Building Canada’s
Largest Gold Mine       Corporate Presentation
Production Early 2013        June 18-22, 2012
Forward Looking Information

This presentation contains certain forward-looking information as defined in applicable securities laws (referred to herein as “forward-
looking statements”). Specifically, this presentation contains forward-looking statements regarding the reserve and resource
estimates, ore grade, expected mine life, anticipated gold production, gold recovery, cash operating costs and other costs, capital
costs, sensitivity to metal prices and other sensitivities, financial analysis of the project, commencement of operations, potential
expansion opportunities, plans for organic growth and expected drilling activities. Forward-looking statements involve known and
unknown risks, uncertainties and other factors which are beyond Detour Gold’s ability to predict or control and may cause Detour
Gold’s actual results, performance or achievements to be materially different from any of its future results, performance or
achievements expressed or implied by forward-looking statements. These risks, uncertainties and other factors include, but are not
limited to, gold price volatility, changes in debt and equity markets, the uncertainties involved in interpreting geological data,
increases in costs, environmental compliance and changes in environmental legislation and regulation, interest rate and exchange
rate fluctuations, general economic conditions and other risks involved in the gold exploration and development industry, as well as
those risk factors discussed in the section entitled “Description of Business - Risk Factors” in Detour Gold’s 2011 AIF and in the
continuous disclosure documents filed by Detour Gold on and available on SEDAR at www.sedar.com. Such forward-looking
statements are also based on a number of assumptions which may prove to be incorrect, including, but not limited to, assumptions
about the following: the supply and demand for gold, and the level and volatility of the price of gold; the availability of financing for
exploration and development activities; the estimated timeline for the development of the Detour Lake gold project; the expected
mine life; anticipated gold production; gold recovery; the development schedule; cash operating costs and other costs; the financial
analysis for the project; capital costs; sensitivity to metal prices and other sensitivities; the accuracy of reserve and resource
estimates and the assumptions on which the reserve and resource estimates are based; the receipt of necessary permits; market
competition; ongoing relations with employees and impacted communities; and general business and economic conditions.
Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking statements contained
herein are made as of the date hereof, or such other date or dates specified in such statements. Detour Gold undertakes no
obligation to update publicly or otherwise revise any forward-looking statements contained herein whether as a result of new
information or future events or otherwise, except as may be required by law. If the Company does update one or more forward-
looking statements, no inference should be drawn that it will make additional updates with respect to those or other forward-looking
statements.




© 2011 Detour Gold All Rights Reserved.                                                                                                     2
NI 43-101 Disclosure

Information Concerning Estimates of Mineral Reserves and Resources

The mineral reserve and resource estimates reported in this presentation were prepared in accordance with Canadian National
Instrument 43-101Standards of Disclosure for Mineral Projects (“NI 43-101”), as required by Canadian securities regulatory
authorities. For United States reporting purposes, the United States Securities and Exchange Commission (“SEC”) applies different
standards in order to classify mineralization as a reserve. In particular, while the terms “measured,” “indicated” and “inferred” mineral
resources are required pursuant to NI 43-101, the SEC does not recognize such terms. Canadian standards differ significantly from
the requirements of the SEC. Investors are cautioned not to assume that any part or all of the mineral deposits in these categories
constitute or will ever be converted into reserves. In addition, “inferred” mineral resources have a great amount of uncertainty as to
their existence and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred
mineral resource will ever be upgraded to a higher category. Under Canadian securities laws, issuers must not make any disclosure
of results of an economic analysis that includes inferred mineral resources, except in rare cases.

On January 31, 2011, Detour Gold announced an updated mineral resource and reserve estimate. The following QPs participated in
this update: Michel Dagbert, Eng., Senior Geostatistician and André Laferrière, P. Geo., Senior Geologist of SGS Canada Inc.
(mineral resources); and André Allaire, Eng., Director Mining and Metals and Patrice Live, Eng., Mining Manager of BBA Inc (mineral
reserve). The NI 43-101 compliant Technical Report for this update was filed on SEDAR on March 15, 2011.

On January 25, 2012, Detour Gold announced a mineral resource and reserve update. The following QPs participated in this update:
Michel Dagbert, Eng., Senior Geostatistician of SGS Canada Inc (mineral resources) and Patrice Live, Eng., Mining Manager of BBA
Inc (mineral reserves).




© 2011 Detour Gold All Rights Reserved.                                                                                                      3
Invest in Detour Gold




   Focus on a world-class asset – Detour Lake
                 Canada’s largest pure gold play with 15.6 M oz in reserves
                  (@ US$ 850/oz gold price)
                 Construction progressing on schedule (70% as of May 31)
   One of the best cash flow/share opportunities
   Gold production starting in Q1 2013
   Excellent organic growth potential (5 year plan)
  Potential expansion of mill throughput


© 2011 Detour Gold All Rights Reserved.                                        4
Share Capital

     Issued and                           Convertible       Options & FN Share       Fully Diluted:
                                                              Commitments:
    Outstanding:              +             Notes:      +
       112.6 M                              13.0 M               8.7 M
                                                                                 =     134.3 M



         Market cap: C$2.6 Billion
         Cash position: C$683 Million
         Major shareholders:
           Paulson & Co.                                    15%                  Detour Lake
                Fidelity Mgmt                                8%
                Detour Gold Mgmt                            <2%
                Institutions total                          >90%


   Note: Share data and cash position as of May 31, 2012.

© 2011 Detour Gold All Rights Reserved.                                                               5
Strong Share Performance
                                    1000%
                                                Share Issuance vs. Performance                                                                          DGC equity financings
                                    900%
                                                                                                                                                            DGC
                                                                                                                                                            08/11
                                    800%
                                                       571% total return
                                                          since IPO
Jan. 2007 to Present Total Return




                                    700%
                                                                                                                                                                               DGC
                                                                                                                             DGC                                               01/12
                                    600%                                                                                     07/10

                                    500%
                                                          DGC
                                    400%                  04/08
                                                                                                    DGC
                                                                           Randgold
                                                                                                    11/09
                                    300%

                                                Buenaventura    DGC
                                    200%                        07/09
                                                                                                                      Eldorado                                                   Osisko
                                                                     AGI
                                    100%                                                                                                                                         (239%)
                                                Aurizon G
                                     IPO                             IMG                                               Yamana              Newcrest
                                                NEM      ABX
                                                                     AEM                                                                                                     Great Basin
                                      0%                                     Anglo Gold Ashanti                                                                     AuRico       (209%)
                                                  CG                                                                                            Hecla
                                                        Goldfields                                          Kinross
                                                                                          Gabriel                                Eco Oro
                                                       GSC                                                                                  Andina           Source: BMO, June 2012
                                    -100%
                                            0                                     50                             100                                  150                             200
                                                                                  Jan. 2007 to Present % Change in Shares Outstanding


© 2011 Detour Gold All Rights Reserved.                                                                                                                                                     6
Successful Focused Approach

  DETOUR LAKE:                                                                    Production
  RECORD TIMING FROM “DISCOVERY”                                                     2013
  TO PROJECTED PRODUCTION

  6 years                                                           Development
                                                                     2011-2012

                                                Feasibility Study
                                                  & Permitting
                                                      2010
                              Pre-feasibility
                                  Study
                                   2009
   Acquisition/
    Discovery
      2007

© 2011 Detour Gold All Rights Reserved.                                                        7
Detour Gold 2012 Objectives
      Mineral reserves/resources update for 2011 year-end
      Top up of $277 million to complete the project and working capital
      Second 45 km segment of transmission line complete
      230 kV transmission line connection in Q3
      Updated mine plan & operational forecast in Q3
      Ore stockpile of 3 Mt available in Q4 for processing
      Manpower ramp-up to 400 (now 273 employees at site and Cochrane)
      Delivery of 12 haul trucks and 2 cable shovels
      Drilling programs:
                50,000 m on Block A open pit & initiate pre-feasibility study
                5,060 m completed on Lower Detour Lake structure (targeting high-
                 grade mineralization)

    © 2011 Detour Gold All Rights Reserved.                                          8
Growing Reserve/Resource Base
 RESOURCE GROWTH EXCEEDING 750% SINCE IPO
 Date            Accumulative
                 DGC Drilling              Resources/Reserves (M oz)          Inferred   M&I   2P
                                                             10M               20M              30M
2005-05
                                               Estimated by Pelangio
2006-09                                          DGC due diligence
2007-12                 50,000m

2008-06               123,000m

2009-09               249,000m                         8.8

2010-06               334,000m             $850/oz           11.4

2011-01               430,000m             $850/oz                  14.9

2012-01               523,000m             $850/oz                     15.6


 © 2011 Detour Gold All Rights Reserved.                                                              9
Detour Lake Reserves & Resources

As at Dec. 31, 2011
                                 Tonnes      Grade        Contained Gold
@ US$850/oz
                                (millions)    (g/t)          (‘000 oz)
Reserves (1)
Proven                             101.6      1.29                4,222      DISCOVERY COST
Probable                           368.4      0.96              11,351          < $10/oz OF
P&P                              470.0       1.03             15,573
Resources (2)
                                                                                RESERVES
Measured                           124.5      1.36                5,424
Indicated                          554.3      1.00              17,836
M&I                              678.8       1.07             23,261
Inferred                         208.5       0.86               5,785




 1.     After a 95% mining recovery rate; Mining dilution factor of 15.5%.
 2.     Inclusive of mineral reserves.


© 2011 Detour Gold All Rights Reserved.                                                   10
Detour Lake Profile (@ US$850/oz)
                                           January 2012
Detour Lake                                   update

Production start                           Q1 2013
OP reserves (M oz)                            15.6                  Open pit
Mill throughput (tpd)                       55,000                  @ 0.5 g/t cut-off   20,600E
Strip ratio (waste:ore)                       3.6
Gold recoveries                               91%
Average grade (g/t)                           1.03
Estimated mine life (yrs)                      22
Avg. production (oz/yr)(1)(2)              657,000
                                                          16,500E
Initial Capex (C$ B)(3)                       1.45


                                                                                         >1.0 g/t Au

                                              700 m                                      0.5 - 1.0 g/t Au

1. After full commissioning in Yr 1.                                                     <0.5 g/t Au
2. Based on March 2011 TR.
3. Initial capex revised in November 2011.

 © 2011 Detour Gold All Rights Reserved.                                                               11
Valuation Re-rating:<1 Yr from Production

                  Intermediate Producers                                        Intermediate Producers
                    P/NAV (Average 0.9x)                                   Reserves/Share Ratio (Average 0.07)

                                                                                  0.17

                     1.1x 1.1x                                                           0.14
                                    1.0x
                                                                                                0.12
                                                   Avg 0.9x
                                           0.8x 0.8x

                                                       0.6x 0.6x
                                                                                                                Avg 0.07

                                                                                                       0.04 0.04 0.04
                                                                                                                        0.03




Source: Bloomberg and Company Reports, Equity Research and Thomson Financial at May 30, 2012.
Note: NAV per share figures are based on equity research consensus; Share data on fully diluted in the money shares outstanding.
.


© 2011 Detour Gold All Rights Reserved.                                                                                            12
Total Cash Costs
                                                                                 Since 2010 (release of Feasibility Study),
   $ 800      $ 796
                                                                               inflationary pressure seen in operating costs

                               $ 706          $ 706                                  Approx. % of total cash cost/oz in FS1
   $ 700

                                                                              Maintenance                                                    Consumables

   $ 600
                                                                                                      24%                        25%


   $ 500                                                                       Royalty          4%
                                                                                                  7%                                   14%           Labour
                                                                                       G&A
              Junior    Senior Intermediate
            Producers Producers Producers
                                                                                                          13%
                                                                                                                          13%
                                                                                             Diesel
2012E Cash Cost Profile (US$/oz)*                                                                                                     Power


*Source: BMO Equity Research
Seniors Producers include: Agnico-Eagle, AngloGold Ashanti, Barrick, Gold Fields, Goldcorp, Kinross, Newcrest, Newmont, Polyus and Yamana.
Intermediate Producers include: African Barrick, Alacer, AuRico, Centamin Egypt, Centerra, Eldorado, Harmony, IAMGold, New Gold, Osisko, Petropavlovsk, Randgold and SEMAFO.
Junior Producers include: Alamos Gold, Aurizon, Avion, Avocet, CGA Mining, Cluff Gold, Dundee Precious Metals, Golden Star, Great Basin Gold, Kingsgate, Lake Shore,
OceanaGold, Perseus, Primero, Resolute, San Gold and Teranga.

1. Total estimated cash cost of US$543/oz based on March 2011 TR using cost parameters from feasibility study, including US$850/oz gold price
   and US$80/barrel oil.


    © 2011 Detour Gold All Rights Reserved.                                                                                                                           13
Mine Site
Construction
Progressing on Schedule




© 2011 Detour Gold All Rights Reserved.   14
Detour Lake: We are on Schedule
                                                     2010                2011                2012          2013
Construction Schedule                          Q1   Q2   Q3   Q4   Q1   Q2   Q3   Q4   Q1   Q2   Q3   Q4    Q1



Award of Engineering Contract

Award of PCM Contract

Detailed Engineering

Construction camp (1,200 people)

Power line (Phase 1&2) – Electrification                            1                   2
Equipment purchase/delivery & assembly

Pre-stripping

Process plant – Commissioning start-up

Tailings dam construction (first cell)

Provincial Permits/Aboriginal IBAs

Federal Permits

Start production and ramp-up


                     GOLD PRODUCTION PROJECTED IN 1Q 2013

     © 2011 Detour Gold All Rights Reserved.                                                                 15
Detour Lake: We are on Budget

                  Capital Expenditures                        (C$ M)
                                                  Spent     Committed   Project Control
                  Description                     May 31,    May 31,       Estimate
                                                   2012       2012      (as of 11/2011)

                  Mining Fleet and Facilities      117          170            203
                  Crushing and Processing (P&E)    390          586            565
                  Tailings and Water Mgmt           15           45             65
                  Infrastructure and Power line    133          148            156
                  Other Indirect                   158          202            310
                  EPCM                              80          100            101
                  Contingency (10%)                   -           1             50
                  Total (pre-production)           893        1,252         1,450


                  PROJECT CONSTRUCTION 70% COMPLETE

© 2011 Detour Gold All Rights Reserved.                                                   16
2012 Operational Readiness Plan

Ore ready to be processed by the fourth quarter of 2012
      Pre-production capital costs include $78 M for pre-strip activities
      Up to 3 Mt of ore ready for process

     2012 Pre-Stripping                                                          PROJECT CHANGE
                                      Feasibility       PCE          Status         OF SCOPE
                                        Study         (11/2011)   (05/31/2012)
                                                                                         =
     Overburden/Till                          16 Mt      21 Mt      5.50 Mt
     Waste                                        -      10 Mt      1.82 Mt         A BENEFIT
     Ore                                                  3 Mt            -
                                                                                  Ore available for
     Estimated Cost                       C$30 M       C$78 M             -
                                                                                 processing in 2012



    © 2011 Detour Gold All Rights Reserved.                                                           17
Mining is Ramping Up




© 2011 Detour Gold All Rights Reserved.   18
Mining is Ramping Up




© 2011 Detour Gold All Rights Reserved.   19
Initial Mining Fleet at Site
 10 CAT 795F trucks at site (2 supplied by CAT);   Loading Units
  4 more being assembled
                                                     3 X Hydraulic CAT6060 (25 m3)
 2 CAT6060 shovels in operation
                                                     2 X Electric cable shovels (48 m3)
                                                    Haulers
                                                     23 X CAT 795F trucks (320 t);
                                                     30-35 at peak of operation




  © 2011 Detour Gold All Rights Reserved.                                            20
Detour Lake Development Progress
 Detailed engineering, procurement
  of major equipment and awarding
  of major contracts complete
 Second 45 km segment of
  powerline complete                                            Detour Lake
 Pre-stripping program ongoing               45 45 km
                                                 km
                                           Powerline
                                             Powerline
                                                             Gravel (34 km)

 Installation of mill equipment
  underway                                               Paved road (151 km)

 Truck wash facilities complete
 Permanent camp construction
  completed




 © 2011 Detour Gold All Rights Reserved.                                       21
Detour Lake
 Mining Facilities




© 2011 Detour Gold All Rights Reserved.
                                          Note: Open pit reserves using US$850/oz gold   22
                                                                                         22
Overview Detour Lake Facilities

                                             Processing Plant


                                                      Truck Wash
                                                                   Truck Shop &
                                                                   Warehouse




                         Mine Offices




12-06-08
   © 2011 Detour Gold All Rights Reserved.                                        23
Overview Detour Lake Facilities




                                             Stockpile
                                             Reclaim
Secondary
Crushers




                                                         Primary
                                                         Crusher


12-06-08
   © 2011 Detour Gold All Rights Reserved.                         24
Primary Crusher (up to 100,000 tpd capacity)




                                                       Here now
12-06-08                                     Surface



                                                       Gyro is
                                                       9 m high
                                               35 m




   © 2011 Detour Gold All Rights Reserved.                  25
Stockpile Reclaim


                                             Cover Stockpile
                                             Reclaim



                                                               12-06-08

                                                                          Secondary and
                                                                          Pebble Crushers




12-06-08

   © 2011 Detour Gold All Rights Reserved.                                                  26
Processing Plant Building



                                             Ball Mills




           SAG Mills




12-06-08
   © 2011 Detour Gold All Rights Reserved.                27
Processing Plant Building
                                               CIP Tanks




                                             Pumps


                                                           12-06-08




Hydrocyclones

   © 2011 Detour Gold All Rights Reserved.                       28
Simple Process Plant
    Conventional gravity and CIP plant
    55,000 tpd (=92% availability of 60,000
     tpd capacity)
    2 parallel lines (each with 1 secondary
     cone crusher + 1 SAG and 1 ball mill)                           A




                                                 Estimated gravity recovery: 30-40%
                                                 Estimated overall gold recovery: 91.0%
A                                                Leach time 29 hours
                                                 Leach feed size 80% passing 95 μm
    © 2011 Detour Gold All Rights Reserved.                                            29
Detour Lake Employees & Contractors
Construction Phase                        Operation Phase (Starting 2013)
   >1,500 workers (currently)               400-500 employees
   Ramping up DGC team (273)                Rotation 1 week in /out
                                             New modern camp facilities with
                                              400 en-suite rooms completed




© 2011 Detour Gold All Rights Reserved.                                         30
Focus: Hiring Local First
                    273 DETOUR GOLD EMPLOYEES (May 30, 2012)
                Require a complement of +400 employees by production start in early 2013



                                   25%
                                                              Workforce Origin
                                              Professional   4% 2%
                                              Front Line
                                                                                 Cochrane
                   75%
                                                                                 Cochrane Area
                                                                     28%
                                                                                 Northern Ontario
                                                             44%
    Professional are: MGMT, Eng., Geo., Supt.                        22%        Rest of Ontario
    Front Line are: Operators, Admin, Support
    28% Reside in Cochrane                                                      Other
    Continuing focus on hiring local/regional


     *25% of employees are Aboriginals

    © 2011 Detour Gold All Rights Reserved.                                                   31
Planning for Organic
Growth
Under-explored Greenstone Belt




© 2011 Detour Gold All Rights Reserved.   32
Planning for Organic Growth
 5 yr plan for successful organic growth
  Large prospective land position of approx. 540 km2
       Land position increased with acquisition of Trade Winds properties
       Two main gold structures with total strike length of >80 km
       Continue focus on Detour Lake deposit extension (northern structure)
       Test targets on structure south of Detour Lake


  Future Objectives
       Grow reserve base to +20 M oz (@ US$850/oz)
       Increase mill throughput to above 75,000 tpd for gold production
        output of +800,000 oz/yr
       Find high-grade ore near-surface within trucking distance to
        supplement mill

© 2011 Detour Gold All Rights Reserved.                                        33
2012 Plan for Successful Organic Growth
  Priority #1 on Block A
       Area between Block A open pit resource (M-Zone) and the
        underground QK Zone discovered by Placer in mid-90’s
                 Drilling program of 50,000 m in 1H 2012
                 Start pre-feasibility study for small open pit (Block A resource)
                 Advance exploration of QK underground zone


  Priority #2 on Lower Detour Deformation Zone (+40 km)
       5,060 m of diamond drilling completed: N-S drill fence on high-grade drill
        hole intercepts (53 g/t Au / 3 m & 22.6 g/t Au / 1 m)
       115 km of IP geophysical survey completed
       Geological and structural mapping; data compilation



© 2011 Detour Gold All Rights Reserved.                                               34
Planning for Organic Growth




                     2012 target




       Deposit open to the west and at depth
       +50,000 m of drilling for 2012 (Block A open pit above QK Zone)


     *Not updated with TWD Dec. 30th PR. On Dec. 1, 2011, Detour Gold announced the acquisition of TWD.


    © 2011 Detour Gold All Rights Reserved.                                                               35
Priority # 1 - Block A Target


Block A near-surface resource




   2012 proposed DH
   2012 extension DH
                                                          Detour Lake
  DH included in 2011 year-end
  reserves                                     2011 year-end reserves = 15.6 M oz
  DH not included in 2011 year-end
  reserves
  Historical DH




     © 2011 Detour Gold All Rights Reserved.                                        36
Priority # 1 - Block A Target


                                                Block A
                                          2012 Drilling Program




              June 10, 2012

              2012 proposed DH
              2012 extension DH                                   2011 year-end reserves
              2012 completed DH
              Historical DH                                                   = 15.6 M oz
              Cancelled or
              not accessible



© 2011 Detour Gold All Rights Reserved.                                                     37
Planning for Organic Growth

   +80 km of favourable
   geology



                                                                                            Sunday Lake Option


                                                               15.6 M oz in Reserves
                                                                                                     Existing DDH
                                                              Insert- see next slide                 Gold occurrence (OGS)
                                                                                                     DDH intersection >1g/2m
                                                                                                     DDH intersection >1g/10m




                                                 MMI Survey Coverage
                                                MMI Au Anomaly


                                          *Note: Excludes drilling around Detour Lake and M zone (Block A).
© 2011 Detour Gold All Rights Reserved.                                                                                    38
Planning for Organic Growth




                    Completed drilling




© 2011 Detour Gold All Rights Reserved.   39
Planning for Organic Growth




?




                            ?

© 2011 Detour Gold All Rights Reserved.   40
Evaluating Expansion Opportunities

                                  Best scenario is throughput
         2012                      increase from 55,000 to 75,000 tpd
                                   @ US$1,200/oz
                                  Start pre-feasibility on Block A

                                  Complete feasibility study and
         2013                      assess technical feasibility and
                                   resultant project economics

                                  At >US$1,000/oz and after
         2014                      successful commercial production
                                   is achieved, proceed with plant
                                   expansion
                                  Complete expansion within 2 years



© 2011 Detour Gold All Rights Reserved.                                 41
Invest in Detour Gold




   Focus on a world-class asset – Detour Lake
                 Canada’s largest pure gold play with 15.6 M oz in reserves
                  (@ US$ 850/oz gold price)
                 Construction progressing on schedule (70% as of May 31)
   One of the best cash flow/share opportunities
   Gold production starting in Q1 2013
   Excellent organic growth potential (5 year plan)
  Potential expansion of mill throughput


© 2011 Detour Gold All Rights Reserved.                                        42
Additional
Information




© 2011 Detour Gold All Rights Reserved.   43
Detour Lake – Surface Plan
                                          DH included in the 2011 year-end
                                          reserves
                                          DH not included in the 2011 year-end
                                          reserves
                                          Pre 2007 DH




2011 Year-end reserves
           = 15.6 M oz



© 2011 Detour Gold All Rights Reserved.                                          44
Detour Lake – Long Section

Looking 20,070 N




   QK Zone



                                          DH included in the 2011 year-end
                                          reserves
                                          DH not included in the 2011 year-end
                                          reserves
                                          Pre 2007 DH




© 2011 Detour Gold All Rights Reserved.                                      45
Block Model - Gold Distribution
                                 Approx. 3 M oz. between 0.3-0.5 g/t Au
                  1,600
                                                                                                                         OK (oz Au)
                                                                                                                         ID3 (oz Au)
                  1,400


                  1,200


                  1,000
 Ounces (000’s)




                   800


                   600


                   400


                   200


                     0
                          0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2.0 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 3.0
                                                                           Cut-off BINs

© 2011 Detour Gold All Rights Reserved.                                                                                                             46
Management & Directors
  Management
   Gerald Panneton, Founder, President &                     Derek Teevan, VP Aboriginal & Government
    CEO, Director                                              Affairs
   Michael Kenyon, Chairman                                  Eric Josipovic, Controller
   Paul Martin, CFO                                          Drew Anwyll, Director of Operations
   Pierre Beaudoin, Sr. VP Capital Projects                  Andrew Croal, Dir. Technical Services
   Pat Donovan, VP Corporate Development                     Laurie Gaborit, Dir. Investor Relations
   Julie Galloway, VP General Counsel &                      Greg Miazga, Dir. Construction &
    Corporate Secretary                                        Engineering
   James Mavor, VP Finance                                   Bill Snelling, Director Corporate Systems
   Rachel Pineault, VP HR & Northern                          and Controls
    Affairs                                                   Christian Brousseau, Project Manager
   James Robertson, VP Environment &                         Patrik Gillerstedt, Mine Manager
    Sustainability

 Directors
 Peter Crossgrove                         Ingrid Hibbard      Gerald Panneton
 Louis Dionne                             Michael Kenyon      Jonathan Rubenstein
 Robert E. Doyle                          Alex G. Morrison    Graham Wozniak



© 2011 Detour Gold All Rights Reserved.                                                              47
Contact Information

Gerald Panneton, President & CEO
Email: gpanneton@detourgold.com
Ph: 416 304 0800
Laurie Gaborit, Director Investor Relations
Email: lgaborit@detourgold.com
Ph: 416 304 0800




www.detourgold.com




© 2011 Detour Gold All Rights Reserved.       48

Mais conteúdo relacionado

Mais procurados

TD Securities Mining Conference Corporate Presentation
TD Securities Mining Conference Corporate PresentationTD Securities Mining Conference Corporate Presentation
TD Securities Mining Conference Corporate PresentationDetourGold
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate PresentationDetourGold
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate PresentationDetourGold
 
GasLog Q3 2012 results presentation
GasLog Q3 2012 results presentationGasLog Q3 2012 results presentation
GasLog Q3 2012 results presentationTradeWindsnews
 
2010 June Presentation
2010 June Presentation2010 June Presentation
2010 June PresentationGoldCorpInc
 
dana holdings Q208Earnings_080708
dana holdings Q208Earnings_080708dana holdings Q208Earnings_080708
dana holdings Q208Earnings_080708finance42
 
презентация для инвесторов, Non deal roadshow, европа и сша, 5-9 апреля 2010
презентация для инвесторов, Non deal roadshow, европа и сша, 5-9 апреля 2010презентация для инвесторов, Non deal roadshow, европа и сша, 5-9 апреля 2010
презентация для инвесторов, Non deal roadshow, европа и сша, 5-9 апреля 2010evraz_company
 
NAL Energy - 2012 CIBC Presentation
NAL Energy - 2012 CIBC PresentationNAL Energy - 2012 CIBC Presentation
NAL Energy - 2012 CIBC PresentationNALenergy
 
UBS Natural Gas, Electric Power & Coal Conference
UBS Natural Gas, Electric Power & Coal ConferenceUBS Natural Gas, Electric Power & Coal Conference
UBS Natural Gas, Electric Power & Coal Conferencefinance14
 
Corporate presentation june
Corporate presentation   juneCorporate presentation   june
Corporate presentation juneMPX_RI
 
el paso C0A209DE-4313-4A81-8B00-54550DEAC9E8_Barclays_Fixed_Income_032509
el paso  C0A209DE-4313-4A81-8B00-54550DEAC9E8_Barclays_Fixed_Income_032509el paso  C0A209DE-4313-4A81-8B00-54550DEAC9E8_Barclays_Fixed_Income_032509
el paso C0A209DE-4313-4A81-8B00-54550DEAC9E8_Barclays_Fixed_Income_032509finance49
 
PowerClip Warranty (3)
PowerClip Warranty (3)PowerClip Warranty (3)
PowerClip Warranty (3)MikeMcMullen
 
Cabo presentation feb282011ppt(f)
Cabo presentation feb282011ppt(f)Cabo presentation feb282011ppt(f)
Cabo presentation feb282011ppt(f)Company Spotlight
 
PEG_Boston Investor Meeting
PEG_Boston Investor MeetingPEG_Boston Investor Meeting
PEG_Boston Investor Meetingfinance20
 

Mais procurados (16)

TD Securities Mining Conference Corporate Presentation
TD Securities Mining Conference Corporate PresentationTD Securities Mining Conference Corporate Presentation
TD Securities Mining Conference Corporate Presentation
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate Presentation
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate Presentation
 
GasLog Q3 2012 results presentation
GasLog Q3 2012 results presentationGasLog Q3 2012 results presentation
GasLog Q3 2012 results presentation
 
2010 June Presentation
2010 June Presentation2010 June Presentation
2010 June Presentation
 
dana holdings Q208Earnings_080708
dana holdings Q208Earnings_080708dana holdings Q208Earnings_080708
dana holdings Q208Earnings_080708
 
презентация для инвесторов, Non deal roadshow, европа и сша, 5-9 апреля 2010
презентация для инвесторов, Non deal roadshow, европа и сша, 5-9 апреля 2010презентация для инвесторов, Non deal roadshow, европа и сша, 5-9 апреля 2010
презентация для инвесторов, Non deal roadshow, европа и сша, 5-9 апреля 2010
 
NAL Energy - 2012 CIBC Presentation
NAL Energy - 2012 CIBC PresentationNAL Energy - 2012 CIBC Presentation
NAL Energy - 2012 CIBC Presentation
 
UBS Natural Gas, Electric Power & Coal Conference
UBS Natural Gas, Electric Power & Coal ConferenceUBS Natural Gas, Electric Power & Coal Conference
UBS Natural Gas, Electric Power & Coal Conference
 
Corporate presentation june
Corporate presentation   juneCorporate presentation   june
Corporate presentation june
 
XEL_111506
XEL_111506XEL_111506
XEL_111506
 
el paso C0A209DE-4313-4A81-8B00-54550DEAC9E8_Barclays_Fixed_Income_032509
el paso  C0A209DE-4313-4A81-8B00-54550DEAC9E8_Barclays_Fixed_Income_032509el paso  C0A209DE-4313-4A81-8B00-54550DEAC9E8_Barclays_Fixed_Income_032509
el paso C0A209DE-4313-4A81-8B00-54550DEAC9E8_Barclays_Fixed_Income_032509
 
PowerClip Warranty (3)
PowerClip Warranty (3)PowerClip Warranty (3)
PowerClip Warranty (3)
 
Cabo presentation feb282011ppt(f)
Cabo presentation feb282011ppt(f)Cabo presentation feb282011ppt(f)
Cabo presentation feb282011ppt(f)
 
XEL_110306
XEL_110306XEL_110306
XEL_110306
 
PEG_Boston Investor Meeting
PEG_Boston Investor MeetingPEG_Boston Investor Meeting
PEG_Boston Investor Meeting
 

Destaque

Reservation xii
Reservation xiiReservation xii
Reservation xiimiarno
 
Detour Gold Corporate Presentation
Detour Gold Corporate PresentationDetour Gold Corporate Presentation
Detour Gold Corporate PresentationDetourGold
 
Dgc 14 06_17-18 - rbc conference
Dgc 14 06_17-18 - rbc conferenceDgc 14 06_17-18 - rbc conference
Dgc 14 06_17-18 - rbc conferenceDetourGold
 
Dgc 15 07_30 - corporate presentation
Dgc 15 07_30 - corporate presentationDgc 15 07_30 - corporate presentation
Dgc 15 07_30 - corporate presentationDetourGold
 
Dgc 14 12_02-03 - scotia conference
Dgc 14 12_02-03 - scotia conferenceDgc 14 12_02-03 - scotia conference
Dgc 14 12_02-03 - scotia conferenceDetourGold
 
Dgc 14 05_07-08 - corporate presentation
Dgc 14 05_07-08 - corporate presentationDgc 14 05_07-08 - corporate presentation
Dgc 14 05_07-08 - corporate presentationDetourGold
 
Dgc 14 05_01 _ q12014
Dgc 14 05_01 _ q12014Dgc 14 05_01 _ q12014
Dgc 14 05_01 _ q12014DetourGold
 

Destaque (7)

Reservation xii
Reservation xiiReservation xii
Reservation xii
 
Detour Gold Corporate Presentation
Detour Gold Corporate PresentationDetour Gold Corporate Presentation
Detour Gold Corporate Presentation
 
Dgc 14 06_17-18 - rbc conference
Dgc 14 06_17-18 - rbc conferenceDgc 14 06_17-18 - rbc conference
Dgc 14 06_17-18 - rbc conference
 
Dgc 15 07_30 - corporate presentation
Dgc 15 07_30 - corporate presentationDgc 15 07_30 - corporate presentation
Dgc 15 07_30 - corporate presentation
 
Dgc 14 12_02-03 - scotia conference
Dgc 14 12_02-03 - scotia conferenceDgc 14 12_02-03 - scotia conference
Dgc 14 12_02-03 - scotia conference
 
Dgc 14 05_07-08 - corporate presentation
Dgc 14 05_07-08 - corporate presentationDgc 14 05_07-08 - corporate presentation
Dgc 14 05_07-08 - corporate presentation
 
Dgc 14 05_01 _ q12014
Dgc 14 05_01 _ q12014Dgc 14 05_01 _ q12014
Dgc 14 05_01 _ q12014
 

Semelhante a Corporate Presentation June 18-22, 2012

National Bank Financial London Gold Conference Corporate Presentation
National Bank Financial London Gold Conference Corporate PresentationNational Bank Financial London Gold Conference Corporate Presentation
National Bank Financial London Gold Conference Corporate PresentationDetourGold
 
Dgc 13 01_20-21_cambridge house vric
Dgc 13 01_20-21_cambridge house vricDgc 13 01_20-21_cambridge house vric
Dgc 13 01_20-21_cambridge house vricDetourGold
 
Avion Corporate Presentation Feb 2011
Avion Corporate Presentation Feb 2011Avion Corporate Presentation Feb 2011
Avion Corporate Presentation Feb 2011Avion Gold Corp
 
Dgc 13 02_24-27_bmo metals and mining conference
Dgc 13 02_24-27_bmo metals and mining conferenceDgc 13 02_24-27_bmo metals and mining conference
Dgc 13 02_24-27_bmo metals and mining conferenceDetourGold
 
Avion corporate presentation - Jan 2011
Avion corporate presentation - Jan 2011Avion corporate presentation - Jan 2011
Avion corporate presentation - Jan 2011Avion Gold Corp
 
Corporate presentation april
Corporate presentation   aprilCorporate presentation   april
Corporate presentation aprilMPX_RI
 
BoAML Canada Mining Conference, Toronto
BoAML Canada Mining Conference, TorontoBoAML Canada Mining Conference, Toronto
BoAML Canada Mining Conference, TorontoDetourGold
 
Dgc 13 09_12-13_bo_aml conference
Dgc 13 09_12-13_bo_aml conferenceDgc 13 09_12-13_bo_aml conference
Dgc 13 09_12-13_bo_aml conferenceDetourGold
 
Dgc 13 04_16-18_european gold forum
Dgc 13 04_16-18_european gold forumDgc 13 04_16-18_european gold forum
Dgc 13 04_16-18_european gold forumDetourGold
 
Detour Gold Corporate Presentation
Detour Gold Corporate PresentationDetour Gold Corporate Presentation
Detour Gold Corporate PresentationDetourGold
 
Investor Presentation April 2012
Investor Presentation April 2012Investor Presentation April 2012
Investor Presentation April 2012PetroMagdalena
 
Edgewater Presentation January 2013
Edgewater Presentation January 2013Edgewater Presentation January 2013
Edgewater Presentation January 2013Adnet Communications
 
public serviceenterprise group Morgan Stanley
public serviceenterprise group Morgan Stanleypublic serviceenterprise group Morgan Stanley
public serviceenterprise group Morgan Stanleyfinance20
 
PEG_MorganStanley
PEG_MorganStanleyPEG_MorganStanley
PEG_MorganStanleyfinance20
 
GE- Goldman Sachs Fourth Annual Alternative Energy Conference
GE- Goldman Sachs Fourth Annual Alternative Energy Conference GE- Goldman Sachs Fourth Annual Alternative Energy Conference
GE- Goldman Sachs Fourth Annual Alternative Energy Conference Manya Mohan
 

Semelhante a Corporate Presentation June 18-22, 2012 (20)

02252013 bmo presentationupdated
02252013 bmo presentationupdated02252013 bmo presentationupdated
02252013 bmo presentationupdated
 
BMO Global Metals & Mining Conference 2013
BMO Global Metals & Mining Conference 2013BMO Global Metals & Mining Conference 2013
BMO Global Metals & Mining Conference 2013
 
National Bank Financial London Gold Conference Corporate Presentation
National Bank Financial London Gold Conference Corporate PresentationNational Bank Financial London Gold Conference Corporate Presentation
National Bank Financial London Gold Conference Corporate Presentation
 
Dgc 13 01_20-21_cambridge house vric
Dgc 13 01_20-21_cambridge house vricDgc 13 01_20-21_cambridge house vric
Dgc 13 01_20-21_cambridge house vric
 
Avion Corporate Presentation Feb 2011
Avion Corporate Presentation Feb 2011Avion Corporate Presentation Feb 2011
Avion Corporate Presentation Feb 2011
 
Q4 & 2012 Earnings
Q4 & 2012 EarningsQ4 & 2012 Earnings
Q4 & 2012 Earnings
 
Dgc 13 02_24-27_bmo metals and mining conference
Dgc 13 02_24-27_bmo metals and mining conferenceDgc 13 02_24-27_bmo metals and mining conference
Dgc 13 02_24-27_bmo metals and mining conference
 
Sau ppt march_2012_final
Sau ppt march_2012_finalSau ppt march_2012_final
Sau ppt march_2012_final
 
Avion corporate presentation - Jan 2011
Avion corporate presentation - Jan 2011Avion corporate presentation - Jan 2011
Avion corporate presentation - Jan 2011
 
Corporate presentation april
Corporate presentation   aprilCorporate presentation   april
Corporate presentation april
 
BoAML Canada Mining Conference, Toronto
BoAML Canada Mining Conference, TorontoBoAML Canada Mining Conference, Toronto
BoAML Canada Mining Conference, Toronto
 
Dgc 13 09_12-13_bo_aml conference
Dgc 13 09_12-13_bo_aml conferenceDgc 13 09_12-13_bo_aml conference
Dgc 13 09_12-13_bo_aml conference
 
Dgc 13 04_16-18_european gold forum
Dgc 13 04_16-18_european gold forumDgc 13 04_16-18_european gold forum
Dgc 13 04_16-18_european gold forum
 
Detour Gold Corporate Presentation
Detour Gold Corporate PresentationDetour Gold Corporate Presentation
Detour Gold Corporate Presentation
 
Investor Presentation April 2012
Investor Presentation April 2012Investor Presentation April 2012
Investor Presentation April 2012
 
Edgewater Presentation January 2013
Edgewater Presentation January 2013Edgewater Presentation January 2013
Edgewater Presentation January 2013
 
public serviceenterprise group Morgan Stanley
public serviceenterprise group Morgan Stanleypublic serviceenterprise group Morgan Stanley
public serviceenterprise group Morgan Stanley
 
PEG_MorganStanley
PEG_MorganStanleyPEG_MorganStanley
PEG_MorganStanley
 
GE- Goldman Sachs Fourth Annual Alternative Energy Conference
GE- Goldman Sachs Fourth Annual Alternative Energy Conference GE- Goldman Sachs Fourth Annual Alternative Energy Conference
GE- Goldman Sachs Fourth Annual Alternative Energy Conference
 
Feb edw-presentation-2013
Feb edw-presentation-2013Feb edw-presentation-2013
Feb edw-presentation-2013
 

Mais de DetourGold

Dgc 17 04_4-6_dgf zurich corporate 1x1 presentation
Dgc 17 04_4-6_dgf zurich corporate 1x1 presentationDgc 17 04_4-6_dgf zurich corporate 1x1 presentation
Dgc 17 04_4-6_dgf zurich corporate 1x1 presentationDetourGold
 
Dgc 17 03_24_corporate presentation
Dgc 17 03_24_corporate presentationDgc 17 03_24_corporate presentation
Dgc 17 03_24_corporate presentationDetourGold
 
Dgc 17 02_27 - bmo presentation_final
Dgc 17 02_27 - bmo presentation_finalDgc 17 02_27 - bmo presentation_final
Dgc 17 02_27 - bmo presentation_finalDetourGold
 
Presentation dgc 17-01_31 _ q4 ops 2017 guidance webcast
Presentation   dgc 17-01_31 _ q4 ops 2017 guidance webcastPresentation   dgc 17-01_31 _ q4 ops 2017 guidance webcast
Presentation dgc 17-01_31 _ q4 ops 2017 guidance webcastDetourGold
 
Dgc 16 11_8-9 - corporate presentation
Dgc 16 11_8-9 - corporate presentationDgc 16 11_8-9 - corporate presentation
Dgc 16 11_8-9 - corporate presentationDetourGold
 
Dgc 16 11_02 - corporate presentation
Dgc 16 11_02 - corporate presentationDgc 16 11_02 - corporate presentation
Dgc 16 11_02 - corporate presentationDetourGold
 
Dgc 16 09_18-21 - dgf conference_1x1
Dgc 16 09_18-21 - dgf conference_1x1Dgc 16 09_18-21 - dgf conference_1x1
Dgc 16 09_18-21 - dgf conference_1x1DetourGold
 
Dgc 16 09_08 - baml conference
Dgc 16 09_08 - baml conferenceDgc 16 09_08 - baml conference
Dgc 16 09_08 - baml conferenceDetourGold
 
Dgc 16 08_30-31 - corporate presentation
Dgc 16 08_30-31 - corporate presentationDgc 16 08_30-31 - corporate presentation
Dgc 16 08_30-31 - corporate presentationDetourGold
 
Dgc 16 06_14-15 - rbc conference
Dgc 16 06_14-15 - rbc conferenceDgc 16 06_14-15 - rbc conference
Dgc 16 06_14-15 - rbc conferenceDetourGold
 
Dgc 16 05_10-12 - BAML conference
Dgc 16 05_10-12 - BAML conferenceDgc 16 05_10-12 - BAML conference
Dgc 16 05_10-12 - BAML conferenceDetourGold
 
BMO Global Metals & Mining Conference - Hollywood, FL
BMO Global Metals & Mining Conference - Hollywood, FLBMO Global Metals & Mining Conference - Hollywood, FL
BMO Global Metals & Mining Conference - Hollywood, FLDetourGold
 
Dgc 16 02_09-10 - corporate presentation
Dgc 16 02_09-10 - corporate presentationDgc 16 02_09-10 - corporate presentation
Dgc 16 02_09-10 - corporate presentationDetourGold
 
Dgc 16 01_26 - td conference
Dgc 16 01_26 - td conferenceDgc 16 01_26 - td conference
Dgc 16 01_26 - td conferenceDetourGold
 
Dgc 16 01_20 - cibc whistler conference
Dgc 16 01_20 - cibc whistler conferenceDgc 16 01_20 - cibc whistler conference
Dgc 16 01_20 - cibc whistler conferenceDetourGold
 
Dgc 15 12_1-2 - scotia mining conference 1-1
Dgc 15 12_1-2 - scotia mining conference 1-1Dgc 15 12_1-2 - scotia mining conference 1-1
Dgc 15 12_1-2 - scotia mining conference 1-1DetourGold
 
Dgc 15 11_17 - rj texas gold investor forum
Dgc 15 11_17 - rj texas gold investor forumDgc 15 11_17 - rj texas gold investor forum
Dgc 15 11_17 - rj texas gold investor forumDetourGold
 
Dgc 15 11_10 - nbf-tsx canadian miners conference
Dgc 15 11_10 - nbf-tsx canadian miners conferenceDgc 15 11_10 - nbf-tsx canadian miners conference
Dgc 15 11_10 - nbf-tsx canadian miners conferenceDetourGold
 
Dgc 15 10_29 - corporate presentation
Dgc 15 10_29 - corporate presentationDgc 15 10_29 - corporate presentation
Dgc 15 10_29 - corporate presentationDetourGold
 
Dgc 15 09_20-23 - dgf 1x1 presentation
Dgc 15 09_20-23 - dgf 1x1 presentationDgc 15 09_20-23 - dgf 1x1 presentation
Dgc 15 09_20-23 - dgf 1x1 presentationDetourGold
 

Mais de DetourGold (20)

Dgc 17 04_4-6_dgf zurich corporate 1x1 presentation
Dgc 17 04_4-6_dgf zurich corporate 1x1 presentationDgc 17 04_4-6_dgf zurich corporate 1x1 presentation
Dgc 17 04_4-6_dgf zurich corporate 1x1 presentation
 
Dgc 17 03_24_corporate presentation
Dgc 17 03_24_corporate presentationDgc 17 03_24_corporate presentation
Dgc 17 03_24_corporate presentation
 
Dgc 17 02_27 - bmo presentation_final
Dgc 17 02_27 - bmo presentation_finalDgc 17 02_27 - bmo presentation_final
Dgc 17 02_27 - bmo presentation_final
 
Presentation dgc 17-01_31 _ q4 ops 2017 guidance webcast
Presentation   dgc 17-01_31 _ q4 ops 2017 guidance webcastPresentation   dgc 17-01_31 _ q4 ops 2017 guidance webcast
Presentation dgc 17-01_31 _ q4 ops 2017 guidance webcast
 
Dgc 16 11_8-9 - corporate presentation
Dgc 16 11_8-9 - corporate presentationDgc 16 11_8-9 - corporate presentation
Dgc 16 11_8-9 - corporate presentation
 
Dgc 16 11_02 - corporate presentation
Dgc 16 11_02 - corporate presentationDgc 16 11_02 - corporate presentation
Dgc 16 11_02 - corporate presentation
 
Dgc 16 09_18-21 - dgf conference_1x1
Dgc 16 09_18-21 - dgf conference_1x1Dgc 16 09_18-21 - dgf conference_1x1
Dgc 16 09_18-21 - dgf conference_1x1
 
Dgc 16 09_08 - baml conference
Dgc 16 09_08 - baml conferenceDgc 16 09_08 - baml conference
Dgc 16 09_08 - baml conference
 
Dgc 16 08_30-31 - corporate presentation
Dgc 16 08_30-31 - corporate presentationDgc 16 08_30-31 - corporate presentation
Dgc 16 08_30-31 - corporate presentation
 
Dgc 16 06_14-15 - rbc conference
Dgc 16 06_14-15 - rbc conferenceDgc 16 06_14-15 - rbc conference
Dgc 16 06_14-15 - rbc conference
 
Dgc 16 05_10-12 - BAML conference
Dgc 16 05_10-12 - BAML conferenceDgc 16 05_10-12 - BAML conference
Dgc 16 05_10-12 - BAML conference
 
BMO Global Metals & Mining Conference - Hollywood, FL
BMO Global Metals & Mining Conference - Hollywood, FLBMO Global Metals & Mining Conference - Hollywood, FL
BMO Global Metals & Mining Conference - Hollywood, FL
 
Dgc 16 02_09-10 - corporate presentation
Dgc 16 02_09-10 - corporate presentationDgc 16 02_09-10 - corporate presentation
Dgc 16 02_09-10 - corporate presentation
 
Dgc 16 01_26 - td conference
Dgc 16 01_26 - td conferenceDgc 16 01_26 - td conference
Dgc 16 01_26 - td conference
 
Dgc 16 01_20 - cibc whistler conference
Dgc 16 01_20 - cibc whistler conferenceDgc 16 01_20 - cibc whistler conference
Dgc 16 01_20 - cibc whistler conference
 
Dgc 15 12_1-2 - scotia mining conference 1-1
Dgc 15 12_1-2 - scotia mining conference 1-1Dgc 15 12_1-2 - scotia mining conference 1-1
Dgc 15 12_1-2 - scotia mining conference 1-1
 
Dgc 15 11_17 - rj texas gold investor forum
Dgc 15 11_17 - rj texas gold investor forumDgc 15 11_17 - rj texas gold investor forum
Dgc 15 11_17 - rj texas gold investor forum
 
Dgc 15 11_10 - nbf-tsx canadian miners conference
Dgc 15 11_10 - nbf-tsx canadian miners conferenceDgc 15 11_10 - nbf-tsx canadian miners conference
Dgc 15 11_10 - nbf-tsx canadian miners conference
 
Dgc 15 10_29 - corporate presentation
Dgc 15 10_29 - corporate presentationDgc 15 10_29 - corporate presentation
Dgc 15 10_29 - corporate presentation
 
Dgc 15 09_20-23 - dgf 1x1 presentation
Dgc 15 09_20-23 - dgf 1x1 presentationDgc 15 09_20-23 - dgf 1x1 presentation
Dgc 15 09_20-23 - dgf 1x1 presentation
 

Último

Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024Probe Gold
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfProbe Gold
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfFrancenel
 
Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024CollectiveMining1
 
Mandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR PresentationMandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR PresentationMandalayResources
 
Q1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfQ1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfProbe Gold
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfProbe Gold
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfsansanir
 
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024Osisko Gold Royalties Ltd
 
Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024CollectiveMining1
 
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...USDAReapgrants.com
 

Último (12)

Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdf
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdf
 
Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024
 
Korea District Heating Corporation 071320 Algorithm Investment Report
Korea District Heating Corporation 071320 Algorithm Investment ReportKorea District Heating Corporation 071320 Algorithm Investment Report
Korea District Heating Corporation 071320 Algorithm Investment Report
 
Mandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR PresentationMandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR Presentation
 
Q1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfQ1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdf
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdf
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdf
 
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
 
Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024
 
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
 

Corporate Presentation June 18-22, 2012

  • 1. Building Canada’s Largest Gold Mine Corporate Presentation Production Early 2013 June 18-22, 2012
  • 2. Forward Looking Information This presentation contains certain forward-looking information as defined in applicable securities laws (referred to herein as “forward- looking statements”). Specifically, this presentation contains forward-looking statements regarding the reserve and resource estimates, ore grade, expected mine life, anticipated gold production, gold recovery, cash operating costs and other costs, capital costs, sensitivity to metal prices and other sensitivities, financial analysis of the project, commencement of operations, potential expansion opportunities, plans for organic growth and expected drilling activities. Forward-looking statements involve known and unknown risks, uncertainties and other factors which are beyond Detour Gold’s ability to predict or control and may cause Detour Gold’s actual results, performance or achievements to be materially different from any of its future results, performance or achievements expressed or implied by forward-looking statements. These risks, uncertainties and other factors include, but are not limited to, gold price volatility, changes in debt and equity markets, the uncertainties involved in interpreting geological data, increases in costs, environmental compliance and changes in environmental legislation and regulation, interest rate and exchange rate fluctuations, general economic conditions and other risks involved in the gold exploration and development industry, as well as those risk factors discussed in the section entitled “Description of Business - Risk Factors” in Detour Gold’s 2011 AIF and in the continuous disclosure documents filed by Detour Gold on and available on SEDAR at www.sedar.com. Such forward-looking statements are also based on a number of assumptions which may prove to be incorrect, including, but not limited to, assumptions about the following: the supply and demand for gold, and the level and volatility of the price of gold; the availability of financing for exploration and development activities; the estimated timeline for the development of the Detour Lake gold project; the expected mine life; anticipated gold production; gold recovery; the development schedule; cash operating costs and other costs; the financial analysis for the project; capital costs; sensitivity to metal prices and other sensitivities; the accuracy of reserve and resource estimates and the assumptions on which the reserve and resource estimates are based; the receipt of necessary permits; market competition; ongoing relations with employees and impacted communities; and general business and economic conditions. Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking statements contained herein are made as of the date hereof, or such other date or dates specified in such statements. Detour Gold undertakes no obligation to update publicly or otherwise revise any forward-looking statements contained herein whether as a result of new information or future events or otherwise, except as may be required by law. If the Company does update one or more forward- looking statements, no inference should be drawn that it will make additional updates with respect to those or other forward-looking statements. © 2011 Detour Gold All Rights Reserved. 2
  • 3. NI 43-101 Disclosure Information Concerning Estimates of Mineral Reserves and Resources The mineral reserve and resource estimates reported in this presentation were prepared in accordance with Canadian National Instrument 43-101Standards of Disclosure for Mineral Projects (“NI 43-101”), as required by Canadian securities regulatory authorities. For United States reporting purposes, the United States Securities and Exchange Commission (“SEC”) applies different standards in order to classify mineralization as a reserve. In particular, while the terms “measured,” “indicated” and “inferred” mineral resources are required pursuant to NI 43-101, the SEC does not recognize such terms. Canadian standards differ significantly from the requirements of the SEC. Investors are cautioned not to assume that any part or all of the mineral deposits in these categories constitute or will ever be converted into reserves. In addition, “inferred” mineral resources have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category. Under Canadian securities laws, issuers must not make any disclosure of results of an economic analysis that includes inferred mineral resources, except in rare cases. On January 31, 2011, Detour Gold announced an updated mineral resource and reserve estimate. The following QPs participated in this update: Michel Dagbert, Eng., Senior Geostatistician and André Laferrière, P. Geo., Senior Geologist of SGS Canada Inc. (mineral resources); and André Allaire, Eng., Director Mining and Metals and Patrice Live, Eng., Mining Manager of BBA Inc (mineral reserve). The NI 43-101 compliant Technical Report for this update was filed on SEDAR on March 15, 2011. On January 25, 2012, Detour Gold announced a mineral resource and reserve update. The following QPs participated in this update: Michel Dagbert, Eng., Senior Geostatistician of SGS Canada Inc (mineral resources) and Patrice Live, Eng., Mining Manager of BBA Inc (mineral reserves). © 2011 Detour Gold All Rights Reserved. 3
  • 4. Invest in Detour Gold  Focus on a world-class asset – Detour Lake  Canada’s largest pure gold play with 15.6 M oz in reserves (@ US$ 850/oz gold price)  Construction progressing on schedule (70% as of May 31)  One of the best cash flow/share opportunities  Gold production starting in Q1 2013  Excellent organic growth potential (5 year plan)  Potential expansion of mill throughput © 2011 Detour Gold All Rights Reserved. 4
  • 5. Share Capital Issued and Convertible Options & FN Share Fully Diluted: Commitments: Outstanding: + Notes: + 112.6 M 13.0 M 8.7 M = 134.3 M  Market cap: C$2.6 Billion  Cash position: C$683 Million  Major shareholders: Paulson & Co. 15% Detour Lake Fidelity Mgmt 8% Detour Gold Mgmt <2% Institutions total >90% Note: Share data and cash position as of May 31, 2012. © 2011 Detour Gold All Rights Reserved. 5
  • 6. Strong Share Performance 1000% Share Issuance vs. Performance DGC equity financings 900% DGC 08/11 800% 571% total return since IPO Jan. 2007 to Present Total Return 700% DGC DGC 01/12 600% 07/10 500% DGC 400% 04/08 DGC Randgold 11/09 300% Buenaventura DGC 200% 07/09 Eldorado Osisko AGI 100% (239%) Aurizon G IPO IMG Yamana Newcrest NEM ABX AEM Great Basin 0% Anglo Gold Ashanti AuRico (209%) CG Hecla Goldfields Kinross Gabriel Eco Oro GSC Andina Source: BMO, June 2012 -100% 0 50 100 150 200 Jan. 2007 to Present % Change in Shares Outstanding © 2011 Detour Gold All Rights Reserved. 6
  • 7. Successful Focused Approach DETOUR LAKE: Production RECORD TIMING FROM “DISCOVERY” 2013 TO PROJECTED PRODUCTION 6 years Development 2011-2012 Feasibility Study & Permitting 2010 Pre-feasibility Study 2009 Acquisition/ Discovery 2007 © 2011 Detour Gold All Rights Reserved. 7
  • 8. Detour Gold 2012 Objectives  Mineral reserves/resources update for 2011 year-end  Top up of $277 million to complete the project and working capital  Second 45 km segment of transmission line complete  230 kV transmission line connection in Q3  Updated mine plan & operational forecast in Q3  Ore stockpile of 3 Mt available in Q4 for processing  Manpower ramp-up to 400 (now 273 employees at site and Cochrane)  Delivery of 12 haul trucks and 2 cable shovels  Drilling programs:  50,000 m on Block A open pit & initiate pre-feasibility study  5,060 m completed on Lower Detour Lake structure (targeting high- grade mineralization) © 2011 Detour Gold All Rights Reserved. 8
  • 9. Growing Reserve/Resource Base RESOURCE GROWTH EXCEEDING 750% SINCE IPO Date Accumulative DGC Drilling Resources/Reserves (M oz) Inferred M&I 2P 10M 20M 30M 2005-05 Estimated by Pelangio 2006-09 DGC due diligence 2007-12 50,000m 2008-06 123,000m 2009-09 249,000m 8.8 2010-06 334,000m $850/oz 11.4 2011-01 430,000m $850/oz 14.9 2012-01 523,000m $850/oz 15.6 © 2011 Detour Gold All Rights Reserved. 9
  • 10. Detour Lake Reserves & Resources As at Dec. 31, 2011 Tonnes Grade Contained Gold @ US$850/oz (millions) (g/t) (‘000 oz) Reserves (1) Proven 101.6 1.29 4,222 DISCOVERY COST Probable 368.4 0.96 11,351 < $10/oz OF P&P 470.0 1.03 15,573 Resources (2) RESERVES Measured 124.5 1.36 5,424 Indicated 554.3 1.00 17,836 M&I 678.8 1.07 23,261 Inferred 208.5 0.86 5,785 1. After a 95% mining recovery rate; Mining dilution factor of 15.5%. 2. Inclusive of mineral reserves. © 2011 Detour Gold All Rights Reserved. 10
  • 11. Detour Lake Profile (@ US$850/oz) January 2012 Detour Lake update Production start Q1 2013 OP reserves (M oz) 15.6 Open pit Mill throughput (tpd) 55,000 @ 0.5 g/t cut-off 20,600E Strip ratio (waste:ore) 3.6 Gold recoveries 91% Average grade (g/t) 1.03 Estimated mine life (yrs) 22 Avg. production (oz/yr)(1)(2) 657,000 16,500E Initial Capex (C$ B)(3) 1.45 >1.0 g/t Au 700 m 0.5 - 1.0 g/t Au 1. After full commissioning in Yr 1. <0.5 g/t Au 2. Based on March 2011 TR. 3. Initial capex revised in November 2011. © 2011 Detour Gold All Rights Reserved. 11
  • 12. Valuation Re-rating:<1 Yr from Production Intermediate Producers Intermediate Producers P/NAV (Average 0.9x) Reserves/Share Ratio (Average 0.07) 0.17 1.1x 1.1x 0.14 1.0x 0.12 Avg 0.9x 0.8x 0.8x 0.6x 0.6x Avg 0.07 0.04 0.04 0.04 0.03 Source: Bloomberg and Company Reports, Equity Research and Thomson Financial at May 30, 2012. Note: NAV per share figures are based on equity research consensus; Share data on fully diluted in the money shares outstanding. . © 2011 Detour Gold All Rights Reserved. 12
  • 13. Total Cash Costs Since 2010 (release of Feasibility Study), $ 800 $ 796 inflationary pressure seen in operating costs $ 706 $ 706 Approx. % of total cash cost/oz in FS1 $ 700 Maintenance Consumables $ 600 24% 25% $ 500 Royalty 4% 7% 14% Labour G&A Junior Senior Intermediate Producers Producers Producers 13% 13% Diesel 2012E Cash Cost Profile (US$/oz)* Power *Source: BMO Equity Research Seniors Producers include: Agnico-Eagle, AngloGold Ashanti, Barrick, Gold Fields, Goldcorp, Kinross, Newcrest, Newmont, Polyus and Yamana. Intermediate Producers include: African Barrick, Alacer, AuRico, Centamin Egypt, Centerra, Eldorado, Harmony, IAMGold, New Gold, Osisko, Petropavlovsk, Randgold and SEMAFO. Junior Producers include: Alamos Gold, Aurizon, Avion, Avocet, CGA Mining, Cluff Gold, Dundee Precious Metals, Golden Star, Great Basin Gold, Kingsgate, Lake Shore, OceanaGold, Perseus, Primero, Resolute, San Gold and Teranga. 1. Total estimated cash cost of US$543/oz based on March 2011 TR using cost parameters from feasibility study, including US$850/oz gold price and US$80/barrel oil. © 2011 Detour Gold All Rights Reserved. 13
  • 14. Mine Site Construction Progressing on Schedule © 2011 Detour Gold All Rights Reserved. 14
  • 15. Detour Lake: We are on Schedule 2010 2011 2012 2013 Construction Schedule Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Award of Engineering Contract Award of PCM Contract Detailed Engineering Construction camp (1,200 people) Power line (Phase 1&2) – Electrification 1 2 Equipment purchase/delivery & assembly Pre-stripping Process plant – Commissioning start-up Tailings dam construction (first cell) Provincial Permits/Aboriginal IBAs Federal Permits Start production and ramp-up GOLD PRODUCTION PROJECTED IN 1Q 2013 © 2011 Detour Gold All Rights Reserved. 15
  • 16. Detour Lake: We are on Budget Capital Expenditures (C$ M) Spent Committed Project Control Description May 31, May 31, Estimate 2012 2012 (as of 11/2011) Mining Fleet and Facilities 117 170 203 Crushing and Processing (P&E) 390 586 565 Tailings and Water Mgmt 15 45 65 Infrastructure and Power line 133 148 156 Other Indirect 158 202 310 EPCM 80 100 101 Contingency (10%) - 1 50 Total (pre-production) 893 1,252 1,450 PROJECT CONSTRUCTION 70% COMPLETE © 2011 Detour Gold All Rights Reserved. 16
  • 17. 2012 Operational Readiness Plan Ore ready to be processed by the fourth quarter of 2012  Pre-production capital costs include $78 M for pre-strip activities  Up to 3 Mt of ore ready for process 2012 Pre-Stripping PROJECT CHANGE Feasibility PCE Status OF SCOPE Study (11/2011) (05/31/2012) = Overburden/Till 16 Mt 21 Mt 5.50 Mt Waste - 10 Mt 1.82 Mt A BENEFIT Ore 3 Mt - Ore available for Estimated Cost C$30 M C$78 M - processing in 2012 © 2011 Detour Gold All Rights Reserved. 17
  • 18. Mining is Ramping Up © 2011 Detour Gold All Rights Reserved. 18
  • 19. Mining is Ramping Up © 2011 Detour Gold All Rights Reserved. 19
  • 20. Initial Mining Fleet at Site  10 CAT 795F trucks at site (2 supplied by CAT); Loading Units 4 more being assembled 3 X Hydraulic CAT6060 (25 m3)  2 CAT6060 shovels in operation 2 X Electric cable shovels (48 m3) Haulers 23 X CAT 795F trucks (320 t); 30-35 at peak of operation © 2011 Detour Gold All Rights Reserved. 20
  • 21. Detour Lake Development Progress  Detailed engineering, procurement of major equipment and awarding of major contracts complete  Second 45 km segment of powerline complete Detour Lake  Pre-stripping program ongoing 45 45 km km Powerline Powerline Gravel (34 km)  Installation of mill equipment underway Paved road (151 km)  Truck wash facilities complete  Permanent camp construction completed © 2011 Detour Gold All Rights Reserved. 21
  • 22. Detour Lake Mining Facilities © 2011 Detour Gold All Rights Reserved. Note: Open pit reserves using US$850/oz gold 22 22
  • 23. Overview Detour Lake Facilities Processing Plant Truck Wash Truck Shop & Warehouse Mine Offices 12-06-08 © 2011 Detour Gold All Rights Reserved. 23
  • 24. Overview Detour Lake Facilities Stockpile Reclaim Secondary Crushers Primary Crusher 12-06-08 © 2011 Detour Gold All Rights Reserved. 24
  • 25. Primary Crusher (up to 100,000 tpd capacity) Here now 12-06-08 Surface Gyro is 9 m high 35 m © 2011 Detour Gold All Rights Reserved. 25
  • 26. Stockpile Reclaim Cover Stockpile Reclaim 12-06-08 Secondary and Pebble Crushers 12-06-08 © 2011 Detour Gold All Rights Reserved. 26
  • 27. Processing Plant Building Ball Mills SAG Mills 12-06-08 © 2011 Detour Gold All Rights Reserved. 27
  • 28. Processing Plant Building CIP Tanks Pumps 12-06-08 Hydrocyclones © 2011 Detour Gold All Rights Reserved. 28
  • 29. Simple Process Plant  Conventional gravity and CIP plant  55,000 tpd (=92% availability of 60,000 tpd capacity)  2 parallel lines (each with 1 secondary cone crusher + 1 SAG and 1 ball mill) A  Estimated gravity recovery: 30-40%  Estimated overall gold recovery: 91.0% A  Leach time 29 hours  Leach feed size 80% passing 95 μm © 2011 Detour Gold All Rights Reserved. 29
  • 30. Detour Lake Employees & Contractors Construction Phase Operation Phase (Starting 2013)  >1,500 workers (currently)  400-500 employees  Ramping up DGC team (273)  Rotation 1 week in /out  New modern camp facilities with 400 en-suite rooms completed © 2011 Detour Gold All Rights Reserved. 30
  • 31. Focus: Hiring Local First 273 DETOUR GOLD EMPLOYEES (May 30, 2012) Require a complement of +400 employees by production start in early 2013 25% Workforce Origin Professional 4% 2% Front Line Cochrane 75% Cochrane Area 28% Northern Ontario 44%  Professional are: MGMT, Eng., Geo., Supt. 22% Rest of Ontario  Front Line are: Operators, Admin, Support  28% Reside in Cochrane Other  Continuing focus on hiring local/regional *25% of employees are Aboriginals © 2011 Detour Gold All Rights Reserved. 31
  • 32. Planning for Organic Growth Under-explored Greenstone Belt © 2011 Detour Gold All Rights Reserved. 32
  • 33. Planning for Organic Growth 5 yr plan for successful organic growth Large prospective land position of approx. 540 km2  Land position increased with acquisition of Trade Winds properties  Two main gold structures with total strike length of >80 km  Continue focus on Detour Lake deposit extension (northern structure)  Test targets on structure south of Detour Lake Future Objectives  Grow reserve base to +20 M oz (@ US$850/oz)  Increase mill throughput to above 75,000 tpd for gold production output of +800,000 oz/yr  Find high-grade ore near-surface within trucking distance to supplement mill © 2011 Detour Gold All Rights Reserved. 33
  • 34. 2012 Plan for Successful Organic Growth Priority #1 on Block A  Area between Block A open pit resource (M-Zone) and the underground QK Zone discovered by Placer in mid-90’s  Drilling program of 50,000 m in 1H 2012  Start pre-feasibility study for small open pit (Block A resource)  Advance exploration of QK underground zone Priority #2 on Lower Detour Deformation Zone (+40 km)  5,060 m of diamond drilling completed: N-S drill fence on high-grade drill hole intercepts (53 g/t Au / 3 m & 22.6 g/t Au / 1 m)  115 km of IP geophysical survey completed  Geological and structural mapping; data compilation © 2011 Detour Gold All Rights Reserved. 34
  • 35. Planning for Organic Growth 2012 target  Deposit open to the west and at depth  +50,000 m of drilling for 2012 (Block A open pit above QK Zone) *Not updated with TWD Dec. 30th PR. On Dec. 1, 2011, Detour Gold announced the acquisition of TWD. © 2011 Detour Gold All Rights Reserved. 35
  • 36. Priority # 1 - Block A Target Block A near-surface resource 2012 proposed DH 2012 extension DH Detour Lake DH included in 2011 year-end reserves 2011 year-end reserves = 15.6 M oz DH not included in 2011 year-end reserves Historical DH © 2011 Detour Gold All Rights Reserved. 36
  • 37. Priority # 1 - Block A Target Block A 2012 Drilling Program June 10, 2012 2012 proposed DH 2012 extension DH 2011 year-end reserves 2012 completed DH Historical DH = 15.6 M oz Cancelled or not accessible © 2011 Detour Gold All Rights Reserved. 37
  • 38. Planning for Organic Growth +80 km of favourable geology Sunday Lake Option 15.6 M oz in Reserves Existing DDH Insert- see next slide Gold occurrence (OGS) DDH intersection >1g/2m DDH intersection >1g/10m MMI Survey Coverage MMI Au Anomaly *Note: Excludes drilling around Detour Lake and M zone (Block A). © 2011 Detour Gold All Rights Reserved. 38
  • 39. Planning for Organic Growth Completed drilling © 2011 Detour Gold All Rights Reserved. 39
  • 40. Planning for Organic Growth ? ? © 2011 Detour Gold All Rights Reserved. 40
  • 41. Evaluating Expansion Opportunities  Best scenario is throughput 2012 increase from 55,000 to 75,000 tpd @ US$1,200/oz  Start pre-feasibility on Block A  Complete feasibility study and 2013 assess technical feasibility and resultant project economics  At >US$1,000/oz and after 2014 successful commercial production is achieved, proceed with plant expansion  Complete expansion within 2 years © 2011 Detour Gold All Rights Reserved. 41
  • 42. Invest in Detour Gold  Focus on a world-class asset – Detour Lake  Canada’s largest pure gold play with 15.6 M oz in reserves (@ US$ 850/oz gold price)  Construction progressing on schedule (70% as of May 31)  One of the best cash flow/share opportunities  Gold production starting in Q1 2013  Excellent organic growth potential (5 year plan)  Potential expansion of mill throughput © 2011 Detour Gold All Rights Reserved. 42
  • 43. Additional Information © 2011 Detour Gold All Rights Reserved. 43
  • 44. Detour Lake – Surface Plan DH included in the 2011 year-end reserves DH not included in the 2011 year-end reserves Pre 2007 DH 2011 Year-end reserves = 15.6 M oz © 2011 Detour Gold All Rights Reserved. 44
  • 45. Detour Lake – Long Section Looking 20,070 N QK Zone DH included in the 2011 year-end reserves DH not included in the 2011 year-end reserves Pre 2007 DH © 2011 Detour Gold All Rights Reserved. 45
  • 46. Block Model - Gold Distribution Approx. 3 M oz. between 0.3-0.5 g/t Au 1,600 OK (oz Au) ID3 (oz Au) 1,400 1,200 1,000 Ounces (000’s) 800 600 400 200 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2.0 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 3.0 Cut-off BINs © 2011 Detour Gold All Rights Reserved. 46
  • 47. Management & Directors Management  Gerald Panneton, Founder, President &  Derek Teevan, VP Aboriginal & Government CEO, Director Affairs  Michael Kenyon, Chairman  Eric Josipovic, Controller  Paul Martin, CFO  Drew Anwyll, Director of Operations  Pierre Beaudoin, Sr. VP Capital Projects  Andrew Croal, Dir. Technical Services  Pat Donovan, VP Corporate Development  Laurie Gaborit, Dir. Investor Relations  Julie Galloway, VP General Counsel &  Greg Miazga, Dir. Construction & Corporate Secretary Engineering  James Mavor, VP Finance  Bill Snelling, Director Corporate Systems  Rachel Pineault, VP HR & Northern and Controls Affairs  Christian Brousseau, Project Manager  James Robertson, VP Environment &  Patrik Gillerstedt, Mine Manager Sustainability Directors Peter Crossgrove Ingrid Hibbard Gerald Panneton Louis Dionne Michael Kenyon Jonathan Rubenstein Robert E. Doyle Alex G. Morrison Graham Wozniak © 2011 Detour Gold All Rights Reserved. 47
  • 48. Contact Information Gerald Panneton, President & CEO Email: gpanneton@detourgold.com Ph: 416 304 0800 Laurie Gaborit, Director Investor Relations Email: lgaborit@detourgold.com Ph: 416 304 0800 www.detourgold.com © 2011 Detour Gold All Rights Reserved. 48