
Bleachers Concession/Restroom
Building
Field
Discus
Shot Put
Discus
Aerial
(Photo taken May 19, 2011)
Huckabee
Georgetown Independent School District 5
6. 2010 BOND PROGRAM UPDATE
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 1
Overall View of Football Field Football Field and Bleachers
Concession/Restroom Building Football Field House
Huckabee
Georgetown Independent School District 6
7. 2010 BOND PROGRAM UPDATE General Contractor
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2
Contract Amount: $25,574,000
I
New Athletic Addition
I
J
H
H
F
G J
H
J
First Floor
Bid Package 1
A
B J
Existing East View
J High School B
A. New Athletic Addition
B. New Fine Arts Addition New Fine Arts Addition
D
E C. New Academic Addition
C
D. New CTE Building
New Academic Addition
E. New ROTC Addition (Alt.)
CR
10 F. New Tennis Courts
4
ay
29 G. New Tennis Building
hw
Hig H. New Baseball/Softball Fieldhouse,
Bleachers, Lighting & Pressbox
I. New Practice Fields
J. New Parking (1,070 spaces)
New Academic Addition
CTE Building
Second Floor New CTE/ROTC Addition
Academic Wing Softball Field House Huckabee
Georgetown Independent School District 7
8. 2010 BOND PROGRAM UPDATE General Contractor
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2
PROGRESS REPORT
MILESTONE DATES
Schematic Design Presentation January 1, 2011
Architect Signs Documents March 8, 2011
Building Permit Application Submittal March 15, 2011
Site Plan Application Submittal March 17, 2011
Pre-Proposal Meeting March 22, 2011
Tour with General Contractors at East View Ninth Grade Center March 30, 2011
Proposal Part A Due April 7, 2011
Proposal Part B Due April 8, 2011
Proposal Evaluations April 11, 2011
Received City Building Dept.. Plan Review Comments April 14, 2011
General Contractor Recommendation to School Board April 18, 2011
Received City Planning Dept.. Plan Review Comments April 25, 2011
Construction Start Date May 19, 2011
First Owner/CO Meeting May 24, 2011
Building Permit Issued June 1, 2011
Substantial Completion June 27, 2012
Huckabee
Georgetown Independent School District 8
9. 2010 BOND PROGRAM UPDATE General Contractor
NEW WAREHOUSE FACILITY
Contract Amount: $641,000
Shed
Existing Support
Services
ALTERNATE #2
Warehouse Shop - Floor Plan
Facility
ALTERNATE #1
Warehouse Facility - Floor Plan
Existing Bus Wash Bay
Site Plan Huckabee
Georgetown Independent School District 9
10. 2010 BOND PROGRAM UPDATE General Contractor
NEW WAREHOUSE FACILITY
PROGRESS REPORT
SITE
MILESTONE DATES
• Building pad and site utilities are in place. Schematic Design Presentation January 10, 2011
BUILDING Architect Signs Documents January 12, 2011
• Underground plumbing is in place. Building Permit Application Submittal January 25, 2011
• Ninety percent of the concrete grade beams have been excavated.
• Concrete slab pour is scheduled for mid-July. Proposal Part A Due February 15, 2011
Proposal Part B Due February 16, 2011
Site Plan Application Submittal February 17, 2011
Proposal Evaluations February 17, 2011
Landscaping Plans Approved March 1, 2011
General Contractor Recommendation to School Board March 7, 2011
Job Coordination Meeting March 25, 2011
Grading/Utilities Permit Received March 31, 2011
First Amended Administrative Exception Submitted April 18, 2011
Second Amended Administrative Exception Submitted April 20, 2011
Final Planning Dept. Comments Received April 25, 2011
Building Permit Issued April 28, 2011
First Owner/CO Meeting May 5, 2011
Construction Start Date May 9, 2011
Substantial Completion August 12, 2011
Huckabee
Georgetown Independent School District 10
11. 2010 BOND PROGRAM UPDATE
NEW WAREHOUSE FACILITY
Building Pad - Warehouse Facility Building Pad - Three-Sided Storage Building
Huckabee
Georgetown Independent School District 11
12. 2010 BOND PROGRAM UPDATE General Contractor
ANNIE PURL ELEMENTARY SCHOOL ROOF AND HVAC MODIFICATIONS
Contract Amount: $229,000
MILESTONE DATES
Schematic Design Presentation January 10, 2011
Architect Signs Documents February 3, 2011
A
Pre-Proposal Meeting February 9, 2011
B B
HVAC Unit HVAC Unit
Proposal Part A Due February 22, 2011
Proposal Part B Due February 23, 2011
Proposal Evaluations February 24, 2011
Building Permit Issued March 2, 2011
General Contractor Recommended to School Board March 7, 2011
A. Replace Roof
B. New HVAC Units First Owner/CO Meeting May 24, 2011
A A C. New Metal Coping on Parapets
D. New Gutter and Downspouts Construction Start Date June 6, 2011
Substantial Completion August 12, 2011
C
B
HVAC Unit D
A
Roof Plan
Huckabee
Georgetown Independent School District 12
13. 2010 BOND PROGRAM UPDATE Construction Manager
GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS
BAIRD WILLIAMS
CONSTRUCTION
Project Manager
CTE Wing
Cafeteria
Athletics
Auditorium
Academic Athletics Athletics
Computer
Labs
Science
Labs
Library
Athletics
Special Education Academic
Fine
Arts
Huckabee
Georgetown Independent School District 13
14. 2010 BOND PROGRAM UPDATE Construction Manager
GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS
BAIRD WILLIAMS
CONSTRUCTION
Project Manager
MILESTONE DATES
Design Kick-off Meeting with Librarian, Science Dept..
February 28, 2011
and Nurse
Design Kick-off Meeting with Athletics March 1, 2011
Initial Construction Phasing with Stakeholders March 3, 2011
Design Kick-off Meeting with Special Education March 4, 2011 First Meeting with District, Architect, Project Manager
April 19, 2011
and Construction Manager
Design Kick-off Meeting with Administration March 10, 2011
Site Logistics Survey with District, Architect, Project
Advertisement for Construction Manager at Risk RFQ March 12, 2011 April 29, 2011
Manager and Construction Manager
Received Construction Manager at Risk Step 1
March 29, 2011 Schematic Design Presentation June 6, 2011
(Qualifications)
Architect Signs Documents August 19, 2011
Evaluation Team Grades and Develops Recommended
March 30, 2011 First Owner/CO Meeting TBD
Short List
Facility Assessment of ADA, Code and Existing Conditions March 29 - 30, 2011 Construction Start Date October 13, 2011
School Board Receives Recommended Short List April 4, 2011 Substantial Completion July 2013
Step 2 of RFQ Submitted to Short Listed Contractors
April 5, 2011
(Fees and General Conditions)
Fees and General Conditions due by 3 PM April 8, 2011
Board of Trustees Select Construction Manager at Risk April 18, 2011
Huckabee
Georgetown Independent School District 14