SlideShare uma empresa Scribd logo
1 de 14
MATERIAL AND CAPACITY REQUIREMENTS
PLANNING (MRP AND CRP)
Part -2
Dr. Mahmoud Abbas Mahmoud Al-Naimi
Assistant Professor
Industrial Engineering Branch
Department of Production Engineering and Metallurgy
University of Technology
Baghdad - Iraq
dr.mahmoudalnaimi@uotechnology.edu.iq
dr.mahmoudalnaimi@yahoo.com
2015 - 2016
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
1
6.3 MRP LOGIC
Following are some of the terms frequently used on (computerized) MRP planning
forms. Note, however, that not all programs use the same terms or provide the same
detail of information.
1. Gross requirements: Projected needs for raw materials, components,
subassemblies, or finished goods by the end of the period shown. Gross requirements
come from the master schedule (for end items) or from the combined needs of other
items.
2. Scheduled receipts: Materials already on order from a vendor or in-house shop
due to be received at the beginning of the period. MRP form shows quantity and
projected time of receipt. (Note: Some MRP forms include planned receipts here too.)
3. On hand/available: The quantity of an item expected to be available at the end of
the time period in which it is shown. This includes amount available from previous
period plus planned-order receipts and scheduled receipts less gross requirements.
4. Net requirements: Net amount needed in the period. This equals the gross
requirements less any projected inventory available from the previous period along
with any scheduled receipts.
5. Planned-order receipt: Materials that will be ordered from a vendor or in-house
shop to be received at the beginning of the period. Otherwise it is similar to a
scheduled receipt.
6. Planned-order release: The planned amount to be ordered in the time period
adjusted by the lead-time offset so that materials will be received on schedule. Once
the orders are actually released, the planned-order releases are deleted from the form
and the planned-order receipts they generated are changed to scheduled receipts.
The master production schedule dictates gross or projected requirements for end items
to the MRP system. Gross requirements do not take account of any inventory on hand
or on order. The MRP computer program then “explodes” the end-item demands into
requirements for components and materials by processing all relevant bills of materials
on a level-by-level (or single-level) basis. Net requirements are then calculated by
adjusting for existing inventory and items already on order as recorded in the
inventory status file.
Net requirements = gross requirements – (on hand/available + scheduled receipts) … 6.1
Order releases are planned for components in a time-phased manner (using lead-time
data from the inventory file) so that materials will arrive precisely when needed. At
this stage the material is referred to as a planned-order receipt. When the orders are
actually issued to vendors or to in-house shops, the planned receipts become scheduled
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
2
receipts. The inventory on hand at the end of a period is the sum of the previous period
on-hand amount plus any receipts (planned or scheduled) less the gross requirements.
On hand/available = on hand at end of previous period + receipts – gross requirements …6.2
ILLUSTRATION 4: A firm producing wheelbarrows is expected to deliver 40
wheelbarrows in week 1, 60 in week 4, 60 in week 6, and 50 in week 8. Among the
requirements for each wheelbarrow are two handlebars, a wheel assembly, and one
tire for the wheel assembly. Orders quantities, lead times, and inventories on hand at
the beginning of period 1 are shown in Table 6.5.
Table 6.5 BOM and inventory data for wheelbarrow components
*90 wheel assemblies are also needed in period 5 for a garden tractor shipment.
A shipment of 300 handlebars is already scheduled to be received at the beginning of
week 2 (i.e., a scheduled receipt). Complete the MRP for the handlebars, wheel
assemblies, and tires; and show what quantities or orders must be released and when
they must be released to satisfy the master schedule.
SOLUTION: Table 6.6 depicts the master schedule and component part schedules.
We shall assume that the customer completes the final assembly, so no time allowance
is required there. Note that because each wheelbarrow requires two handlebars, the
gross requirements for handlebars are double the number of end products. Thus the
gross requirements in period 1 are 40 × 2 = 80 units.
Table 6.6 (a) End item Master schedule; wheelbarrows
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
3
Table 6.6 (b) Master schedule and MRP component plans for wheelbarrows
* Requirements from another product (garden tractor) that uses the same wheel
assembly.
The 100 handlebars on hand at the beginning of period 1 are adequate to supply the
gross requirement of 80 handlebars, leaving 20 on hand at the end of period 1. With
the (scheduled) receipt of 300 handlebars in period 2, the on-hand inventory remains
adequate until the end of week 8, when 80 units are on hand. However, the gross
requirement for 100 units in period 9 exceeds the on-hand inventory. This results in
net requirements (using Eq. 6.1) of 100 – 80 = 20 units. To satisfy this, a planned-
order receipt for the standard order quantity (300) is scheduled for the beginning of
period 8. In so far as the handlebars have a 2 week lead-time, the planned order for the
Handle bars must be released 2 weeks earlier (week 6). The planned order receipt will
result in a projected end-of-period on-hand inventory (using Eq. 6.2) of 80 + 300 –
100 = 280 units.
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
4
6.4 SYSTEM REFINEMENTS
Key features of MRP systems are (1) the generation of lower-level requirements, (2)
time phasing of those requirements, and (3) the planned-order releases that flow from
them. Note particularly that planned-order releases of parent items generate gross
requirements at the component level (e.g., tires).
Additional features of many MRP systems are their capability to handle (a)
simulations, (b) firm-planned orders, (c) pegging, and (d) the availability of planning
bills of material.
Simulation: The simulation capability allows planners to “trial fit” a master schedule
onto the MRP system before the schedule is actually accepted and released. With this
feature, a planner can “try” a potential customer order on the system to see if materials
and delivery dates can be met even before the order is accepted. If lead times,
materials, and capacities are sufficient, the order can be accepted; otherwise, changes
in quantities or delivery times may have to be negotiated, or the order may even have
to be turned down.
Firm-Planned Orders: Sometimes the “normal” manufacturing times are not enough
to meet an emergency, secure a special order, or service a valued customer. Firm-
planned order capability enables planners to instruct the computer to accept certain
requirements, even though normal MRP logic would automatically delay or reschedule
such orders. By designating certain orders as “firm-planned orders,” planners can
ensure that the computer will not automatically change the release date, the planned-
order receipt date, or the order quantity. In addition, the system can establish a “time
fence” around the planned-order release date to preclude the scheduling of other
orders near that time so as to ensure that resources are available to do the special job.
Pegging: Pegging refers to the ability to work backward from component
requirements to identify the parent item, or items that generated those requirements.
For example, suppose an automobile manufacturer learned that some of the brake
materials (already used in production) were defective. The “where used” pegging file
would allow production analysts to trace requirements upward in the product structure
tree to determine what end-item models contained the defective components.
Modular and Planning Bills: Modular bills of materials describe the product
structure for basic subassemblies of parts that are common to different end items. For
example, several models of a manufacturer’s automobiles may contain the same
transmission, drive train, air-conditioning, and braking systems. By scheduling these
items as (common) modules, production can sometimes be more effectively
“smoothed” and inventory investment minimized.
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
5
6.5 SAFETY STOCK, LOT SIZING AND SYSTEM UPDATING
Safety stock: Note that the MRP component plan shown in Table 6.6 includes space
for an entry of safety stock. Although one of the reasons for using MRP to manage
dependent demand inventory items is to avoid the need for safety stock, in reality
firms may elect to carry safety stock on some items for a variety of reasons: Safety
stock amounts are sometimes deducted before showing the On hand/Available
quantities.
Following are some of the reasons for carrying safety stock of components on an MRP
format
1. Not all demand is dependent. Some items (e.g., repair parts) may have a service
requirement that has an independent demand component.
2. Variable lead times from suppliers are a common source of uncertainty to many
firms.
3. Firms may experience machine breakdowns, scrap losses, and last-minute customer
changes.
Lot sizing: Order quantities are not always specified in advance. Different lot-sizing
methods are in use, they are (1) fixed-order quantity amounts, e.g., 300 handlebars; (2)
EOQ amounts [EOQ method will be explained later on]; (3) lot for lot, which is
ordering the exact amount of the net requirements for each period; (4) fixed period
requirements, e.g., a 2-month supply; and (5) various least-cost approaches, e.g., least-
unit cost, least-total cost.
The part-period algorithm is a method that uses a ratio of ordering costs to carrying
costs per period, which yields a part-period number. Then requirements for current
and future periods are cumulated until the cumulative holding cost (in part-period
terms) is as close as possible to this number.
System updating: MRP system designs typically use one of two methods to process
data, update files, and ensure that the system information is valid and conforms with
actual: (1) regenerative processing or (2) net change processing.
Regenerative MRP systems: use batch processing to replan the whole system (full
explosion of all items) on a regular basis (e.g., weekly).
Net change MRP systems: are online and react continuously to changes from the
master schedule, inventory file, and other transactions.
Early MRP installations were largely of the regenerative type, but then as net change
systems became perfected, more firms began installing them. However, being “activity
driven,” net change systems are sometimes “nervous” and tend to overreact to
changes. The major disadvantage of regenerative systems is the time lag that exists
until updated information is incorporated into the system.
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
6
System application: Although MRP systems are widely used, they are most
beneficial in manufacturing environments where products are manufactured to order,
or assembled to order or to stock. MRP does not provide as much advantage in low-
volume, highly complex applications or in continuous flow processes, such as
refineries. It does, however, enjoy wide application in metals, paper, food, chemical,
and other processing applications.
ILLUSTRATION 5: Clemson Industries produces products X and Y, which have
demand, safety stock, and product structure levels as shown in Fig. 6.4. The on hand
inventories are as follows: X = 100, Y = 30, A = 70, B = 0, C = 200, and D = 800.
The lot size for A is 250, and the lot size for D is 1,000 (or multiples of these
amounts); all the other items are specified on a lot-for-lot (LFL) basis (that is, the
quantities are the same as the net requirements). The only scheduled receipts are 250
units of X due in period 2. Determine the order quantities and order release dates for
all requirements using an MRP format. (Note: Assume safety stock amounts are to be
included in the on hand/Available).
Fig. 6.4 Product structure with BOM
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
7
SOLUTION:
First, establish the codes (lowest level) applicable to each product as shown in Table
6.7. Items C and D appear both at level 1 in product Y and at level 2 in product X, so
they are assigned to level 2. Thus their requirements are not netted out until all level 0
and 1 requirements have been netted out.
Table 6.7
Next, set up an MRP format for all items (see Table 9.8), and enter the end-item gross
requirements for X and Y. They both have low-level codes of 0 and so can be netted
out using order quantities that match their requirements (preserving safety stocks, of
course). This results in planned order releases of 200 and 250 units for X (periods 4
and 6) and 400 units of Y (period 4).
Next, explode the planned-order releases for X and Y (that is, multiply them by the
quantities required of the level l items, A and B). (Note that C and D are not level l
items.) Projected requirements for A (200 and 250 units) are direct results of the
planned-order releases for X. Two units of B are required for each X, so item B’s
projected requirements in periods 4 and 6 are 400 and 500, respectively. Items A and
B are then netted, and the order release dates and amounts are set.
Next, explode the level 2, planned-order releases to the level 3 items. The arrows in
Table 6.8 show that requirements for C and D come from planned-order releases for
both B and Y. End item Y requires
4 units of D, so the projected requirements in period 4 are 2,100 units, with 1,600 from
Y (that is, 4 × 400) and 500 from B. Together, they generate a planned-order release
for 2,000 units of D in period 2
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
8
Table 6.8
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
9
6.6 ECONOMIC ORDER QUANTITY (EOQ) METHOD
Large batch sizes result in high inventory levels which are, of course, expensive in
terms of the cost of capital tied up in inventory. Small batches imply a proportionately
lower inventory cost. However, there is a set-up cost incurred with the placing of an
order or the start-up of a batch on a machine. This set-up cost (for manufactured
items) or ordering cost (for purchased items) must be distributed over the batch or
order size. If set-up or ordering costs are high then we may need to resort to larger
batches to reduce the "per unit cost" of set-up and thereby incur larger inventory costs.
It is clear, therefore, that there is a tradeoff between order or set-up costs and
inventory costs. The Economic Order Quantity (EOQ) method is simply a
mathematical expression of this tradeoff and reflects the minimum total cost of
holding stock and set-up. The EOQ can be calculated using the following formula:
EOQ =
)(
))((2
Cc
DCo
......................................... 6.3
Where
EOQ = the economic batch or order size
Co = set-up cost per batch or ordering cost per order
D = the annual demand for the item
Cc = inventory holding (carrying) cost, on annual basis per unit
ILLUSTRATION 6: A manufacturer uses 25000 gear assemblies each year and
purchases them at $3.40 each. It costs $50 to process and receive an order, and
inventory can be carried at a cost of $0.78 per unit-year. What will be the Economic
Order Quantity (EOQ)?
SOLUTION
Given data are:
D = 25000 gear assemblies per year
Co = $ 50 per order
Cc = $ 0.78 per unit-year
EOQ =
)78.0(
)25000)(50(2
= 1790 gear assemblies
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
10
EOQ in MRP systems: Annual demand is not given in MRP problems. Annual
demand is estimated from the known demand on planning horizon (such as10 weeks)
in such case the average demand per week multiplied by 52 to obtain the annual
demand (D). Then EOQ amount can be calculated by means of (Eq. 6.3). Therefore,
whenever it will be necessary to place an order, the order size will be the EOQ
amount.
ILLUSTRATION 7: Consider the following MRP lot sizing problem, the net
requirements are shown in table (6.9) for eight scheduling weeks where the cost per
item is $10, order or setup cost is $47, and inventory carrying cost/week is 0.5%. What
will be the Economic Order Quantity (EOQ)?
Table (6.9)
Week 1 2 3 4 5 6 7 8
Net requirements 50 60 70 60 95 75 60 55
SOLUTION
The economic order quantity EOQ is calculated as follows:
Annual demand based on the 8 weeks = D = (525/8)(52) = 3412.5 units
Annual holding cost = Cc = (0.5%)(10)(52) = $2.6 per unit
Setup cost = Co = $47 (given)
EOQ =
)6.2(
)5.3412)(47(2
= 351 units
Week
Net
requirements
Production
quantity
Ending
inventory
Holding
cost $
Setup cost
$
Total cost
$
1 50 351 301 15.05 47.00 62.05
2 60 0 241 12.05 00.00 74.10
3 70 0 171 8.55 00.00 82.65
4 60 0 111 5.55 00.00 88.20
5 95 0 16 0.80 00.00 89.00
6 75 351 292 14.60 47.00 150.60
7 60 0 232 11.60 00.00 162.20
8 55 0 177 8.85 00.00 171.05
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
11
6.7 CAPACITY REQUIREMENTS PLANNING (CRP)
Capacity is a measure of the productive capability of a facility per unit of time. In
terms of the relevant time horizon, capacity management decisions are concerned with
the following:
l. Long range-resource planning of capital facilities, equipment, and human resources.
2. Medium range-requirements planning of labor and equipment to meet MPS needs.
3. Short range-control of the flow (input-output) and sequencing of operations.
Capacity requirements planning (CRP) applies primarily to medium-range activities.
The CRP system receives planned and released orders from the material requirements
planning system and attempts to develop loads for the firm’s work centers that are in
good balance with the work-center capacities. Like MRP, CRP is an iterative process
that involves planning, revision of capacity (or revision of the master schedule), and
replanning until a reasonably good load profile is developed (see figure 6.1).
Planned-order releases (in the MRP system) are converted to standard hours of load on
key work centers in the CRP system.
Following are the essential inputs and outputs in a CRP system:
6.8 CRP ACTIVITIES: INFINITE AND FINITE LOADING
Planned order releases (in MRP system) are converted to standard hours of load on
key work centers in CRP system. Figure 6.5 illustrate this transition for a planned
order release of 300 handlebars in period 6 (in table 6.6) to 6.2 standard hours of work
in work center (WC) 4. These hours and the hours for other jobs planned for WC 4
during period 6, plus the hours for orders already released, make up the total expected
load of 185 standard hours. Note that 20 hours have been allowed for unplanned
emergency jobs.
Infinite loading; is the practice of loading work centers with all loads when they are
required, without regard to the actual capacity of the work centers. CRP often uses
infinite loading on an initial load profile to evaluate, or "size up", the proposed load
from MPS, and help planners make decisions regarding the use of overtime, alternate
routing, etc.
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
12
Figure 6.5 Transition for a planned order release from MRP to load in CRP system
Finite loading; limits the load assigned to a work center to the maximum capacity of
the work center. Finite loading is the most useful when making the final assignment of
work to work centers, often the major adjustments have been made by using infinite
loading procedures. Figure 6.6 illustrate the difference between infinite and finite
loading.
Figure 6.6 Infinite and finite loading profiles
6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control
13
6.9 UTILIZATION AND EFFICIENCY
Utilization refers to the percentage of available working time that a worker actually
works or a machine actually runs. Scheduled maintenance, lunch breaks, and setup
time are examples of activities that reduce actual working time.
Efficiency refers to how well a machine or worker performs compared to a standard
output level.
6.10 RATED CAPACITY
Rated capacity of work center can be calculated by using the following equation
Rated capacity = (number of machines)(machine hours)(percentage of
utilization)(system efficiency) ……………. 6.4
ILLUSTRATION 8: A work center operates six days per week on a two-shafts-per
day basis (8 hours per shift) and has four machines with the same capability. If the
machines are utilized 75% of the time at system efficiency of 90%, what is the rated
output in standard hours per week?
SOLUTION
Rated capacity = (number of machines)(machine hours)(percentage of
utilization)(system efficiency)
= (4)(8x6x2)(0.75)(0.90) = 259 standard hr/week
6.12 LOAD PERCENT
Load is the standard hours of work (or equivalent units of production) assigned to a
production facility. After load and capacity have been determined, a load percent can
be calculated as:
Load percent = × 100% ……….. 6.5

Mais conteúdo relacionado

Mais procurados

Material requirement planning, MRP.
Material requirement planning, MRP. Material requirement planning, MRP.
Material requirement planning, MRP. shoaibzaheer1
 
Material requirement planning (mrp1)
Material requirement planning (mrp1)Material requirement planning (mrp1)
Material requirement planning (mrp1)saleh asgari
 
Material Requirement Planning (mrp)
Material Requirement Planning (mrp)Material Requirement Planning (mrp)
Material Requirement Planning (mrp)Snehav Sharma
 
Capacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity PlanningCapacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity PlanningRaju Pegada
 
Material requirement planning (mrp1)
Material requirement planning (mrp1)Material requirement planning (mrp1)
Material requirement planning (mrp1)Ravimohan Rajmohan
 
Material Requirement Planning
Material Requirement PlanningMaterial Requirement Planning
Material Requirement PlanningPritesh Mogane
 
Inventory management
Inventory managementInventory management
Inventory managementkahogan62
 
material requirement planning
material requirement planningmaterial requirement planning
material requirement planningNaushii Khan
 
Material requirements planning & erp ppt @ bec doms
Material requirements planning & erp  ppt @ bec domsMaterial requirements planning & erp  ppt @ bec doms
Material requirements planning & erp ppt @ bec domsBabasab Patil
 
What is master production schedule
What is master production scheduleWhat is master production schedule
What is master production scheduleMRPeasy
 
small and effective ppt on master production schedule
small and effective ppt on master production schedulesmall and effective ppt on master production schedule
small and effective ppt on master production scheduleyashbhhardwaj260
 
Materials requirement planning
Materials requirement planningMaterials requirement planning
Materials requirement planningAnila Vanguri
 
The Capacity Requirement Planning
The Capacity Requirement Planning The Capacity Requirement Planning
The Capacity Requirement Planning BagishMishra3
 
Material requirement planning - Production and Operation Management
Material requirement planning - Production and Operation ManagementMaterial requirement planning - Production and Operation Management
Material requirement planning - Production and Operation ManagementSuryakumar Thangarasu
 

Mais procurados (20)

Material requirement planning, MRP.
Material requirement planning, MRP. Material requirement planning, MRP.
Material requirement planning, MRP.
 
Material requirement planning (mrp1)
Material requirement planning (mrp1)Material requirement planning (mrp1)
Material requirement planning (mrp1)
 
Material Requirement Planning (mrp)
Material Requirement Planning (mrp)Material Requirement Planning (mrp)
Material Requirement Planning (mrp)
 
MRP-II
MRP-IIMRP-II
MRP-II
 
Capacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity PlanningCapacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity Planning
 
MRP
MRPMRP
MRP
 
Mrp ii
Mrp iiMrp ii
Mrp ii
 
Material requirement planning (mrp1)
Material requirement planning (mrp1)Material requirement planning (mrp1)
Material requirement planning (mrp1)
 
Inventory Optimization Using ABC-XYZ Analysis
Inventory Optimization Using ABC-XYZ AnalysisInventory Optimization Using ABC-XYZ Analysis
Inventory Optimization Using ABC-XYZ Analysis
 
Material Requirement Planning
Material Requirement PlanningMaterial Requirement Planning
Material Requirement Planning
 
Inventory management
Inventory managementInventory management
Inventory management
 
material requirement planning
material requirement planningmaterial requirement planning
material requirement planning
 
Material requirements planning & erp ppt @ bec doms
Material requirements planning & erp  ppt @ bec domsMaterial requirements planning & erp  ppt @ bec doms
Material requirements planning & erp ppt @ bec doms
 
Rccp report
Rccp reportRccp report
Rccp report
 
What is master production schedule
What is master production scheduleWhat is master production schedule
What is master production schedule
 
assembly line balancing
assembly line balancingassembly line balancing
assembly line balancing
 
small and effective ppt on master production schedule
small and effective ppt on master production schedulesmall and effective ppt on master production schedule
small and effective ppt on master production schedule
 
Materials requirement planning
Materials requirement planningMaterials requirement planning
Materials requirement planning
 
The Capacity Requirement Planning
The Capacity Requirement Planning The Capacity Requirement Planning
The Capacity Requirement Planning
 
Material requirement planning - Production and Operation Management
Material requirement planning - Production and Operation ManagementMaterial requirement planning - Production and Operation Management
Material requirement planning - Production and Operation Management
 

Destaque

Capacity Requirement Planning
Capacity Requirement PlanningCapacity Requirement Planning
Capacity Requirement Planningsenthil.G
 
Business process reengineering
Business process reengineeringBusiness process reengineering
Business process reengineeringNeelkamal Sharma
 
Explorando el ambiente de excel
Explorando el ambiente de excelExplorando el ambiente de excel
Explorando el ambiente de excelJennyPaucar1
 
Presentació Toni Solà
Presentació Toni SolàPresentació Toni Solà
Presentació Toni SolàToniSola
 
SEspejo- Final Proposal
SEspejo- Final ProposalSEspejo- Final Proposal
SEspejo- Final ProposalShelly Espejo
 
Design Insight: Professional Development Workshop
Design Insight: Professional  Development WorkshopDesign Insight: Professional  Development Workshop
Design Insight: Professional Development WorkshopCole Henson
 
20160328000305skala
20160328000305skala20160328000305skala
20160328000305skalaAimi Yusri
 
DevOps Practices and how to implement it using VSTS
DevOps Practices and how to implement it using VSTSDevOps Practices and how to implement it using VSTS
DevOps Practices and how to implement it using VSTSFernando Mejía
 
Webinar AppDynamics
Webinar AppDynamicsWebinar AppDynamics
Webinar AppDynamicsatSistemas
 
social engineering for fun and profit
social engineering for fun and profitsocial engineering for fun and profit
social engineering for fun and profitSimone Onofri
 
Mps vs aggregate planning
Mps vs aggregate planningMps vs aggregate planning
Mps vs aggregate planningUmar Yazdani
 
Devops Powered by Splunk
Devops Powered by SplunkDevops Powered by Splunk
Devops Powered by SplunkSplunk
 
TEORIA DE LA PROBABILIDAD. AUTOR: ELI ANGULO
TEORIA DE LA PROBABILIDAD. AUTOR: ELI ANGULOTEORIA DE LA PROBABILIDAD. AUTOR: ELI ANGULO
TEORIA DE LA PROBABILIDAD. AUTOR: ELI ANGULOEli Ang
 
Capacity requirement planning sure 12mt07ind019
Capacity requirement planning sure 12mt07ind019Capacity requirement planning sure 12mt07ind019
Capacity requirement planning sure 12mt07ind019samjune
 
线上问题排查交流
线上问题排查交流线上问题排查交流
线上问题排查交流Edward Lee
 

Destaque (19)

Mrp & crp
Mrp & crp Mrp & crp
Mrp & crp
 
Capacity Requirement Planning
Capacity Requirement PlanningCapacity Requirement Planning
Capacity Requirement Planning
 
Resource Requirement Planning
Resource Requirement PlanningResource Requirement Planning
Resource Requirement Planning
 
Business process reengineering
Business process reengineeringBusiness process reengineering
Business process reengineering
 
SAP Production Planning
SAP Production PlanningSAP Production Planning
SAP Production Planning
 
成功神學
成功神學成功神學
成功神學
 
Explorando el ambiente de excel
Explorando el ambiente de excelExplorando el ambiente de excel
Explorando el ambiente de excel
 
Presentació Toni Solà
Presentació Toni SolàPresentació Toni Solà
Presentació Toni Solà
 
SEspejo- Final Proposal
SEspejo- Final ProposalSEspejo- Final Proposal
SEspejo- Final Proposal
 
Design Insight: Professional Development Workshop
Design Insight: Professional  Development WorkshopDesign Insight: Professional  Development Workshop
Design Insight: Professional Development Workshop
 
20160328000305skala
20160328000305skala20160328000305skala
20160328000305skala
 
DevOps Practices and how to implement it using VSTS
DevOps Practices and how to implement it using VSTSDevOps Practices and how to implement it using VSTS
DevOps Practices and how to implement it using VSTS
 
Webinar AppDynamics
Webinar AppDynamicsWebinar AppDynamics
Webinar AppDynamics
 
social engineering for fun and profit
social engineering for fun and profitsocial engineering for fun and profit
social engineering for fun and profit
 
Mps vs aggregate planning
Mps vs aggregate planningMps vs aggregate planning
Mps vs aggregate planning
 
Devops Powered by Splunk
Devops Powered by SplunkDevops Powered by Splunk
Devops Powered by Splunk
 
TEORIA DE LA PROBABILIDAD. AUTOR: ELI ANGULO
TEORIA DE LA PROBABILIDAD. AUTOR: ELI ANGULOTEORIA DE LA PROBABILIDAD. AUTOR: ELI ANGULO
TEORIA DE LA PROBABILIDAD. AUTOR: ELI ANGULO
 
Capacity requirement planning sure 12mt07ind019
Capacity requirement planning sure 12mt07ind019Capacity requirement planning sure 12mt07ind019
Capacity requirement planning sure 12mt07ind019
 
线上问题排查交流
线上问题排查交流线上问题排查交流
线上问题排查交流
 

Semelhante a Material and capacity requirements planning (mrp and crp) part 2

Production planning and control - Basic concepts
Production planning and control - Basic conceptsProduction planning and control - Basic concepts
Production planning and control - Basic conceptsgokulfea
 
Operations Management Material Requirements Planning (MRP)
Operations ManagementMaterial Requirements Planning (MRP)Operations ManagementMaterial Requirements Planning (MRP)
Operations Management Material Requirements Planning (MRP)Mostafa Ewees
 
IRJET- Production Plan and Control
IRJET- Production Plan and ControlIRJET- Production Plan and Control
IRJET- Production Plan and ControlIRJET Journal
 
Lecture 24 conversion cycle -the traditional manufacturing environment accou...
Lecture 24  conversion cycle -the traditional manufacturing environment accou...Lecture 24  conversion cycle -the traditional manufacturing environment accou...
Lecture 24 conversion cycle -the traditional manufacturing environment accou...Habib Ullah Qamar
 
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaaSCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaainfinitepestcontrol
 
Mrp systems & scheduling
Mrp systems & schedulingMrp systems & scheduling
Mrp systems & schedulingvarun0610
 
Planificador de Producción a capacidad finita Simatic IT Preactor AP
Planificador de Producción a capacidad finita Simatic IT Preactor AP Planificador de Producción a capacidad finita Simatic IT Preactor AP
Planificador de Producción a capacidad finita Simatic IT Preactor AP Planning Manufacturing.
 
COMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGCOMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGjntuhcej
 
Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)jntuhcej
 
Material Requirements planning system 01Page to 04 Page
Material Requirements planning system                      01Page to 04 PageMaterial Requirements planning system                      01Page to 04 Page
Material Requirements planning system 01Page to 04 PageHasibul Islam
 
Software Solution for Production Planning and Scheduling
Software Solution for Production Planning and SchedulingSoftware Solution for Production Planning and Scheduling
Software Solution for Production Planning and SchedulingIRJET Journal
 
manufacturing resource planning
manufacturing resource planningmanufacturing resource planning
manufacturing resource planningDinesh Nikam
 
MASTER PRODUCTION SCHEDULE (MPS).pptx
MASTER PRODUCTION SCHEDULE (MPS).pptxMASTER PRODUCTION SCHEDULE (MPS).pptx
MASTER PRODUCTION SCHEDULE (MPS).pptxGulaHangus
 
Sap mrp-configuration-pp
Sap mrp-configuration-ppSap mrp-configuration-pp
Sap mrp-configuration-ppLokesh Modem
 
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...IRJET Journal
 
Manufacturing and materials management
Manufacturing and materials managementManufacturing and materials management
Manufacturing and materials managementAkbar Setiadi
 

Semelhante a Material and capacity requirements planning (mrp and crp) part 2 (20)

Lect 6.ppt
Lect 6.pptLect 6.ppt
Lect 6.ppt
 
Production planning and control - Basic concepts
Production planning and control - Basic conceptsProduction planning and control - Basic concepts
Production planning and control - Basic concepts
 
Supply_Chain_PP MOD
Supply_Chain_PP MODSupply_Chain_PP MOD
Supply_Chain_PP MOD
 
Operations Management Material Requirements Planning (MRP)
Operations ManagementMaterial Requirements Planning (MRP)Operations ManagementMaterial Requirements Planning (MRP)
Operations Management Material Requirements Planning (MRP)
 
Article final ivan f
Article final ivan fArticle final ivan f
Article final ivan f
 
IRJET- Production Plan and Control
IRJET- Production Plan and ControlIRJET- Production Plan and Control
IRJET- Production Plan and Control
 
Lecture 24 conversion cycle -the traditional manufacturing environment accou...
Lecture 24  conversion cycle -the traditional manufacturing environment accou...Lecture 24  conversion cycle -the traditional manufacturing environment accou...
Lecture 24 conversion cycle -the traditional manufacturing environment accou...
 
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaaSCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
 
Mrp systems & scheduling
Mrp systems & schedulingMrp systems & scheduling
Mrp systems & scheduling
 
Planificador de Producción a capacidad finita Simatic IT Preactor AP
Planificador de Producción a capacidad finita Simatic IT Preactor AP Planificador de Producción a capacidad finita Simatic IT Preactor AP
Planificador de Producción a capacidad finita Simatic IT Preactor AP
 
COMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGCOMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNING
 
Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)
 
Material Requirements planning system 01Page to 04 Page
Material Requirements planning system                      01Page to 04 PageMaterial Requirements planning system                      01Page to 04 Page
Material Requirements planning system 01Page to 04 Page
 
Software Solution for Production Planning and Scheduling
Software Solution for Production Planning and SchedulingSoftware Solution for Production Planning and Scheduling
Software Solution for Production Planning and Scheduling
 
manufacturing resource planning
manufacturing resource planningmanufacturing resource planning
manufacturing resource planning
 
Mrp 1
Mrp 1Mrp 1
Mrp 1
 
MASTER PRODUCTION SCHEDULE (MPS).pptx
MASTER PRODUCTION SCHEDULE (MPS).pptxMASTER PRODUCTION SCHEDULE (MPS).pptx
MASTER PRODUCTION SCHEDULE (MPS).pptx
 
Sap mrp-configuration-pp
Sap mrp-configuration-ppSap mrp-configuration-pp
Sap mrp-configuration-pp
 
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
 
Manufacturing and materials management
Manufacturing and materials managementManufacturing and materials management
Manufacturing and materials management
 

Mais de Dr. Mahmoud Al-Naimi

أسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfأسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfDr. Mahmoud Al-Naimi
 
Certificate - Dr. Mahmoud AL-Naimi
Certificate  - Dr. Mahmoud AL-NaimiCertificate  - Dr. Mahmoud AL-Naimi
Certificate - Dr. Mahmoud AL-NaimiDr. Mahmoud Al-Naimi
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعDr. Mahmoud Al-Naimi
 
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةكيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةDr. Mahmoud Al-Naimi
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...Dr. Mahmoud Al-Naimi
 
أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)Dr. Mahmoud Al-Naimi
 
Product design and manufacture lecture 1
Product design and manufacture lecture  1Product design and manufacture lecture  1
Product design and manufacture lecture 1Dr. Mahmoud Al-Naimi
 
Easy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projectsEasy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projectsDr. Mahmoud Al-Naimi
 
Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Dr. Mahmoud Al-Naimi
 
Easy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationEasy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationDr. Mahmoud Al-Naimi
 
ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق Dr. Mahmoud Al-Naimi
 
Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Dr. Mahmoud Al-Naimi
 
Computer in Design and Manufacturing
Computer in Design and Manufacturing Computer in Design and Manufacturing
Computer in Design and Manufacturing Dr. Mahmoud Al-Naimi
 
إنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةإنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةDr. Mahmoud Al-Naimi
 

Mais de Dr. Mahmoud Al-Naimi (20)

أسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfأسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdf
 
Certificate - Dr. Mahmoud AL-Naimi
Certificate  - Dr. Mahmoud AL-NaimiCertificate  - Dr. Mahmoud AL-Naimi
Certificate - Dr. Mahmoud AL-Naimi
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريع
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةكيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...
 
أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)
 
(Aoa) and (aon) networks
(Aoa) and (aon) networks(Aoa) and (aon) networks
(Aoa) and (aon) networks
 
Applications dr. mahmoud al-naimi
Applications   dr. mahmoud al-naimiApplications   dr. mahmoud al-naimi
Applications dr. mahmoud al-naimi
 
Product design and manufacture lecture 1
Product design and manufacture lecture  1Product design and manufacture lecture  1
Product design and manufacture lecture 1
 
Easy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projectsEasy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projects
 
Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations
 
Easy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationEasy steps to network construction and critical path determination
Easy steps to network construction and critical path determination
 
ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق
 
Control charts for variables
Control charts for variables Control charts for variables
Control charts for variables
 
Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)
 
Evolution of mrp type systems
Evolution of mrp type systemsEvolution of mrp type systems
Evolution of mrp type systems
 
Computer in Design and Manufacturing
Computer in Design and Manufacturing Computer in Design and Manufacturing
Computer in Design and Manufacturing
 
إنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةإنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكية
 
Network construction
Network construction  Network construction
Network construction
 

Último

Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfErwinPantujan2
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)cama23
 
Food processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture honsFood processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture honsManeerUddin
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationRosabel UA
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxlancelewisportillo
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfVanessa Camilleri
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...Postal Advocate Inc.
 
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...JojoEDelaCruz
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfJemuel Francisco
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptshraddhaparab530
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptxmary850239
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4JOYLYNSAMANIEGO
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptxmary850239
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 

Último (20)

Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
 
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptxYOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)
 
Food processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture honsFood processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture hons
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translation
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdf
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
 
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.ppt
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 

Material and capacity requirements planning (mrp and crp) part 2

  • 1. MATERIAL AND CAPACITY REQUIREMENTS PLANNING (MRP AND CRP) Part -2 Dr. Mahmoud Abbas Mahmoud Al-Naimi Assistant Professor Industrial Engineering Branch Department of Production Engineering and Metallurgy University of Technology Baghdad - Iraq dr.mahmoudalnaimi@uotechnology.edu.iq dr.mahmoudalnaimi@yahoo.com 2015 - 2016
  • 2. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 1 6.3 MRP LOGIC Following are some of the terms frequently used on (computerized) MRP planning forms. Note, however, that not all programs use the same terms or provide the same detail of information. 1. Gross requirements: Projected needs for raw materials, components, subassemblies, or finished goods by the end of the period shown. Gross requirements come from the master schedule (for end items) or from the combined needs of other items. 2. Scheduled receipts: Materials already on order from a vendor or in-house shop due to be received at the beginning of the period. MRP form shows quantity and projected time of receipt. (Note: Some MRP forms include planned receipts here too.) 3. On hand/available: The quantity of an item expected to be available at the end of the time period in which it is shown. This includes amount available from previous period plus planned-order receipts and scheduled receipts less gross requirements. 4. Net requirements: Net amount needed in the period. This equals the gross requirements less any projected inventory available from the previous period along with any scheduled receipts. 5. Planned-order receipt: Materials that will be ordered from a vendor or in-house shop to be received at the beginning of the period. Otherwise it is similar to a scheduled receipt. 6. Planned-order release: The planned amount to be ordered in the time period adjusted by the lead-time offset so that materials will be received on schedule. Once the orders are actually released, the planned-order releases are deleted from the form and the planned-order receipts they generated are changed to scheduled receipts. The master production schedule dictates gross or projected requirements for end items to the MRP system. Gross requirements do not take account of any inventory on hand or on order. The MRP computer program then “explodes” the end-item demands into requirements for components and materials by processing all relevant bills of materials on a level-by-level (or single-level) basis. Net requirements are then calculated by adjusting for existing inventory and items already on order as recorded in the inventory status file. Net requirements = gross requirements – (on hand/available + scheduled receipts) … 6.1 Order releases are planned for components in a time-phased manner (using lead-time data from the inventory file) so that materials will arrive precisely when needed. At this stage the material is referred to as a planned-order receipt. When the orders are actually issued to vendors or to in-house shops, the planned receipts become scheduled
  • 3. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 2 receipts. The inventory on hand at the end of a period is the sum of the previous period on-hand amount plus any receipts (planned or scheduled) less the gross requirements. On hand/available = on hand at end of previous period + receipts – gross requirements …6.2 ILLUSTRATION 4: A firm producing wheelbarrows is expected to deliver 40 wheelbarrows in week 1, 60 in week 4, 60 in week 6, and 50 in week 8. Among the requirements for each wheelbarrow are two handlebars, a wheel assembly, and one tire for the wheel assembly. Orders quantities, lead times, and inventories on hand at the beginning of period 1 are shown in Table 6.5. Table 6.5 BOM and inventory data for wheelbarrow components *90 wheel assemblies are also needed in period 5 for a garden tractor shipment. A shipment of 300 handlebars is already scheduled to be received at the beginning of week 2 (i.e., a scheduled receipt). Complete the MRP for the handlebars, wheel assemblies, and tires; and show what quantities or orders must be released and when they must be released to satisfy the master schedule. SOLUTION: Table 6.6 depicts the master schedule and component part schedules. We shall assume that the customer completes the final assembly, so no time allowance is required there. Note that because each wheelbarrow requires two handlebars, the gross requirements for handlebars are double the number of end products. Thus the gross requirements in period 1 are 40 × 2 = 80 units. Table 6.6 (a) End item Master schedule; wheelbarrows
  • 4. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 3 Table 6.6 (b) Master schedule and MRP component plans for wheelbarrows * Requirements from another product (garden tractor) that uses the same wheel assembly. The 100 handlebars on hand at the beginning of period 1 are adequate to supply the gross requirement of 80 handlebars, leaving 20 on hand at the end of period 1. With the (scheduled) receipt of 300 handlebars in period 2, the on-hand inventory remains adequate until the end of week 8, when 80 units are on hand. However, the gross requirement for 100 units in period 9 exceeds the on-hand inventory. This results in net requirements (using Eq. 6.1) of 100 – 80 = 20 units. To satisfy this, a planned- order receipt for the standard order quantity (300) is scheduled for the beginning of period 8. In so far as the handlebars have a 2 week lead-time, the planned order for the Handle bars must be released 2 weeks earlier (week 6). The planned order receipt will result in a projected end-of-period on-hand inventory (using Eq. 6.2) of 80 + 300 – 100 = 280 units.
  • 5. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 4 6.4 SYSTEM REFINEMENTS Key features of MRP systems are (1) the generation of lower-level requirements, (2) time phasing of those requirements, and (3) the planned-order releases that flow from them. Note particularly that planned-order releases of parent items generate gross requirements at the component level (e.g., tires). Additional features of many MRP systems are their capability to handle (a) simulations, (b) firm-planned orders, (c) pegging, and (d) the availability of planning bills of material. Simulation: The simulation capability allows planners to “trial fit” a master schedule onto the MRP system before the schedule is actually accepted and released. With this feature, a planner can “try” a potential customer order on the system to see if materials and delivery dates can be met even before the order is accepted. If lead times, materials, and capacities are sufficient, the order can be accepted; otherwise, changes in quantities or delivery times may have to be negotiated, or the order may even have to be turned down. Firm-Planned Orders: Sometimes the “normal” manufacturing times are not enough to meet an emergency, secure a special order, or service a valued customer. Firm- planned order capability enables planners to instruct the computer to accept certain requirements, even though normal MRP logic would automatically delay or reschedule such orders. By designating certain orders as “firm-planned orders,” planners can ensure that the computer will not automatically change the release date, the planned- order receipt date, or the order quantity. In addition, the system can establish a “time fence” around the planned-order release date to preclude the scheduling of other orders near that time so as to ensure that resources are available to do the special job. Pegging: Pegging refers to the ability to work backward from component requirements to identify the parent item, or items that generated those requirements. For example, suppose an automobile manufacturer learned that some of the brake materials (already used in production) were defective. The “where used” pegging file would allow production analysts to trace requirements upward in the product structure tree to determine what end-item models contained the defective components. Modular and Planning Bills: Modular bills of materials describe the product structure for basic subassemblies of parts that are common to different end items. For example, several models of a manufacturer’s automobiles may contain the same transmission, drive train, air-conditioning, and braking systems. By scheduling these items as (common) modules, production can sometimes be more effectively “smoothed” and inventory investment minimized.
  • 6. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 5 6.5 SAFETY STOCK, LOT SIZING AND SYSTEM UPDATING Safety stock: Note that the MRP component plan shown in Table 6.6 includes space for an entry of safety stock. Although one of the reasons for using MRP to manage dependent demand inventory items is to avoid the need for safety stock, in reality firms may elect to carry safety stock on some items for a variety of reasons: Safety stock amounts are sometimes deducted before showing the On hand/Available quantities. Following are some of the reasons for carrying safety stock of components on an MRP format 1. Not all demand is dependent. Some items (e.g., repair parts) may have a service requirement that has an independent demand component. 2. Variable lead times from suppliers are a common source of uncertainty to many firms. 3. Firms may experience machine breakdowns, scrap losses, and last-minute customer changes. Lot sizing: Order quantities are not always specified in advance. Different lot-sizing methods are in use, they are (1) fixed-order quantity amounts, e.g., 300 handlebars; (2) EOQ amounts [EOQ method will be explained later on]; (3) lot for lot, which is ordering the exact amount of the net requirements for each period; (4) fixed period requirements, e.g., a 2-month supply; and (5) various least-cost approaches, e.g., least- unit cost, least-total cost. The part-period algorithm is a method that uses a ratio of ordering costs to carrying costs per period, which yields a part-period number. Then requirements for current and future periods are cumulated until the cumulative holding cost (in part-period terms) is as close as possible to this number. System updating: MRP system designs typically use one of two methods to process data, update files, and ensure that the system information is valid and conforms with actual: (1) regenerative processing or (2) net change processing. Regenerative MRP systems: use batch processing to replan the whole system (full explosion of all items) on a regular basis (e.g., weekly). Net change MRP systems: are online and react continuously to changes from the master schedule, inventory file, and other transactions. Early MRP installations were largely of the regenerative type, but then as net change systems became perfected, more firms began installing them. However, being “activity driven,” net change systems are sometimes “nervous” and tend to overreact to changes. The major disadvantage of regenerative systems is the time lag that exists until updated information is incorporated into the system.
  • 7. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 6 System application: Although MRP systems are widely used, they are most beneficial in manufacturing environments where products are manufactured to order, or assembled to order or to stock. MRP does not provide as much advantage in low- volume, highly complex applications or in continuous flow processes, such as refineries. It does, however, enjoy wide application in metals, paper, food, chemical, and other processing applications. ILLUSTRATION 5: Clemson Industries produces products X and Y, which have demand, safety stock, and product structure levels as shown in Fig. 6.4. The on hand inventories are as follows: X = 100, Y = 30, A = 70, B = 0, C = 200, and D = 800. The lot size for A is 250, and the lot size for D is 1,000 (or multiples of these amounts); all the other items are specified on a lot-for-lot (LFL) basis (that is, the quantities are the same as the net requirements). The only scheduled receipts are 250 units of X due in period 2. Determine the order quantities and order release dates for all requirements using an MRP format. (Note: Assume safety stock amounts are to be included in the on hand/Available). Fig. 6.4 Product structure with BOM
  • 8. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 7 SOLUTION: First, establish the codes (lowest level) applicable to each product as shown in Table 6.7. Items C and D appear both at level 1 in product Y and at level 2 in product X, so they are assigned to level 2. Thus their requirements are not netted out until all level 0 and 1 requirements have been netted out. Table 6.7 Next, set up an MRP format for all items (see Table 9.8), and enter the end-item gross requirements for X and Y. They both have low-level codes of 0 and so can be netted out using order quantities that match their requirements (preserving safety stocks, of course). This results in planned order releases of 200 and 250 units for X (periods 4 and 6) and 400 units of Y (period 4). Next, explode the planned-order releases for X and Y (that is, multiply them by the quantities required of the level l items, A and B). (Note that C and D are not level l items.) Projected requirements for A (200 and 250 units) are direct results of the planned-order releases for X. Two units of B are required for each X, so item B’s projected requirements in periods 4 and 6 are 400 and 500, respectively. Items A and B are then netted, and the order release dates and amounts are set. Next, explode the level 2, planned-order releases to the level 3 items. The arrows in Table 6.8 show that requirements for C and D come from planned-order releases for both B and Y. End item Y requires 4 units of D, so the projected requirements in period 4 are 2,100 units, with 1,600 from Y (that is, 4 × 400) and 500 from B. Together, they generate a planned-order release for 2,000 units of D in period 2
  • 9. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 8 Table 6.8
  • 10. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 9 6.6 ECONOMIC ORDER QUANTITY (EOQ) METHOD Large batch sizes result in high inventory levels which are, of course, expensive in terms of the cost of capital tied up in inventory. Small batches imply a proportionately lower inventory cost. However, there is a set-up cost incurred with the placing of an order or the start-up of a batch on a machine. This set-up cost (for manufactured items) or ordering cost (for purchased items) must be distributed over the batch or order size. If set-up or ordering costs are high then we may need to resort to larger batches to reduce the "per unit cost" of set-up and thereby incur larger inventory costs. It is clear, therefore, that there is a tradeoff between order or set-up costs and inventory costs. The Economic Order Quantity (EOQ) method is simply a mathematical expression of this tradeoff and reflects the minimum total cost of holding stock and set-up. The EOQ can be calculated using the following formula: EOQ = )( ))((2 Cc DCo ......................................... 6.3 Where EOQ = the economic batch or order size Co = set-up cost per batch or ordering cost per order D = the annual demand for the item Cc = inventory holding (carrying) cost, on annual basis per unit ILLUSTRATION 6: A manufacturer uses 25000 gear assemblies each year and purchases them at $3.40 each. It costs $50 to process and receive an order, and inventory can be carried at a cost of $0.78 per unit-year. What will be the Economic Order Quantity (EOQ)? SOLUTION Given data are: D = 25000 gear assemblies per year Co = $ 50 per order Cc = $ 0.78 per unit-year EOQ = )78.0( )25000)(50(2 = 1790 gear assemblies
  • 11. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 10 EOQ in MRP systems: Annual demand is not given in MRP problems. Annual demand is estimated from the known demand on planning horizon (such as10 weeks) in such case the average demand per week multiplied by 52 to obtain the annual demand (D). Then EOQ amount can be calculated by means of (Eq. 6.3). Therefore, whenever it will be necessary to place an order, the order size will be the EOQ amount. ILLUSTRATION 7: Consider the following MRP lot sizing problem, the net requirements are shown in table (6.9) for eight scheduling weeks where the cost per item is $10, order or setup cost is $47, and inventory carrying cost/week is 0.5%. What will be the Economic Order Quantity (EOQ)? Table (6.9) Week 1 2 3 4 5 6 7 8 Net requirements 50 60 70 60 95 75 60 55 SOLUTION The economic order quantity EOQ is calculated as follows: Annual demand based on the 8 weeks = D = (525/8)(52) = 3412.5 units Annual holding cost = Cc = (0.5%)(10)(52) = $2.6 per unit Setup cost = Co = $47 (given) EOQ = )6.2( )5.3412)(47(2 = 351 units Week Net requirements Production quantity Ending inventory Holding cost $ Setup cost $ Total cost $ 1 50 351 301 15.05 47.00 62.05 2 60 0 241 12.05 00.00 74.10 3 70 0 171 8.55 00.00 82.65 4 60 0 111 5.55 00.00 88.20 5 95 0 16 0.80 00.00 89.00 6 75 351 292 14.60 47.00 150.60 7 60 0 232 11.60 00.00 162.20 8 55 0 177 8.85 00.00 171.05
  • 12. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 11 6.7 CAPACITY REQUIREMENTS PLANNING (CRP) Capacity is a measure of the productive capability of a facility per unit of time. In terms of the relevant time horizon, capacity management decisions are concerned with the following: l. Long range-resource planning of capital facilities, equipment, and human resources. 2. Medium range-requirements planning of labor and equipment to meet MPS needs. 3. Short range-control of the flow (input-output) and sequencing of operations. Capacity requirements planning (CRP) applies primarily to medium-range activities. The CRP system receives planned and released orders from the material requirements planning system and attempts to develop loads for the firm’s work centers that are in good balance with the work-center capacities. Like MRP, CRP is an iterative process that involves planning, revision of capacity (or revision of the master schedule), and replanning until a reasonably good load profile is developed (see figure 6.1). Planned-order releases (in the MRP system) are converted to standard hours of load on key work centers in the CRP system. Following are the essential inputs and outputs in a CRP system: 6.8 CRP ACTIVITIES: INFINITE AND FINITE LOADING Planned order releases (in MRP system) are converted to standard hours of load on key work centers in CRP system. Figure 6.5 illustrate this transition for a planned order release of 300 handlebars in period 6 (in table 6.6) to 6.2 standard hours of work in work center (WC) 4. These hours and the hours for other jobs planned for WC 4 during period 6, plus the hours for orders already released, make up the total expected load of 185 standard hours. Note that 20 hours have been allowed for unplanned emergency jobs. Infinite loading; is the practice of loading work centers with all loads when they are required, without regard to the actual capacity of the work centers. CRP often uses infinite loading on an initial load profile to evaluate, or "size up", the proposed load from MPS, and help planners make decisions regarding the use of overtime, alternate routing, etc.
  • 13. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 12 Figure 6.5 Transition for a planned order release from MRP to load in CRP system Finite loading; limits the load assigned to a work center to the maximum capacity of the work center. Finite loading is the most useful when making the final assignment of work to work centers, often the major adjustments have been made by using infinite loading procedures. Figure 6.6 illustrate the difference between infinite and finite loading. Figure 6.6 Infinite and finite loading profiles
  • 14. 6201-5201Dr. Mahmoud Abbas MahmoudProduction Planning and Control 13 6.9 UTILIZATION AND EFFICIENCY Utilization refers to the percentage of available working time that a worker actually works or a machine actually runs. Scheduled maintenance, lunch breaks, and setup time are examples of activities that reduce actual working time. Efficiency refers to how well a machine or worker performs compared to a standard output level. 6.10 RATED CAPACITY Rated capacity of work center can be calculated by using the following equation Rated capacity = (number of machines)(machine hours)(percentage of utilization)(system efficiency) ……………. 6.4 ILLUSTRATION 8: A work center operates six days per week on a two-shafts-per day basis (8 hours per shift) and has four machines with the same capability. If the machines are utilized 75% of the time at system efficiency of 90%, what is the rated output in standard hours per week? SOLUTION Rated capacity = (number of machines)(machine hours)(percentage of utilization)(system efficiency) = (4)(8x6x2)(0.75)(0.90) = 259 standard hr/week 6.12 LOAD PERCENT Load is the standard hours of work (or equivalent units of production) assigned to a production facility. After load and capacity have been determined, a load percent can be calculated as: Load percent = × 100% ……….. 6.5