SlideShare uma empresa Scribd logo
1 de 5
Baixar para ler offline
Phased Array Ultrasonic Testing Vendor Qualifcation
for a major subsea project
(A risk mitigation strategy)
ABSTRACT
A significant fabrication risk was identified
on the Shah Deniz 2 subsea gas manifolds.
Heavy wall thickness welds needed to be
inspected and the limits of radiography
meant a PAUT vendor had to be qualified in
time for the fabrication of the pipework.
Colin Smith:
https://uk.linkedin.com/in/colinanthonysmith
A significant risk had to be addressed if the fabrication site was to avoid using radiography
on heavy wall welds on the high pressure (900bar) gas pipework. The obvious benefits were:
safety (elimination of radiography as the means to NDE the welds), quality – at the 62.5mm
wall thicknesses in the stainless steels it would be difficult to detect crack-like defects in the
root areas with the usual UT and RT methods, and finally productivity; being able to weld &
inspect at the same time in the same vicinity had significant productivity benefits.
There are many NDE contractors who claim that they can PAUT welds and they can if the
welds are ferrous. However, if the welds are nickel based alloys or a stainless steel, then this
significantly reduces the number of NDE contractors with the correct knowhow.
Nickel based alloys and stainless steels are ultrasonically more opaque than ferrous alloys
due to the attenuation of the sound beam. This demands greater energy from the probes
and programming to tailor the beam for the specific application.
An amplitude based PAUT program was initiated by the client – with a goal of qualifying two
PAUT vendors to achieve a competitive tendering situation prior to start of inspection of the
heavy wall pipework required on the Shah Deniz 2, gas production manifold pipework.
These two vendors would then be pre-qualified for the main subsea contractor to choose
for the fabrication phase in Norway. I led this initiative and delivered the successful
outcome.
Scanning a 10” joint – note the finish on the weld caps.
A sized based PAUT program was initially considered but this would have involved
significant engineering to accept non-Code compliant defects justified by FEA. So the
amplitude based approach was adopted and ASME allowable defects as the basis of
acceptance. No crack like indications are allowable in the Code.
The qualification program was commenced 18 months before pipework fabrication. Seeded
coupons were manufactured at two locations one in Europe and one in the USA. It became
evident that only one seeded coupon manufacturer could achieve the correct morphology
of the defects that needed to be seeded at the correct depths. Of particular interest was the
location in the root area of 1.5mm crack like indications. These were to simulate lack of
fusion in the root. However the coupon was peppered with various types of defects
throughout the weld thickness. The ultimate acceptance criteria was: zero crack like
indications were allowable. The two seeded coupons were made with four rings of contract
material: 25%Cr super duplex to itself with matching filler, and nickel alloy clad X65 welded
to 25%Cr super duplex with a high nickel filler. These seeded coupons took 12 weeks to
fabricate. Seeding was performed using the thickest sections to be used on site: 62.5mm wt
on the 10” pipework.
The seeded coupons were then shipped to the two preferred PAUT vendors facilities in turn
where the operator was tested using the PAUT vendors procedure. These trials were
witnessed by the client – care was taken to ensure that no collaboration between operators
took place. This served to qualify the operator and the vendors procedure. The output was a
map submitted to the client declaring where the PAUT operator found the defects and they
had to be characterized. This map was compared to the original map. Operator and vendor
either passed or failed the test.
After trialing five potential vendors only two were capable of detecting the crack like
defects in the root area. Some vendors could not detect many of the seeded defects in the
mid thickness of the 62.5mm joints. Final value of the CTR was in excess of $1.5MM.
In addition to the seeded coupons (and in parallel) the vendors had to be supplied with
contract material coupons of each size of pipework that was to be tested: in this case 6” x
47.5mm wt , the 10” x 62.5mm wt and the 12” x 38mm wt. Priority was given to the 10”
coupons for the seeding trials.
Phased array automatic ultrasonic testing on 10” super duplex joint 62.5mm wall thickness.
Duration from mobilization to demobilization 3 hrs – two scans (one from either side).

Mais conteúdo relacionado

Mais procurados

Cody Cunningham resume edited
Cody Cunningham resume editedCody Cunningham resume edited
Cody Cunningham resume edited
Cody Cunningham
 
KDV WT Brochure 100510
KDV WT Brochure 100510KDV WT Brochure 100510
KDV WT Brochure 100510
Ilan Almagor
 
cvkemp robert (Sept 16) (1) (1)
cvkemp robert (Sept 16) (1) (1)cvkemp robert (Sept 16) (1) (1)
cvkemp robert (Sept 16) (1) (1)
Robert Kemp
 
Analytical Science 5th Symposium Programme Registration Form (singlepages)
Analytical Science 5th Symposium Programme  Registration Form (singlepages)Analytical Science 5th Symposium Programme  Registration Form (singlepages)
Analytical Science 5th Symposium Programme Registration Form (singlepages)
?Graham Sithole?
 
IECS_Cable_Concrete_Brochure
IECS_Cable_Concrete_BrochureIECS_Cable_Concrete_Brochure
IECS_Cable_Concrete_Brochure
Nnamdi Eguh
 

Mais procurados (17)

Testing/Manufacture/Automobile, Paint & Plating Testing Equipments
Testing/Manufacture/Automobile, Paint & Plating Testing EquipmentsTesting/Manufacture/Automobile, Paint & Plating Testing Equipments
Testing/Manufacture/Automobile, Paint & Plating Testing Equipments
 
sales flier
sales fliersales flier
sales flier
 
Cody Cunningham resume edited
Cody Cunningham resume editedCody Cunningham resume edited
Cody Cunningham resume edited
 
New DMH2015 Resume
New DMH2015 ResumeNew DMH2015 Resume
New DMH2015 Resume
 
Sealtec Metallic Gaskets from ERIKS
Sealtec Metallic Gaskets from ERIKSSealtec Metallic Gaskets from ERIKS
Sealtec Metallic Gaskets from ERIKS
 
KDV WT Brochure 100510
KDV WT Brochure 100510KDV WT Brochure 100510
KDV WT Brochure 100510
 
MaagKit Data Sheet
MaagKit Data SheetMaagKit Data Sheet
MaagKit Data Sheet
 
EA article -Legacy Way
EA article -Legacy WayEA article -Legacy Way
EA article -Legacy Way
 
Cirexx International Presentation
Cirexx International PresentationCirexx International Presentation
Cirexx International Presentation
 
OSProfile
OSProfileOSProfile
OSProfile
 
02Resume updated
02Resume updated02Resume updated
02Resume updated
 
PVC-UPVC solvent Cement Manufacture
 PVC-UPVC solvent Cement Manufacture PVC-UPVC solvent Cement Manufacture
PVC-UPVC solvent Cement Manufacture
 
Sentry dry chemical hand portable extinguishers data specification sheet
Sentry dry chemical hand portable extinguishers data specification sheetSentry dry chemical hand portable extinguishers data specification sheet
Sentry dry chemical hand portable extinguishers data specification sheet
 
cvkemp robert (Sept 16) (1) (1)
cvkemp robert (Sept 16) (1) (1)cvkemp robert (Sept 16) (1) (1)
cvkemp robert (Sept 16) (1) (1)
 
Analytical Science 5th Symposium Programme Registration Form (singlepages)
Analytical Science 5th Symposium Programme  Registration Form (singlepages)Analytical Science 5th Symposium Programme  Registration Form (singlepages)
Analytical Science 5th Symposium Programme Registration Form (singlepages)
 
Cleveland Cable - Marine & Offshore, Railway, Instrumentation, Control & Comm...
Cleveland Cable - Marine & Offshore, Railway, Instrumentation, Control & Comm...Cleveland Cable - Marine & Offshore, Railway, Instrumentation, Control & Comm...
Cleveland Cable - Marine & Offshore, Railway, Instrumentation, Control & Comm...
 
IECS_Cable_Concrete_Brochure
IECS_Cable_Concrete_BrochureIECS_Cable_Concrete_Brochure
IECS_Cable_Concrete_Brochure
 

Destaque

Comercio internacional regular 11
Comercio internacional regular 11Comercio internacional regular 11
Comercio internacional regular 11
J M
 
SAMKUMAR- Sr.Linux SystemAdministrator (1)
SAMKUMAR- Sr.Linux SystemAdministrator (1)SAMKUMAR- Sr.Linux SystemAdministrator (1)
SAMKUMAR- Sr.Linux SystemAdministrator (1)
gandi samkumar
 
Aplicacionesclavemariogarciacortes
AplicacionesclavemariogarciacortesAplicacionesclavemariogarciacortes
Aplicacionesclavemariogarciacortes
Mario Garcia
 
Apresentação projeto troca troca literário com ênfase na diversidade étnico -...
Apresentação projeto troca troca literário com ênfase na diversidade étnico -...Apresentação projeto troca troca literário com ênfase na diversidade étnico -...
Apresentação projeto troca troca literário com ênfase na diversidade étnico -...
scarabelot1
 

Destaque (12)

chapter 3 ethics: computer and internet crime
chapter 3 ethics: computer and internet crimechapter 3 ethics: computer and internet crime
chapter 3 ethics: computer and internet crime
 
DAVIS_BRANDON_T_201407_FINAL
DAVIS_BRANDON_T_201407_FINALDAVIS_BRANDON_T_201407_FINAL
DAVIS_BRANDON_T_201407_FINAL
 
National Cooperative Month Observed in October
National Cooperative Month Observed in OctoberNational Cooperative Month Observed in October
National Cooperative Month Observed in October
 
Comercio internacional regular 11
Comercio internacional regular 11Comercio internacional regular 11
Comercio internacional regular 11
 
India - a Market to Watch
India - a Market to WatchIndia - a Market to Watch
India - a Market to Watch
 
SAMKUMAR- Sr.Linux SystemAdministrator (1)
SAMKUMAR- Sr.Linux SystemAdministrator (1)SAMKUMAR- Sr.Linux SystemAdministrator (1)
SAMKUMAR- Sr.Linux SystemAdministrator (1)
 
Engine heat recovery
Engine heat recoveryEngine heat recovery
Engine heat recovery
 
Gloria Ines Suarez Martinez
Gloria Ines Suarez Martinez	Gloria Ines Suarez Martinez
Gloria Ines Suarez Martinez
 
Aplicacionesclavemariogarciacortes
AplicacionesclavemariogarciacortesAplicacionesclavemariogarciacortes
Aplicacionesclavemariogarciacortes
 
Eyes in the Sky™
 Eyes in the Sky™  Eyes in the Sky™
Eyes in the Sky™
 
Atic8 luciareis
Atic8 luciareisAtic8 luciareis
Atic8 luciareis
 
Apresentação projeto troca troca literário com ênfase na diversidade étnico -...
Apresentação projeto troca troca literário com ênfase na diversidade étnico -...Apresentação projeto troca troca literário com ênfase na diversidade étnico -...
Apresentação projeto troca troca literário com ênfase na diversidade étnico -...
 

Semelhante a PAUT risk mitigation strategy

2014 04 (a4) naogp editorial - q&a maats bending machines
2014   04 (a4) naogp editorial - q&a maats bending machines2014   04 (a4) naogp editorial - q&a maats bending machines
2014 04 (a4) naogp editorial - q&a maats bending machines
Maats
 
Pipeline Welding
Pipeline WeldingPipeline Welding
Pipeline Welding
jacobrajeev
 
Thiet ke duong_ong_tren_bo
Thiet ke duong_ong_tren_boThiet ke duong_ong_tren_bo
Thiet ke duong_ong_tren_bo
Robinking Boley
 
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser ProjectsISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
Jean-Francois Saint-Marcoux
 
Aussie hole opener a hit - CUI MayJune Final
Aussie hole opener a hit - CUI MayJune FinalAussie hole opener a hit - CUI MayJune Final
Aussie hole opener a hit - CUI MayJune Final
Ervin Bata
 
riopipeline2015_1094_ibp1094_15
riopipeline2015_1094_ibp1094_15riopipeline2015_1094_ibp1094_15
riopipeline2015_1094_ibp1094_15
Monica Riccio
 
DW143-Ductwork-Leakage-Testing.pdf
DW143-Ductwork-Leakage-Testing.pdfDW143-Ductwork-Leakage-Testing.pdf
DW143-Ductwork-Leakage-Testing.pdf
wrsconsultoria1
 

Semelhante a PAUT risk mitigation strategy (20)

mcd_SOAR A
mcd_SOAR Amcd_SOAR A
mcd_SOAR A
 
Neidigk: 2013 Sandia Wind Plant Reliability Workshop
Neidigk: 2013 Sandia Wind Plant Reliability WorkshopNeidigk: 2013 Sandia Wind Plant Reliability Workshop
Neidigk: 2013 Sandia Wind Plant Reliability Workshop
 
Esab world pipelines
Esab world pipelinesEsab world pipelines
Esab world pipelines
 
7285665.pdf
7285665.pdf7285665.pdf
7285665.pdf
 
Rengaraj nagappan cv aug 15done
Rengaraj nagappan cv aug 15doneRengaraj nagappan cv aug 15done
Rengaraj nagappan cv aug 15done
 
2014 04 (a4) naogp editorial - q&a maats bending machines
2014   04 (a4) naogp editorial - q&a maats bending machines2014   04 (a4) naogp editorial - q&a maats bending machines
2014 04 (a4) naogp editorial - q&a maats bending machines
 
SPE 147856
SPE 147856SPE 147856
SPE 147856
 
Pipeline Welding
Pipeline WeldingPipeline Welding
Pipeline Welding
 
NAMRC newsletter
NAMRC newsletterNAMRC newsletter
NAMRC newsletter
 
Meshak cv
Meshak cv Meshak cv
Meshak cv
 
Meshak cv
Meshak cv Meshak cv
Meshak cv
 
Why Do The Consulting Engineers Stress On Maintaining Pipe Casing Integrity?
Why Do The Consulting Engineers Stress On Maintaining Pipe Casing Integrity?Why Do The Consulting Engineers Stress On Maintaining Pipe Casing Integrity?
Why Do The Consulting Engineers Stress On Maintaining Pipe Casing Integrity?
 
Thiet ke duong_ong_tren_bo
Thiet ke duong_ong_tren_boThiet ke duong_ong_tren_bo
Thiet ke duong_ong_tren_bo
 
Mithun Banjan CV
Mithun Banjan CVMithun Banjan CV
Mithun Banjan CV
 
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser ProjectsISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
 
Aussie hole opener a hit - CUI MayJune Final
Aussie hole opener a hit - CUI MayJune FinalAussie hole opener a hit - CUI MayJune Final
Aussie hole opener a hit - CUI MayJune Final
 
riopipeline2015_1094_ibp1094_15
riopipeline2015_1094_ibp1094_15riopipeline2015_1094_ibp1094_15
riopipeline2015_1094_ibp1094_15
 
Arctest CR presentation
Arctest CR presentationArctest CR presentation
Arctest CR presentation
 
OCS Training - API 570 piping inspection course
OCS Training - API 570 piping inspection courseOCS Training - API 570 piping inspection course
OCS Training - API 570 piping inspection course
 
DW143-Ductwork-Leakage-Testing.pdf
DW143-Ductwork-Leakage-Testing.pdfDW143-Ductwork-Leakage-Testing.pdf
DW143-Ductwork-Leakage-Testing.pdf
 

PAUT risk mitigation strategy

  • 1. Phased Array Ultrasonic Testing Vendor Qualifcation for a major subsea project (A risk mitigation strategy) ABSTRACT A significant fabrication risk was identified on the Shah Deniz 2 subsea gas manifolds. Heavy wall thickness welds needed to be inspected and the limits of radiography meant a PAUT vendor had to be qualified in time for the fabrication of the pipework. Colin Smith: https://uk.linkedin.com/in/colinanthonysmith
  • 2. A significant risk had to be addressed if the fabrication site was to avoid using radiography on heavy wall welds on the high pressure (900bar) gas pipework. The obvious benefits were: safety (elimination of radiography as the means to NDE the welds), quality – at the 62.5mm wall thicknesses in the stainless steels it would be difficult to detect crack-like defects in the root areas with the usual UT and RT methods, and finally productivity; being able to weld & inspect at the same time in the same vicinity had significant productivity benefits. There are many NDE contractors who claim that they can PAUT welds and they can if the welds are ferrous. However, if the welds are nickel based alloys or a stainless steel, then this significantly reduces the number of NDE contractors with the correct knowhow. Nickel based alloys and stainless steels are ultrasonically more opaque than ferrous alloys due to the attenuation of the sound beam. This demands greater energy from the probes and programming to tailor the beam for the specific application. An amplitude based PAUT program was initiated by the client – with a goal of qualifying two PAUT vendors to achieve a competitive tendering situation prior to start of inspection of the heavy wall pipework required on the Shah Deniz 2, gas production manifold pipework. These two vendors would then be pre-qualified for the main subsea contractor to choose for the fabrication phase in Norway. I led this initiative and delivered the successful outcome. Scanning a 10” joint – note the finish on the weld caps. A sized based PAUT program was initially considered but this would have involved significant engineering to accept non-Code compliant defects justified by FEA. So the
  • 3. amplitude based approach was adopted and ASME allowable defects as the basis of acceptance. No crack like indications are allowable in the Code. The qualification program was commenced 18 months before pipework fabrication. Seeded coupons were manufactured at two locations one in Europe and one in the USA. It became evident that only one seeded coupon manufacturer could achieve the correct morphology of the defects that needed to be seeded at the correct depths. Of particular interest was the location in the root area of 1.5mm crack like indications. These were to simulate lack of fusion in the root. However the coupon was peppered with various types of defects throughout the weld thickness. The ultimate acceptance criteria was: zero crack like indications were allowable. The two seeded coupons were made with four rings of contract material: 25%Cr super duplex to itself with matching filler, and nickel alloy clad X65 welded to 25%Cr super duplex with a high nickel filler. These seeded coupons took 12 weeks to fabricate. Seeding was performed using the thickest sections to be used on site: 62.5mm wt on the 10” pipework. The seeded coupons were then shipped to the two preferred PAUT vendors facilities in turn where the operator was tested using the PAUT vendors procedure. These trials were witnessed by the client – care was taken to ensure that no collaboration between operators took place. This served to qualify the operator and the vendors procedure. The output was a map submitted to the client declaring where the PAUT operator found the defects and they had to be characterized. This map was compared to the original map. Operator and vendor either passed or failed the test. After trialing five potential vendors only two were capable of detecting the crack like defects in the root area. Some vendors could not detect many of the seeded defects in the mid thickness of the 62.5mm joints. Final value of the CTR was in excess of $1.5MM.
  • 4. In addition to the seeded coupons (and in parallel) the vendors had to be supplied with contract material coupons of each size of pipework that was to be tested: in this case 6” x 47.5mm wt , the 10” x 62.5mm wt and the 12” x 38mm wt. Priority was given to the 10” coupons for the seeding trials.
  • 5. Phased array automatic ultrasonic testing on 10” super duplex joint 62.5mm wall thickness. Duration from mobilization to demobilization 3 hrs – two scans (one from either side).