This document provides information on upcoming tunnel construction works for the Eglinton Crosstown LRT project in Toronto, including the construction of jet grout headwalls at Chaplin station. Key details include:
- Jet grout headwalls will be installed at Chaplin station to support future excavation of the station box using a temporary grout plant located on Gilgorm Avenue over 8-10 months.
- Tunnel boring machine 1 has passed through the west headwall at Keele Street, and tunnel boring machine 2 is following closely behind.
- The grout plant and headwall construction will impact traffic flow on Chaplin Avenue and temporarily close lanes.
Chaplin Grout Plant and Headwall Construction Spring 2014
1. Chaplin Grout Plant and
Headwall Construction
Spring 2014
Councillor Stintz Briefing
February 3, 2014
Jamie Robinson
Director, Communications and Community Relations
Toronto Expansion Projects, Metrolinx
1
2. Eglinton Crosstown LRT
Project
$4.9 B (2010$), funded by the Province of Ontario
19 kilometres east-west LRT from Kennedy to
Jane/Black Creek, including 10 kilometers of tunnel
Connections to Yonge-University-Spadina Subway,
Scarborough RT and GO Stouffville
Up to 26 stations
2
4. Tunnelling Update
TBM 1 is well underway with tunnelling; just recently bored
through our west headwall at Keele St.
TBM 2, a twin machine, has been assembled and is
following closely behind
4
8. Tunnel Drive Sequence
After Tunnel Contract:
• Install Station
Sidewall and
Headwall Support of
Excavation
• Excavate Station and
Commence
Removing Concrete
Tunnel Liners
Finally:
• Station Box Fully
Excavated & Tunnel
Lining Removed (Not
shown)
8
11. Tunnel Drive Works Current Status
In 2013 the majority of tunnel works took place between
Black Creek Drive and the vicinity of Allen Road
In 2014 work continues east of Allen Road
Crews are starting the construction of headwalls and utility
relocation at future station sites along Eglinton Avenue
West
11
12. Tunnel Drive Works
Headwalls: Temporary support walls for future excavation
of the LRT stations.
Made of concrete and installed to the depth of the future
track level
Two methods of installation used: Secant Pile Walls, Jet
Grout
Machinery including drill rigs, grout tanks, diggers and other
equipment
12
13. Tunnel Drive Works
Secant pile wall : formed by
intersecting concrete piles
13
Jet grout wall : uses engineered
grout to form wall in situ
16. Grout Plant for Headwall Construction
Why a grout plant at Chaplin?
Headwalls for Chaplin required
Gilgorm adjacent to work site
Gilgorm to remain open one lane northbound
Allows efficient use of space
Other options examined included Vesta Drive and Eglinton
Gilgorm preferred because of:
reduced property impact
reduced footprint on Eglinton Ave.
16
17. Grout Plant at Chaplin
The site will be situated on Metrolinxowned property and occupy City of
Toronto roadway
A fence will enclose the site to
demarcate the site from the public
roadway throughout the entire works
The plant will service headwall
construction for Chaplin Station and
cross-passages at Vesta Dr and
Castle Knock Road
The site is expected to be in place
for approximately 8-10 months
17
18. Grout Plant at Chaplin
Advantages of jet grout
technique for headwall
installation:
Reduce requirement for
extensive utility relocation
Overall construction time
savings
18
19. Timeline
With appropriate permissions in place Metrolinx’ contractor will:
Begin to set up the grout plant
Install fencing and secure the perimeter
Install grout lines in the roadway
Test works
Begin Chaplin headwall construction works
Chaplin headwall construction is currently scheduled to
commence in March 2014
8-10 months anticipated
Headwall works at Avenue Road and Bathurst are currently
being reviewed
19
20. Chaplin Work Staging- South Setup
Work is set up on the south side of Eglinton
The work zone is separated from the ROW with concrete
barriers and fencing
Unoccupied traffic lanes remain open on the north side of
Eglinton with one lane in each direction
Through-traffic southbound on Chaplin at Eglinton will not
be permitted
Southbound traffic must exit at Eglinton or choose an
alternate route
Expected duration: Approximately 4 months
20
21. Chaplin Work Staging- North Setup
A work site is set up on the north side of Eglinton
The work zone is separated from the ROW with concrete
barriers and fencing
Unoccupied traffic lanes remain open on the south side of
Eglinton with one lane in each direction
Through-traffic northbound on Chaplin at Eglinton will not
be permitted
Northbound traffic must exit at Eglinton or choose an
alternate route
Expected duration: Approximately 4 months
Latimer Avenue is closed to/from Eglinton during this phase
21
25. Next Steps
Community Relations will outreach to specific condos and
apartment buildings to raise awareness of the site and
planned works
Co-ordination with TTC will continue to ensure continued
bus service
Co-ordination with local Fire Station also continues to
ensure service levels
25