SlideShare uma empresa Scribd logo
1 de 32
Baixar para ler offline
Land Transport Authority
We Keep Your World MOVING. We Keep Your World MOVING. We Keep You
MOVING. We Keep Your World MOVING. We Keep Your World MOVING.
Internship Presentation
DEVARSH KUMAR
3rd year undergraduate
Department of Civil Engineering
Indian Institute of Technology Madras
email – devarsh10iitm@gmail.com
OUTLINE
Top Down vs Bottom Up
method in construction
• TIME comparison
• COST analysis
Earth Pressure Balance TBM
• OPEN CUT TUNNEL
alignment of C928
• KEY position selection
Sustainable Development
• Environmentally
improved material
Learning Outcome
• Challenges
encountered
• Site photos with
description
• Construction
Market Activity
Cycle Model
C937B Tai Seng Facility Building
C929
Kaki Bukit
Station
(Top Down)
C929A
C928
Bedok North
Station
(Bottom Up)
C928
C929A
C929A
Layout Chart
Rate of volume
of earth to be
excavated (20m)
$129/m3
$99/m3
Rate of concrete
to be used for
roof slab (1.5m)
$150/m3
$150/m3
Hypothetical Structure
Length – 60 m
Width – 24 m
Top Down
vs
Bottom Up
Total cost
$4.0 M
Total cost
$4.7 M
Less TIME
taken
Rate of volume
of earth to be
excavated (20m)
$129/m3
$99/m3
Rate of concrete
to be used for
roof slab (1.5m)
$150/m3
$150/m3
Rebar (adopt
230 kg/m3)
$1.46/kg
$1.46/kg
Area of
formwork to
be used
NA
$75/m2
Hypothetical Structure
Length – 60 m
Width – 24 m
Top Down
vs
Bottom Up
Total cost
$4.0 M
Total cost
$4.7 M
Less TIME
taken
Reasons for higher cost of Top - Down
• Limited construction openings for handling materials and
machineries.
• Limited headroom for excavators to operate.
• Need more lightening and ventilation systems.
• Even though there is no scaffolding materials used to prop
the formwork to the soffit of the roof slab in Top – Down
Method yet its price is high because of very high rate of the
volume of earth to be excavated.
NOTE – cost figure represent C929A and cannot be generalised
Tunnel Alignment
Expo Bound
Bukit Panjang Bound
C929A Station Box
C929
C928
WEST Cut and Cover Tunnel Alignment
START
END
EAST Cut and Cover Tunnel Alignment
C927
Expo Bound
Bukit Panjang Bound
Station Box
C928
START
END
Key Position
Selection
KEY position 7 to
11 are not used
because
• It is difficult to
install as
Connection
Segments (B)
and Standard
Segments (A) are
under
compression.
• It is the weakest
link.
Sequence of
Key Position
Selection for
building
Segments
Required Information
• Straight portion of the
Tunnel
• Tunnel is moving UPWARD
L16 R2, R5, R14
SUSTAINABLE DEVELOPMENT
Choose efficient formwork
Timber Formwork System Formwork
Material Timber & Plywood Aluminium
Durability 20 times 120 – 150 times
Wastage Yes No
Quality Workmanship dependent Good
Labour Skilled Unskilled
Cost $26/m2 $34/m2
Source – Guidebook for best environmental practices, LTA, Singapore
Environmentally Improved Materials
• Using MILLED WASTE for temporary pathway instead of
concrete.
• Using factory prefabricated reinforcement because there is :
60% reduction in processing waste
30% increase in labour productivity
• Good coverage of stockpile using Erosion Control Blanket
either Natural material blanket or synthetic blanket.
• Using Scrap bin for disposing welding rods, twisted steel
wires, etc. for recycle.
Learning Outcomes
Challenges
Encountered
Bedok North
Station
(1) Water Canal
Diversion
Temporary Canal
HDB
D-WALL
SBP
In case of any failure, water
will remain confine between
D-Wall and SBP and station
box remains unaffected
Bedok North
Station
Challenges
Encountered
(2) Water Ingress
Stock pile
Water squeeze out from
underground into the station
box due to additional
surcharge because of stock
pile
Kaki Bukit Station – Challenges Encountered
Restriction
in space
• Top 2 metres
from ground
had scattered
services lines
that took an
additional 9
months for its
diversion and
trench
building
• Bottom up
might take less
time but
presence of
HDB and
factories on
either side of the
station made it
safe to use top
down
construction
method to limit
the D - wall
movement.
Why is there a discontinuity in the
coupler position ?
Presence of WATER STOP
Plan View
Elevation View
Water Stop
Stop End
Couplers
D - Wall
Why is there a
rope hanging
in a Slurry
Storage Tank
?
Desander
float
marker
Excavated area
Slurry
Storage
tank
marker
float
Construction Market
Activity Cycle Model
Where WE stand ?
Peak
Zone
Mid Zone
Trough Zone
GROWTH DECLINE
Apartment
Industrial Building Offices, HotelCIVIL
agnes kamsiah
CK SIMON
KINSKI
SELVAKUM
AR
MOD
YOU
GEN
SHAWN
Thank
you

Mais conteúdo relacionado

Mais procurados

Use of Waste Tyre as Subgrade in Flexible Pavement
Use of Waste Tyre as Subgrade in Flexible PavementUse of Waste Tyre as Subgrade in Flexible Pavement
Use of Waste Tyre as Subgrade in Flexible PavementIRJET Journal
 
Dynamic Modulus Master Curve Construction Using Christensen-Anderson-Marastea...
Dynamic Modulus Master Curve Construction Using Christensen-Anderson-Marastea...Dynamic Modulus Master Curve Construction Using Christensen-Anderson-Marastea...
Dynamic Modulus Master Curve Construction Using Christensen-Anderson-Marastea...IJERA Editor
 
gr_2016_cir-lam-card_fnl
gr_2016_cir-lam-card_fnlgr_2016_cir-lam-card_fnl
gr_2016_cir-lam-card_fnlDennis McElroy
 
Susan tighe green_roads-the_sustainable_road_ahead-ppt
Susan tighe green_roads-the_sustainable_road_ahead-pptSusan tighe green_roads-the_sustainable_road_ahead-ppt
Susan tighe green_roads-the_sustainable_road_ahead-pptSARFARAZ24
 
Designing and construction of piles under various field conditions
Designing and construction of piles under various field conditions Designing and construction of piles under various field conditions
Designing and construction of piles under various field conditions Dr. Naveen BP
 
Structural evaluation of low volume road pavements using pavement dynamic con...
Structural evaluation of low volume road pavements using pavement dynamic con...Structural evaluation of low volume road pavements using pavement dynamic con...
Structural evaluation of low volume road pavements using pavement dynamic con...eSAT Publishing House
 
Structural evaluation of low volume road pavements using pavement dynamic con...
Structural evaluation of low volume road pavements using pavement dynamic con...Structural evaluation of low volume road pavements using pavement dynamic con...
Structural evaluation of low volume road pavements using pavement dynamic con...eSAT Journals
 
IRJET- Experimental Study on Ground Improvement by using Concrete Piles
IRJET- Experimental Study on Ground Improvement by using Concrete PilesIRJET- Experimental Study on Ground Improvement by using Concrete Piles
IRJET- Experimental Study on Ground Improvement by using Concrete PilesIRJET Journal
 
Recycling of asphalt pavements - Via Nordica 2012
Recycling of asphalt pavements - Via Nordica 2012Recycling of asphalt pavements - Via Nordica 2012
Recycling of asphalt pavements - Via Nordica 2012Carl Christian Thodesen
 
SHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
SHATEC Engineering Consultants - Graniterock dba FMG CIR WhitepaperSHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
SHATEC Engineering Consultants - Graniterock dba FMG CIR WhitepaperDennis McElroy
 
Design and analysis of flexible pavemeT
Design and analysis of flexible pavemeTDesign and analysis of flexible pavemeT
Design and analysis of flexible pavemeTDevesh Chaurasia
 
Determining the rheological properties of asphalt
Determining the rheological properties of asphaltDetermining the rheological properties of asphalt
Determining the rheological properties of asphalteSAT Publishing House
 

Mais procurados (18)

Aashto design
Aashto designAashto design
Aashto design
 
PloymerHX_ppt
PloymerHX_pptPloymerHX_ppt
PloymerHX_ppt
 
Use of Waste Tyre as Subgrade in Flexible Pavement
Use of Waste Tyre as Subgrade in Flexible PavementUse of Waste Tyre as Subgrade in Flexible Pavement
Use of Waste Tyre as Subgrade in Flexible Pavement
 
Dynamic Modulus Master Curve Construction Using Christensen-Anderson-Marastea...
Dynamic Modulus Master Curve Construction Using Christensen-Anderson-Marastea...Dynamic Modulus Master Curve Construction Using Christensen-Anderson-Marastea...
Dynamic Modulus Master Curve Construction Using Christensen-Anderson-Marastea...
 
gr_2016_cir-lam-card_fnl
gr_2016_cir-lam-card_fnlgr_2016_cir-lam-card_fnl
gr_2016_cir-lam-card_fnl
 
Susan tighe green_roads-the_sustainable_road_ahead-ppt
Susan tighe green_roads-the_sustainable_road_ahead-pptSusan tighe green_roads-the_sustainable_road_ahead-ppt
Susan tighe green_roads-the_sustainable_road_ahead-ppt
 
Designing and construction of piles under various field conditions
Designing and construction of piles under various field conditions Designing and construction of piles under various field conditions
Designing and construction of piles under various field conditions
 
Structural evaluation of low volume road pavements using pavement dynamic con...
Structural evaluation of low volume road pavements using pavement dynamic con...Structural evaluation of low volume road pavements using pavement dynamic con...
Structural evaluation of low volume road pavements using pavement dynamic con...
 
Structural evaluation of low volume road pavements using pavement dynamic con...
Structural evaluation of low volume road pavements using pavement dynamic con...Structural evaluation of low volume road pavements using pavement dynamic con...
Structural evaluation of low volume road pavements using pavement dynamic con...
 
T10 sustainable pavements-la chance
T10 sustainable pavements-la chanceT10 sustainable pavements-la chance
T10 sustainable pavements-la chance
 
IRJET- Experimental Study on Ground Improvement by using Concrete Piles
IRJET- Experimental Study on Ground Improvement by using Concrete PilesIRJET- Experimental Study on Ground Improvement by using Concrete Piles
IRJET- Experimental Study on Ground Improvement by using Concrete Piles
 
V35119123
V35119123V35119123
V35119123
 
Recycling of asphalt pavements - Via Nordica 2012
Recycling of asphalt pavements - Via Nordica 2012Recycling of asphalt pavements - Via Nordica 2012
Recycling of asphalt pavements - Via Nordica 2012
 
construction management
construction managementconstruction management
construction management
 
SHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
SHATEC Engineering Consultants - Graniterock dba FMG CIR WhitepaperSHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
SHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
 
Anant Gupta CV
Anant Gupta CVAnant Gupta CV
Anant Gupta CV
 
Design and analysis of flexible pavemeT
Design and analysis of flexible pavemeTDesign and analysis of flexible pavemeT
Design and analysis of flexible pavemeT
 
Determining the rheological properties of asphalt
Determining the rheological properties of asphaltDetermining the rheological properties of asphalt
Determining the rheological properties of asphalt
 

Semelhante a Internship_report

investigation of low cost concrete using industrial waste as supplimentry cem...
investigation of low cost concrete using industrial waste as supplimentry cem...investigation of low cost concrete using industrial waste as supplimentry cem...
investigation of low cost concrete using industrial waste as supplimentry cem...Abhilash Chandra Dey
 
Susan tighe green_roads-the_sustainable_road_ahead-ppt
Susan tighe green_roads-the_sustainable_road_ahead-pptSusan tighe green_roads-the_sustainable_road_ahead-ppt
Susan tighe green_roads-the_sustainable_road_ahead-pptSARFARAZ24
 
Composite (GRP) Railway Stations & Solutions
Composite (GRP) Railway Stations & SolutionsComposite (GRP) Railway Stations & Solutions
Composite (GRP) Railway Stations & SolutionsAmbarjeet Shome
 
Polymer road technology
Polymer road technologyPolymer road technology
Polymer road technologyNikhil Bhole
 
Annayya S U - Project Phase 2 - 05.03.2023.ppt
Annayya S U - Project Phase 2 - 05.03.2023.pptAnnayya S U - Project Phase 2 - 05.03.2023.ppt
Annayya S U - Project Phase 2 - 05.03.2023.pptSuhasRamachandra10
 
IRJET- Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET-  	  Cost Analysis of Two-Way Slab and Post Tension SlabIRJET-  	  Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET- Cost Analysis of Two-Way Slab and Post Tension SlabIRJET Journal
 
An Experimental Study on Use of Cow Dung Ash and Rice Husk ASH as Partial Rep...
An Experimental Study on Use of Cow Dung Ash and Rice Husk ASH as Partial Rep...An Experimental Study on Use of Cow Dung Ash and Rice Husk ASH as Partial Rep...
An Experimental Study on Use of Cow Dung Ash and Rice Husk ASH as Partial Rep...Innocent Nsengimana
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017ktx500
 
Mud concrete block using construction and demolition waste live
Mud concrete block using construction and demolition waste liveMud concrete block using construction and demolition waste live
Mud concrete block using construction and demolition waste liveaadesh dhoka
 
Civil - Structural Works
Civil - Structural WorksCivil - Structural Works
Civil - Structural WorksBabu Arumugam
 
Precast modular structures
Precast modular structuresPrecast modular structures
Precast modular structuresAnirudh Gupta
 
Performance analysis of geosynthetics used in asphalt rehabilitation on urban...
Performance analysis of geosynthetics used in asphalt rehabilitation on urban...Performance analysis of geosynthetics used in asphalt rehabilitation on urban...
Performance analysis of geosynthetics used in asphalt rehabilitation on urban...Matthew Coleman
 
CERAMIC WASTE CONCRETE
CERAMIC WASTE CONCRETECERAMIC WASTE CONCRETE
CERAMIC WASTE CONCRETEseminarppts
 
2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...
2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...
2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...California Asphalt Pavement Association
 
IRJET- Experimental Investigation on Concrete by Partial Replacement of Coars...
IRJET- Experimental Investigation on Concrete by Partial Replacement of Coars...IRJET- Experimental Investigation on Concrete by Partial Replacement of Coars...
IRJET- Experimental Investigation on Concrete by Partial Replacement of Coars...IRJET Journal
 
Batch 10 - PPT.pptx
Batch 10 - PPT.pptxBatch 10 - PPT.pptx
Batch 10 - PPT.pptxDANIELDAS8
 

Semelhante a Internship_report (20)

investigation of low cost concrete using industrial waste as supplimentry cem...
investigation of low cost concrete using industrial waste as supplimentry cem...investigation of low cost concrete using industrial waste as supplimentry cem...
investigation of low cost concrete using industrial waste as supplimentry cem...
 
Susan tighe green_roads-the_sustainable_road_ahead-ppt
Susan tighe green_roads-the_sustainable_road_ahead-pptSusan tighe green_roads-the_sustainable_road_ahead-ppt
Susan tighe green_roads-the_sustainable_road_ahead-ppt
 
Composite (GRP) Railway Stations & Solutions
Composite (GRP) Railway Stations & SolutionsComposite (GRP) Railway Stations & Solutions
Composite (GRP) Railway Stations & Solutions
 
Polymer road technology
Polymer road technologyPolymer road technology
Polymer road technology
 
Annayya S U - Project Phase 2 - 05.03.2023.ppt
Annayya S U - Project Phase 2 - 05.03.2023.pptAnnayya S U - Project Phase 2 - 05.03.2023.ppt
Annayya S U - Project Phase 2 - 05.03.2023.ppt
 
PPT FINAL.pptx
PPT FINAL.pptxPPT FINAL.pptx
PPT FINAL.pptx
 
IRJET- Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET-  	  Cost Analysis of Two-Way Slab and Post Tension SlabIRJET-  	  Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET- Cost Analysis of Two-Way Slab and Post Tension Slab
 
An Experimental Study on Use of Cow Dung Ash and Rice Husk ASH as Partial Rep...
An Experimental Study on Use of Cow Dung Ash and Rice Husk ASH as Partial Rep...An Experimental Study on Use of Cow Dung Ash and Rice Husk ASH as Partial Rep...
An Experimental Study on Use of Cow Dung Ash and Rice Husk ASH as Partial Rep...
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017
 
2022 Long-life asphalt pavement at Caltrans
2022 Long-life asphalt pavement at Caltrans2022 Long-life asphalt pavement at Caltrans
2022 Long-life asphalt pavement at Caltrans
 
Mud concrete block using construction and demolition waste live
Mud concrete block using construction and demolition waste liveMud concrete block using construction and demolition waste live
Mud concrete block using construction and demolition waste live
 
Civil - Structural Works
Civil - Structural WorksCivil - Structural Works
Civil - Structural Works
 
Geotechnical Investigation
Geotechnical InvestigationGeotechnical Investigation
Geotechnical Investigation
 
Precast modular structures
Precast modular structuresPrecast modular structures
Precast modular structures
 
Performance analysis of geosynthetics used in asphalt rehabilitation on urban...
Performance analysis of geosynthetics used in asphalt rehabilitation on urban...Performance analysis of geosynthetics used in asphalt rehabilitation on urban...
Performance analysis of geosynthetics used in asphalt rehabilitation on urban...
 
CERAMIC WASTE CONCRETE
CERAMIC WASTE CONCRETECERAMIC WASTE CONCRETE
CERAMIC WASTE CONCRETE
 
PREETHAM B PPT.pptx
PREETHAM B   PPT.pptxPREETHAM B   PPT.pptx
PREETHAM B PPT.pptx
 
2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...
2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...
2023 CalAPA Spring Asphalt Conference presentation by John Harvey of the CCPI...
 
IRJET- Experimental Investigation on Concrete by Partial Replacement of Coars...
IRJET- Experimental Investigation on Concrete by Partial Replacement of Coars...IRJET- Experimental Investigation on Concrete by Partial Replacement of Coars...
IRJET- Experimental Investigation on Concrete by Partial Replacement of Coars...
 
Batch 10 - PPT.pptx
Batch 10 - PPT.pptxBatch 10 - PPT.pptx
Batch 10 - PPT.pptx
 

Internship_report

  • 1. Land Transport Authority We Keep Your World MOVING. We Keep Your World MOVING. We Keep You MOVING. We Keep Your World MOVING. We Keep Your World MOVING. Internship Presentation DEVARSH KUMAR 3rd year undergraduate Department of Civil Engineering Indian Institute of Technology Madras email – devarsh10iitm@gmail.com
  • 2. OUTLINE Top Down vs Bottom Up method in construction • TIME comparison • COST analysis Earth Pressure Balance TBM • OPEN CUT TUNNEL alignment of C928 • KEY position selection Sustainable Development • Environmentally improved material Learning Outcome • Challenges encountered • Site photos with description • Construction Market Activity Cycle Model
  • 3. C937B Tai Seng Facility Building C929 Kaki Bukit Station (Top Down) C929A C928 Bedok North Station (Bottom Up) C928 C929A C929A Layout Chart
  • 4. Rate of volume of earth to be excavated (20m) $129/m3 $99/m3 Rate of concrete to be used for roof slab (1.5m) $150/m3 $150/m3 Hypothetical Structure Length – 60 m Width – 24 m Top Down vs Bottom Up Total cost $4.0 M Total cost $4.7 M Less TIME taken
  • 5. Rate of volume of earth to be excavated (20m) $129/m3 $99/m3 Rate of concrete to be used for roof slab (1.5m) $150/m3 $150/m3 Rebar (adopt 230 kg/m3) $1.46/kg $1.46/kg Area of formwork to be used NA $75/m2 Hypothetical Structure Length – 60 m Width – 24 m Top Down vs Bottom Up Total cost $4.0 M Total cost $4.7 M Less TIME taken
  • 6. Reasons for higher cost of Top - Down • Limited construction openings for handling materials and machineries. • Limited headroom for excavators to operate. • Need more lightening and ventilation systems. • Even though there is no scaffolding materials used to prop the formwork to the soffit of the roof slab in Top – Down Method yet its price is high because of very high rate of the volume of earth to be excavated. NOTE – cost figure represent C929A and cannot be generalised
  • 8. Expo Bound Bukit Panjang Bound C929A Station Box C929 C928 WEST Cut and Cover Tunnel Alignment
  • 10. EAST Cut and Cover Tunnel Alignment C927 Expo Bound Bukit Panjang Bound Station Box C928
  • 13. KEY position 7 to 11 are not used because • It is difficult to install as Connection Segments (B) and Standard Segments (A) are under compression. • It is the weakest link. Sequence of Key Position Selection for building Segments
  • 14. Required Information • Straight portion of the Tunnel • Tunnel is moving UPWARD
  • 15. L16 R2, R5, R14
  • 16.
  • 17.
  • 19. Choose efficient formwork Timber Formwork System Formwork Material Timber & Plywood Aluminium Durability 20 times 120 – 150 times Wastage Yes No Quality Workmanship dependent Good Labour Skilled Unskilled Cost $26/m2 $34/m2 Source – Guidebook for best environmental practices, LTA, Singapore
  • 20. Environmentally Improved Materials • Using MILLED WASTE for temporary pathway instead of concrete. • Using factory prefabricated reinforcement because there is : 60% reduction in processing waste 30% increase in labour productivity • Good coverage of stockpile using Erosion Control Blanket either Natural material blanket or synthetic blanket. • Using Scrap bin for disposing welding rods, twisted steel wires, etc. for recycle.
  • 22. Challenges Encountered Bedok North Station (1) Water Canal Diversion Temporary Canal HDB D-WALL SBP In case of any failure, water will remain confine between D-Wall and SBP and station box remains unaffected
  • 23. Bedok North Station Challenges Encountered (2) Water Ingress Stock pile Water squeeze out from underground into the station box due to additional surcharge because of stock pile
  • 24. Kaki Bukit Station – Challenges Encountered Restriction in space • Top 2 metres from ground had scattered services lines that took an additional 9 months for its diversion and trench building • Bottom up might take less time but presence of HDB and factories on either side of the station made it safe to use top down construction method to limit the D - wall movement.
  • 25. Why is there a discontinuity in the coupler position ?
  • 27. Plan View Elevation View Water Stop Stop End Couplers D - Wall
  • 28. Why is there a rope hanging in a Slurry Storage Tank ?
  • 30. Construction Market Activity Cycle Model Where WE stand ?
  • 31. Peak Zone Mid Zone Trough Zone GROWTH DECLINE Apartment Industrial Building Offices, HotelCIVIL