Kaizen Event : UC Squib Productivity Improvement and
Reduction in Rejection.
Team Leader:Deepak(ME).
Team members: Kiran (Prod), Rajesh (ME), Prasad (Tool Main), Paramesh (Prod)
Date : 18th
March 2010
page
Information is Tyco Electronics Confidential & Proprietary
Do Not Reproduce or Distribute
Base line
Metric Baseline Target Improvement
Cycle Time 54 sec 40 sec 26%
Rejection
percentage
12% 4% 67%
Mold down time 6.3 hrs/month 1 hr/month 84%
page
Information is Tyco Electronics Confidential & Proprietary
Do Not Reproduce or Distribute
PRODUCT OVER VIEW
UC squib is used in air bag application. It is used for secure connection of the
airbag ignitor via the cable harness to the airbag control box.
We produce around 39 pn according to different lengths and cables.
Customer:-
Autoliv,Takata,Filec.
page
Information is Tyco Electronics Confidential & Proprietary
Do Not Reproduce or Distribute
Why this project?
• Increase in customer demand.
• The daily machine capacity was 7500nos
• Customer escalation regarding delivery
• High scrap percentage.
page
Information is Tyco Electronics Confidential & Proprietary
Do Not Reproduce or Distribute
Pareto Analysis
Rejection
reasons Qty Percentage
Material
entry 13636 39.81
Flash on
cable 4735 13.82
Rough finish 3970 11.59
Flash on
contact 3642 10.63
Incoming
problem 2969 8.67
Short shot 2584 7.54
Contaminati
on 1343 3.92
Contact
visible 726 2.12
Contact
height
variation 352 1.03
Cable
damage 296 0.86
Paretoforrejectionqty
39.81
53.63
65.22
75.86
84.52
92.07
95.99 98.11 99.14 100.00
0
2000
4000
6000
8000
10000
12000
14000
16000
Materialentry Flashoncable Roughfinish Flashoncontact Incoming
problem
Shortshot Contamination Contactvisible Contactheight
variation
Cabledamge
Reasons
Qty
0.00
20.00
40.00
60.00
80.00
100.00
120.00
page
Information is Tyco Electronics Confidential & Proprietary
Do Not Reproduce or Distribute
Action Plan
Major Problem Causes Corrective action proposed
Material entry Gap between ferrite and contact.
Narrow process window .
Delay in cycles.
Optimizing the cycle time.
By increasing mold open/Close speed,
By increasing nozzle advance/retraction speed.
Rotary table speed.
Adding one more operator station for part removal.
Flash on cable Improper placement.
Narrow process window.
Imbalance in filling.
Training to operators .
Optimizing the cycle time.
page
Information is Tyco Electronics Confidential & Proprietary
Do Not Reproduce or Distribute
Action Plan
Major Problem Causes Corrective action proposed
Rough finish
Drooling
Delay in cycle
Narrow process window.
Imbalance in filling.
Optimizing the cycle time
Flash on contact Delay in cycle
Narrow process window.
Imbalance in filling.
Optimizing the cycle time
page
Information is Tyco Electronics Confidential & Proprietary
Do Not Reproduce or Distribute
Action plan
Burn
mark
No air
vents
Air vents
provided
Before After Before After
Cable insertion
Nozzle Retraction speed (%):-25
Nozzle retract stroke(mm):260
Delay time (sec):-15
Nozzle retraction
Nozzle Retraction speed (%):-
40
Nozzle retract stoke(mm):223
Delay time (sec):-2
Speed(%):-35
Rotary table
movement
Speed(%):-50 Opening speed(%):15/40/20 Mold opening Opening speed(%):15/40/20
Closing
speed(%):15/20/15
Mold closing
Closing
speed(%):35/45/1
5
Speed(%):-35
Rotary table
movement
Speed(%):-50
Nozzle advance speed
(%):-50/15
Nozzle advance
Nozzle advance
speed (%):-50/15
Cable removal
Injection
page
Information is Tyco Electronics Confidential & Proprietary
Do Not Reproduce or Distribute
Action Plan
• One more stage for manpower added for part removal and insertion
instead of one person doing it.
• Training for all UC Squib operators as per WI.
Before After
page
Information is Tyco Electronics Confidential & Proprietary
Do Not Reproduce or Distribute
Benefits
• Productivity Improvement.
• Efficiency improvement
Daily output
9065
12545
0
2000
4000
6000
8000
10000
12000
14000
Before After
Qty
Efficiency
155
110
127
138
0
20
40
60
80
100
120
140
160
180
November December January Febraury
Month
Eff
page
Information is Tyco Electronics Confidential & Proprietary
Do Not Reproduce or Distribute
Benifits
Rej PPM
9 0 3 3 2
3 8 2 55
3 4 571
4 2 72 1
0
10000
20000
30000
40000
50000
60000
70000
80000
90000
100000
November December January FebruaryMonth
PPM
• Reduction in rejection.
• Mold down time reduced from 6.3 hrs to 1 hr.
page
Information is Tyco Electronics Confidential & Proprietary
Do Not Reproduce or Distribute
Benefits and Next Action Plan
Savings ($) December January February
3547 4038 4446
Next Action Plans
• Replacing the injection unit with nozzle shut of unit.
• Working on Visual inspection stages .
page
Information is Tyco Electronics Confidential & Proprietary
Do Not Reproduce or Distribute
Thank you

More Related Content

Viewers also liked

Meeting the Needs of Disadvantaged Students by Ikhlas Ahmad
Meeting the Needs of Disadvantaged Students by Ikhlas AhmadMeeting the Needs of Disadvantaged Students by Ikhlas Ahmad
Meeting the Needs of Disadvantaged Students by Ikhlas AhmadIkhlas Ahmad
 
Evaluación modulo final
Evaluación modulo finalEvaluación modulo final
Evaluación modulo finalM. Ugas
 
Confissão de fé de Westminster - PRST
Confissão de fé de Westminster - PRSTConfissão de fé de Westminster - PRST
Confissão de fé de Westminster - PRSTPresbitério de Santos
 
Importancia acerca del uso correcto de la computadora
Importancia acerca del uso correcto de la computadoraImportancia acerca del uso correcto de la computadora
Importancia acerca del uso correcto de la computadoracamilo leyton
 
Strength Finder Results
Strength Finder ResultsStrength Finder Results
Strength Finder ResultsDavid Martin
 
MANUAL DE PROCEDIMIENTO
MANUAL DE PROCEDIMIENTO MANUAL DE PROCEDIMIENTO
MANUAL DE PROCEDIMIENTO macorovi
 
REGLAMENTO INTERNO DE TRABAJO
REGLAMENTO INTERNO DE TRABAJO REGLAMENTO INTERNO DE TRABAJO
REGLAMENTO INTERNO DE TRABAJO macorovi
 

Viewers also liked (17)

Final Gyanesh Profile
Final Gyanesh ProfileFinal Gyanesh Profile
Final Gyanesh Profile
 
Paulo Afonso - Business Model Canvas
Paulo Afonso - Business Model CanvasPaulo Afonso - Business Model Canvas
Paulo Afonso - Business Model Canvas
 
Meeting the Needs of Disadvantaged Students by Ikhlas Ahmad
Meeting the Needs of Disadvantaged Students by Ikhlas AhmadMeeting the Needs of Disadvantaged Students by Ikhlas Ahmad
Meeting the Needs of Disadvantaged Students by Ikhlas Ahmad
 
Inversiones básicas
Inversiones básicasInversiones básicas
Inversiones básicas
 
Cuidadosdelagua
CuidadosdelaguaCuidadosdelagua
Cuidadosdelagua
 
santosh _ Resume (1)
santosh _ Resume (1)santosh _ Resume (1)
santosh _ Resume (1)
 
Evaluación modulo final
Evaluación modulo finalEvaluación modulo final
Evaluación modulo final
 
Redes sociales
Redes socialesRedes sociales
Redes sociales
 
Confissão de fé de Westminster - PRST
Confissão de fé de Westminster - PRSTConfissão de fé de Westminster - PRST
Confissão de fé de Westminster - PRST
 
Importancia acerca del uso correcto de la computadora
Importancia acerca del uso correcto de la computadoraImportancia acerca del uso correcto de la computadora
Importancia acerca del uso correcto de la computadora
 
Strength Finder Results
Strength Finder ResultsStrength Finder Results
Strength Finder Results
 
MANUAL DE PROCEDIMIENTO
MANUAL DE PROCEDIMIENTO MANUAL DE PROCEDIMIENTO
MANUAL DE PROCEDIMIENTO
 
Trabajo de tecnica
Trabajo de tecnicaTrabajo de tecnica
Trabajo de tecnica
 
Ttip.pptx
Ttip.pptxTtip.pptx
Ttip.pptx
 
Cómo planificar un viaje
Cómo planificar un viajeCómo planificar un viaje
Cómo planificar un viaje
 
REGLAMENTO INTERNO DE TRABAJO
REGLAMENTO INTERNO DE TRABAJO REGLAMENTO INTERNO DE TRABAJO
REGLAMENTO INTERNO DE TRABAJO
 
River Rafting Rishikesh
River Rafting RishikeshRiver Rafting Rishikesh
River Rafting Rishikesh
 

Similar to Kaizen uc squib

Maximizing Machine Productivity - Your Trending Need (By: Nitin Chowdhary)
Maximizing Machine Productivity - Your Trending Need (By: Nitin Chowdhary)Maximizing Machine Productivity - Your Trending Need (By: Nitin Chowdhary)
Maximizing Machine Productivity - Your Trending Need (By: Nitin Chowdhary)Nitin9618
 
Physics of Failure Electronics Reliability Assurance Software
Physics of Failure Electronics Reliability Assurance SoftwarePhysics of Failure Electronics Reliability Assurance Software
Physics of Failure Electronics Reliability Assurance SoftwareCheryl Tulkoff
 
Eia 364-38 c final
Eia 364-38 c finalEia 364-38 c final
Eia 364-38 c finalgaryftp
 
_ Mini Catalogs by app
_ Mini Catalogs by app_ Mini Catalogs by app
_ Mini Catalogs by appVincent Fetzer
 
geaazrhszegsr wrrathet eTETR Etrsfe deaFddaewe te3thr esesSEeee
geaazrhszegsr wrrathet eTETR Etrsfe deaFddaewe te3thr esesSEeeegeaazrhszegsr wrrathet eTETR Etrsfe deaFddaewe te3thr esesSEeee
geaazrhszegsr wrrathet eTETR Etrsfe deaFddaewe te3thr esesSEeeemariogultom6
 
Greenbelt Six Sigma Final Outline
Greenbelt Six Sigma Final OutlineGreenbelt Six Sigma Final Outline
Greenbelt Six Sigma Final Outlineguest098cf2fe
 
GE Digital Predix. Mario Testino, General Electrics
GE Digital Predix. Mario Testino, General ElectricsGE Digital Predix. Mario Testino, General Electrics
GE Digital Predix. Mario Testino, General ElectricsData Driven Innovation
 
Functional safety by FMEA/FTA
Functional safety by FMEA/FTAFunctional safety by FMEA/FTA
Functional safety by FMEA/FTAmehmor
 
The economics of reducing the cost of energy by 13% revenues
The economics of reducing the cost of energy by 13% revenuesThe economics of reducing the cost of energy by 13% revenues
The economics of reducing the cost of energy by 13% revenuesSentient Science
 
IRJET - Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
IRJET -  	  Invistigation and Implement of Six Sigma and Reduce Labour Cost a...IRJET -  	  Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
IRJET - Invistigation and Implement of Six Sigma and Reduce Labour Cost a...IRJET Journal
 
OEE - One Metric to Rule them All
OEE - One Metric to Rule them AllOEE - One Metric to Rule them All
OEE - One Metric to Rule them AllVibra
 
IRJET- Automated Machine Design through Software Controller Support
IRJET- Automated Machine Design through Software Controller SupportIRJET- Automated Machine Design through Software Controller Support
IRJET- Automated Machine Design through Software Controller SupportIRJET Journal
 
Selection and Economics for Test Fixtures and Test Interconnect
Selection and Economics for Test Fixtures and Test InterconnectSelection and Economics for Test Fixtures and Test Interconnect
Selection and Economics for Test Fixtures and Test InterconnectGreg Crouch
 
IRJET-Numerical Analysis of Extruder Screw & Controlling the Diameter of Plas...
IRJET-Numerical Analysis of Extruder Screw & Controlling the Diameter of Plas...IRJET-Numerical Analysis of Extruder Screw & Controlling the Diameter of Plas...
IRJET-Numerical Analysis of Extruder Screw & Controlling the Diameter of Plas...IRJET Journal
 
UTC Telecom & Technology 2015 - Battery Backup Workshop
UTC Telecom & Technology 2015 - Battery Backup WorkshopUTC Telecom & Technology 2015 - Battery Backup Workshop
UTC Telecom & Technology 2015 - Battery Backup WorkshopDakx Turcotte
 
Embedding Passive and Active Devices in Substrates
Embedding Passive and Active Devices in SubstratesEmbedding Passive and Active Devices in Substrates
Embedding Passive and Active Devices in SubstratesMichael Tschandl
 

Similar to Kaizen uc squib (20)

Maximizing Machine Productivity - Your Trending Need (By: Nitin Chowdhary)
Maximizing Machine Productivity - Your Trending Need (By: Nitin Chowdhary)Maximizing Machine Productivity - Your Trending Need (By: Nitin Chowdhary)
Maximizing Machine Productivity - Your Trending Need (By: Nitin Chowdhary)
 
Physics of Failure Electronics Reliability Assurance Software
Physics of Failure Electronics Reliability Assurance SoftwarePhysics of Failure Electronics Reliability Assurance Software
Physics of Failure Electronics Reliability Assurance Software
 
Eia 364-38 c final
Eia 364-38 c finalEia 364-38 c final
Eia 364-38 c final
 
Company Presentation.pptx
Company Presentation.pptxCompany Presentation.pptx
Company Presentation.pptx
 
_ Mini Catalogs by app
_ Mini Catalogs by app_ Mini Catalogs by app
_ Mini Catalogs by app
 
geaazrhszegsr wrrathet eTETR Etrsfe deaFddaewe te3thr esesSEeee
geaazrhszegsr wrrathet eTETR Etrsfe deaFddaewe te3thr esesSEeeegeaazrhszegsr wrrathet eTETR Etrsfe deaFddaewe te3thr esesSEeee
geaazrhszegsr wrrathet eTETR Etrsfe deaFddaewe te3thr esesSEeee
 
Six Sigma Final Outline
Six Sigma Final OutlineSix Sigma Final Outline
Six Sigma Final Outline
 
Greenbelt Six Sigma Final Outline
Greenbelt Six Sigma Final OutlineGreenbelt Six Sigma Final Outline
Greenbelt Six Sigma Final Outline
 
GE Digital Predix. Mario Testino, General Electrics
GE Digital Predix. Mario Testino, General ElectricsGE Digital Predix. Mario Testino, General Electrics
GE Digital Predix. Mario Testino, General Electrics
 
Functional safety by FMEA/FTA
Functional safety by FMEA/FTAFunctional safety by FMEA/FTA
Functional safety by FMEA/FTA
 
The economics of reducing the cost of energy by 13% revenues
The economics of reducing the cost of energy by 13% revenuesThe economics of reducing the cost of energy by 13% revenues
The economics of reducing the cost of energy by 13% revenues
 
Sandia 2014 Wind Turbine Blade Workshop- Nolet
Sandia 2014 Wind Turbine Blade Workshop- NoletSandia 2014 Wind Turbine Blade Workshop- Nolet
Sandia 2014 Wind Turbine Blade Workshop- Nolet
 
IRJET - Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
IRJET -  	  Invistigation and Implement of Six Sigma and Reduce Labour Cost a...IRJET -  	  Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
IRJET - Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
 
OEE - One Metric to Rule them All
OEE - One Metric to Rule them AllOEE - One Metric to Rule them All
OEE - One Metric to Rule them All
 
IRJET- Automated Machine Design through Software Controller Support
IRJET- Automated Machine Design through Software Controller SupportIRJET- Automated Machine Design through Software Controller Support
IRJET- Automated Machine Design through Software Controller Support
 
Selection and Economics for Test Fixtures and Test Interconnect
Selection and Economics for Test Fixtures and Test InterconnectSelection and Economics for Test Fixtures and Test Interconnect
Selection and Economics for Test Fixtures and Test Interconnect
 
IRJET-Numerical Analysis of Extruder Screw & Controlling the Diameter of Plas...
IRJET-Numerical Analysis of Extruder Screw & Controlling the Diameter of Plas...IRJET-Numerical Analysis of Extruder Screw & Controlling the Diameter of Plas...
IRJET-Numerical Analysis of Extruder Screw & Controlling the Diameter of Plas...
 
160kV 35um spot
160kV 35um spot160kV 35um spot
160kV 35um spot
 
UTC Telecom & Technology 2015 - Battery Backup Workshop
UTC Telecom & Technology 2015 - Battery Backup WorkshopUTC Telecom & Technology 2015 - Battery Backup Workshop
UTC Telecom & Technology 2015 - Battery Backup Workshop
 
Embedding Passive and Active Devices in Substrates
Embedding Passive and Active Devices in SubstratesEmbedding Passive and Active Devices in Substrates
Embedding Passive and Active Devices in Substrates
 

Kaizen uc squib

  • 1. Information is Tyco Electronics Confidential & Proprietary Do Not Reproduce or Distribute Kaizen Event : UC Squib Productivity Improvement and Reduction in Rejection. Team Leader:Deepak(ME). Team members: Kiran (Prod), Rajesh (ME), Prasad (Tool Main), Paramesh (Prod) Date : 18th March 2010
  • 2. page Information is Tyco Electronics Confidential & Proprietary Do Not Reproduce or Distribute Base line Metric Baseline Target Improvement Cycle Time 54 sec 40 sec 26% Rejection percentage 12% 4% 67% Mold down time 6.3 hrs/month 1 hr/month 84%
  • 3. page Information is Tyco Electronics Confidential & Proprietary Do Not Reproduce or Distribute PRODUCT OVER VIEW UC squib is used in air bag application. It is used for secure connection of the airbag ignitor via the cable harness to the airbag control box. We produce around 39 pn according to different lengths and cables. Customer:- Autoliv,Takata,Filec.
  • 4. page Information is Tyco Electronics Confidential & Proprietary Do Not Reproduce or Distribute Why this project? • Increase in customer demand. • The daily machine capacity was 7500nos • Customer escalation regarding delivery • High scrap percentage.
  • 5. page Information is Tyco Electronics Confidential & Proprietary Do Not Reproduce or Distribute Pareto Analysis Rejection reasons Qty Percentage Material entry 13636 39.81 Flash on cable 4735 13.82 Rough finish 3970 11.59 Flash on contact 3642 10.63 Incoming problem 2969 8.67 Short shot 2584 7.54 Contaminati on 1343 3.92 Contact visible 726 2.12 Contact height variation 352 1.03 Cable damage 296 0.86 Paretoforrejectionqty 39.81 53.63 65.22 75.86 84.52 92.07 95.99 98.11 99.14 100.00 0 2000 4000 6000 8000 10000 12000 14000 16000 Materialentry Flashoncable Roughfinish Flashoncontact Incoming problem Shortshot Contamination Contactvisible Contactheight variation Cabledamge Reasons Qty 0.00 20.00 40.00 60.00 80.00 100.00 120.00
  • 6. page Information is Tyco Electronics Confidential & Proprietary Do Not Reproduce or Distribute Action Plan Major Problem Causes Corrective action proposed Material entry Gap between ferrite and contact. Narrow process window . Delay in cycles. Optimizing the cycle time. By increasing mold open/Close speed, By increasing nozzle advance/retraction speed. Rotary table speed. Adding one more operator station for part removal. Flash on cable Improper placement. Narrow process window. Imbalance in filling. Training to operators . Optimizing the cycle time.
  • 7. page Information is Tyco Electronics Confidential & Proprietary Do Not Reproduce or Distribute Action Plan Major Problem Causes Corrective action proposed Rough finish Drooling Delay in cycle Narrow process window. Imbalance in filling. Optimizing the cycle time Flash on contact Delay in cycle Narrow process window. Imbalance in filling. Optimizing the cycle time
  • 8. page Information is Tyco Electronics Confidential & Proprietary Do Not Reproduce or Distribute Action plan Burn mark No air vents Air vents provided Before After Before After Cable insertion Nozzle Retraction speed (%):-25 Nozzle retract stroke(mm):260 Delay time (sec):-15 Nozzle retraction Nozzle Retraction speed (%):- 40 Nozzle retract stoke(mm):223 Delay time (sec):-2 Speed(%):-35 Rotary table movement Speed(%):-50 Opening speed(%):15/40/20 Mold opening Opening speed(%):15/40/20 Closing speed(%):15/20/15 Mold closing Closing speed(%):35/45/1 5 Speed(%):-35 Rotary table movement Speed(%):-50 Nozzle advance speed (%):-50/15 Nozzle advance Nozzle advance speed (%):-50/15 Cable removal Injection
  • 9. page Information is Tyco Electronics Confidential & Proprietary Do Not Reproduce or Distribute Action Plan • One more stage for manpower added for part removal and insertion instead of one person doing it. • Training for all UC Squib operators as per WI. Before After
  • 10. page Information is Tyco Electronics Confidential & Proprietary Do Not Reproduce or Distribute Benefits • Productivity Improvement. • Efficiency improvement Daily output 9065 12545 0 2000 4000 6000 8000 10000 12000 14000 Before After Qty Efficiency 155 110 127 138 0 20 40 60 80 100 120 140 160 180 November December January Febraury Month Eff
  • 11. page Information is Tyco Electronics Confidential & Proprietary Do Not Reproduce or Distribute Benifits Rej PPM 9 0 3 3 2 3 8 2 55 3 4 571 4 2 72 1 0 10000 20000 30000 40000 50000 60000 70000 80000 90000 100000 November December January FebruaryMonth PPM • Reduction in rejection. • Mold down time reduced from 6.3 hrs to 1 hr.
  • 12. page Information is Tyco Electronics Confidential & Proprietary Do Not Reproduce or Distribute Benefits and Next Action Plan Savings ($) December January February 3547 4038 4446 Next Action Plans • Replacing the injection unit with nozzle shut of unit. • Working on Visual inspection stages .
  • 13. page Information is Tyco Electronics Confidential & Proprietary Do Not Reproduce or Distribute Thank you

Editor's Notes

  1. <number>
  2. <number>
  3. <number>