SlideShare uma empresa Scribd logo
1 de 49
Baixar para ler offline
Dealing with Schedules That 
     Cannot be Approved



             Chris Carson, PSP, CCM, PMP
Corporate Director of Project Controls, Alpha Corporation
          Chris.carson@alphacorporation.com
                      757-342-5524
                                     1
Chris Carson
Corporate Director of Project Controls, Alpha Corporation
   • Responsible for standards, processes, and procedures for a team of schedulers, analysts, and project
         managers in multiple office locations, as well as analysis, work product, testimony, and marketing
     •   Developed and manages the in-house project controls training program at Alpha
•   Certifications: PSP, CCM, PMP
•   University: University of Virginia, Mechanical Engineering, 1968-1972
•   Professional Field: 38 years of experience in Construction Management Services
    specializing in Scheduling, Schedule Analysis, Estimating, Claims
•   Active in AACE (Association for the Advancement of Cost Estimating International)
     •   Author & reviewer of Recommended Practices in Scheduling & Forensic Schedule Analysis RP
•   Active in PMI (Project Management Institute) Scheduling Community of Practice
     •   Managing Director for SEI (Scheduling Excellence Initiative) writing Best Practices and Guidelines for
         Scheduling and Schedule Impact Analysis
•   Active in CMAA (Construction Management Association of America)
     •   Served on committee revising Time Management Chapter
     •   Chosen as one of National CCM Trainers
•   Active in Planning Planet & the International Guild of Project Controls
     •   Chief Editor for US, developing accreditations for project controls
Something you do not know about me:
    I’m Irish-American so I’ve likely told everything to everyone (my wife can vouch)

                                                                       2
Unapprovable Schedules

  • It is in best interests of the project to get an approvable 
    schedule in place early
  • Necessary for:
      –   Planning
      –   Management
      –   Analysis
      –   Documentation
  • As‐planned portion must model Contractor’s means and 
    methods
  • As‐built portion must accurately represent history
  • Schedule should represent reasonable approach for all 
    tasks that could affect the project


                                              3
• If schedule does not support these goals, likely does not 
  meet industry practices
• Owner will likely be taking on risks from the schedule
• Schedule Review
    –   Process designed to improve quality of schedule
    –   Protects Owner from illegitimate EoT requests
    –   Protects Contractor by “proving” entitlement to EoT
    –   But be reasonable!




                                                4
• Too many projects start without approved schedules
   – Increases risks to Owner and Contractor
   – However, if risks of approval are greater than risks of 
     rejection, rejection is better option
• This session should: 
   – Offer suggestions as to ways to increase ability to approve 
     schedules
   – Provide guidance for what to do if schedule cannot be 
     approved




                                                5
• Outline
   – Risks of approval of “bad” schedule
   – Reasons why schedules cannot be approved
   – Suggestions for scheduling requirements to increase ability 
     to approve schedule
   – Project controls actions when schedules cannot be 
     approved
   – General project actions that can be taken to increase 
     opportunities to approve schedules
   – General industry actions that can be taken to increase 
     opportunities to approve schedules




                                               6
• Risks of approval of “bad” schedule
   – Owner
       • Opportunities for claims positioning from manipulation
       • Reduced ability to analyze delay 
       • Reduced ability to predict completion
       • Could commit Owner to high resource need for submittals and 
         paperwork
       • Poor logic makes Total float values less meaningful
       • Increased chances that trades and spaces will overload near end of 
         project
            – Risk of delay and disruption
            – Risk of reduced quality (Dick Faris – Q x S = T x C)




                                                        7
• Risks of approval of “bad” schedule
   – Contractor
       • No approved basis from which to measure delays
       • Owner has not accepted Owner‐responsible work integration into the 
         schedule
       • inability to prove Owner caused delays or disruption
       • Planning is probably not sufficient
       • Subcontractor input probably not sufficient
       • Total Float values not legitimate or useful
            – No early warning of problems
            – No ability to correct course before wasting money




                                                      8
• Reasons why baseline or as‐planned schedules 
  cannot be approved
   – Incomplete schedule
   – Poor modeling of scope and plan
   – Misalignment between schedule and narrative (plan not 
     evident in schedule)
   – Missing narrative
   – Missing scope of work
   – Uneven development of trade scope
   – Inappropriate Critical Paths
   – Problems with logic relationships
   – Failure to plan for resources
   – Schedule component problems (lags, constraints, calendars, 
     dangling or open activities, cost loading)


                                             9
• Reasons why update schedules cannot be approved
   –   Poor continuing modeling of scope and plan
   –   Unexplained revisions
   –   Missing narrative (to explain revisions)
   –   Out of sequence work (affecting Critical Path)
   –   Inappropriate Critical Paths
   –   Addition of delay events not approved by Owner
   –   Inaccurate as‐built data
   –   Inadequate resource planning
   –   Cost loading errors




                                             10
• Suggestions for scheduling requirements to increase 
  ability to approve schedule
   –   Require bid or tender schedule to qualify for award
   –   Time for planning – Contract should precede NTP
   –   Specify scheduler requirements (PSP, experience)
   –   Use two stage schedule submission
        • Preliminary or Initial – short interim planning
        • Detailed or Initial – full schedule
   –   Clarification of level of detail requirements
   –   Elaboration of written narrative requirement
   –   Requirement for crew resource loading
   –   Higher retainage costs for submission of approvable 
       schedule


                                                            11
• Suggestions for scheduling meetings to increase ability to 
  approve schedule:
    –   Preliminary schedule review feedback
    –   Risk workshop
    –   Scheduling planning presentation meeting
    –   Presentation of Time Impact Analyses for EoTs
    –   Presentation of disputed issue analyses




                                               12
• Feedback from preliminary schedule




                                       13
• Risk Workshop – jointly with Owner and Contractor




                                        14
• Project controls actions when schedules cannot be 
  approved
   – Identification of major discrepancies
   – Careful documentation of all discrepancies
       • Point out reason for discrepancies
       • Summarized list
   – Separate impacts absorbed into the 
     schedule/project from those that are not
       • Absorbed impacts require a forensic analysis
       • Impacts not yet absorbed require a Prospective TIA




                                                 15
• List of discrepancies – clear, succinct




                                            16
• Project controls actions when schedules cannot be 
  approved
   – Project requires a much higher level of documentation of 
     as‐built data
       • Daily recordkeeping is necessary
   – Deal with as‐built portion of the schedule separately from 
     as‐planned
       • Similar to impact analysis
           – As‐built has absorbed delays
           – As‐planned has not absorbed delays




                                              17
• As‐Built Documentation
   – When schedule discrepancies are severe, develop 
     Daily Specific As‐Built (DSAB) Schedule to document 
     actual conditions
   – Document actual resources, ideally crews/equipment
   – Perform resource analysis to validate what drove 
     schedule performance
   – Perform identification of As‐Built Longest Path (or 
     ABCP as noted in AACE International’s FSA RP)
   – Maintain cumulative delay chart from revised 
     schedules, annotate delay chart with impacts/low 
     productivity – Schedule Log (RP upcoming)
   – Capture Time Performance Ratio or Missed S/F

                                         18
DSAB Prepared in a Forensic Mode
• Daily Specific As‐Built in As‐Planned vs. As‐Built Schedule Analysis
                        » Cost Engineering Vol. 50/No. 3 March 2008 By Svetlana Lyasko




                                                                                         19
AB Forensic Schedule Development
• Retrospective As‐Built Schedule Development
   –   2005 AACE International Transactions CDR.12 by Dr. Anamaria Popescu and Andrew Avalon




                                                                                               20
DSAB Performed during Project
 • Daily Specific As‐Built schedule development
    – Significantly easier than in forensic application




                                                     21
DSAB Procedure
•   DSAB development – capture daily data into spreadsheet 
     – Each line item is a 1 day resource




                                                       22
DSAB Procedure

 • DSAB – identify field data for each line item, align with schedule 
 • These “activity codes” allow for filtering, sorting




                                                 23
DSAB Procedure

• DSAB – develop all data for codes, then import into schedule




                                            24
Actual Resource Collection – by Crews
• Resource collection by crews 
   – Show planned crew loads (from contractor’s schedules to make a point)
   – Collect count of actual crews




                                               25
Resource Analysis – Compare Plan/Actual

 • Resource analysis




                             26
Identify ABLP for Negotiations

 • Presentation of ABLP analysis – alone or as AP vs. AB
     – Use resource analysis to help establish ABLP
     – Use ABLP to confirm validity of corrected schedules




                                                27
As‐Built Longest Path

    • As‐Built Longest Path (ABLP) presentation
                                                               2004                  2005                      2006
 Location              Work Description
                                                        A M J J A S O N D   J F M A M J J A S O N D   J F M A M J J A S O N D

            Mobilization

  SBW 5     Clearing and Grubbing
            Demolition, Asphalt Placement, Erosion
  SBW 4
            and Sediment Control
                                                             38 CD
  B603      Electrical Conduit, Demolition
            Demolition, Formwork, Rebar, Deck
                                                              13 CD
  B601
            Concrete Placement                                19 CD
            Formwork, Rebar, Deck Concrete
  B602
            Placement                                           37 CD
            Formwork, Rebar, Footer & Wingwall
            Placement, Precast Concrete Wall
                                                                     99 CD
  SBW 5
            Erection, Asphalt Placement, Guardrail                        90 CD
            Installation
  SBW 6     Precast Concrete Wall Erection                                                               361 CD
            Electrical, Clearing & Grubbing,
  SBW 5
            Excavation & Backfill                                                            20 CD
            Excavation & Backfill, Asphalt Placement,
  SBW 6
            Guardrail Installation                                                            11 CD
  B602      Concrete decks, Curb and Gutter                                                    39 CD
  B601      Demolition, Demobilization
                                                                                                   3 CD
            Concrete sidewalk placement, Demolition,
                                                                                                   4 CD
  B603
            Demobilization                                                                        27 CD



                                                                                       28
Cumulative Delay Discussion

• Schedule Log to generate cumulative delay chart
 Chron                                                       Activity    Critical                Update Window Project Duration Remain. Time
         File Name   Start Date   Data Date   Early Finish                           Cum Delay                                                                  Notes
 Order                                                        Count     Activities                  Size (cd)        (cd)          (cd)


          6-Jul-09   15-Apr-09    15-Apr-09    26-Jul-10       578         29            0            N/A             467           467                   baseline DC 2003
                                                               580         83            0            N/A
          6-Jul-09   15-Apr-09    15-Apr-09    26-Jul-10                                                              467           467             revised baseline DC Hodges 03
                                                               578         61                         92
         16-Jul-08   15-Apr-09    16-Jul-09    10-Aug-10                                10                            482           390            Revised baseline (Zero Progress)
         9-Mar-09                                                          50            0            N/A
                     15-Apr-09    15-Apr-09    26-Jul-10       571                                                    467           467               Baseline Revisions DC 03
                                                                           50            0            N/A
  1      15-Apr-09   15-Apr-09    15-Apr-09    26-Jul-10       571                                                    467           467                     Baseline Final
                                                                                      #VALUE!         16
          DESIGN
                     15-Apr-09    1-May-09        N/A
                                                                8           8                                      #VALUE!                             Design Issues Schedule
         19-Oct-09                19-Oct-09    29-Sep-10                   112          65            171
  2                  15-Apr-09                                 571                                                    532           345                Update October 19, 2009
         4-Dec-09                 4-Dec-09                                              91            46
  3                  15-Apr-09
                                               25-Oct-10
                                                               571
                                                                           133
                                                                                                                      558           325               Update December 04, 2009


         4-Dec-09    15-Apr-09    4-Dec-09     9-Dec-10        571         221          136            0              603           370        Update December 04, 2009, with Glenwood
  3
         21-Jan-10                21-Jan-10    15-Dec-10                   212          142           48
  4                  15-Apr-09                                 571                                                    609           328                 January Update 2010
                                                                                        154           41
  5      3-Mar-10
                     15-Apr-09
                                  3-Mar-10     27-Dec-10
                                                               571
                                                                           213                                        621           299                 February Update 2010
                                                                                        154           77
  6      19-May-10
                     15-Apr-09
                                  19-May-10    27-Dec-10
                                                               571
                                                                           127                                        621           222                   May update 2010
                                                                                        133           44
  7       2-Jul-10
                     15-Apr-09
                                   2-Jul-10    6-Dec-10
                                                               571
                                                                           134                                        600           157                   June Update 2010
                                                                                        144           26
  8      28-Jul-10
                     15-Apr-09
                                  28-Jul-10    17-Dec-10
                                                               571
                                                                           185                                        611           142                   July Update 2010
                                                                                        172            0
             IT
                     15-Apr-09    28-Jul-10
                                               14-Jan-11       577         185                                        639           170                IT Claim with July Update
                                                                                        199           65
  9      1-Oct-10
                     15-Apr-09
                                  1-Oct-10     10-Feb-11
                                                               571
                                                                           113                                        534           266                September Update 2010
                                                                                        227            2
           TANK
                     15-Apr-09    3-Oct-10
                                               10-Mar-11       576         114                                        694           158            Day Tank Claim with Sept Update
                                                                                        213           31
  10     3-Nov-10
                     15-Apr-09
                                  3-Nov-10     24-Feb-11
                                                               571
                                                                           82                                         680           113                 October Update 2010
                                                                                        219           37
  11     10-Dec-10
                     15-Apr-09
                                  10-Dec-10    2-Mar-11
                                                               571
                                                                           62                                         686           82                 November Update 2010
                                                                                        210           67
  12     15-Feb-11
                     15-Apr-09
                                  15-Feb-11    21-Feb-11
                                                               571
                                                                           18                                         677            6                  January Update 2011
                                                                                        256           31
                     15-Apr-09                                 571                                                    723           21
  13     18-Mar-11                18-Mar-11    8-Apr-11                     6
                                                                                        295           39
                                                                                                                                                                        29
                                                                                                                                                        February Update 2011

  14     26-Apr-11
                     15-Apr-09
                                  26-Apr-11    17-May-11
                                                               571
                                                                            6
                                                                                                                      762           21                 March/April Update 2011
Cumulative Delay Discussion
• Chart Cumulative Delays directly from Schedule Log




                                               30
Cumulative Delay Discussion

• Chart Cumulative Delays – Overlay known delay event timeframes




                                          31
Cumulative Delay Discussion

• Chart Cumulative Delays – Label known delay timeframes




                                          32
Cumulative Delay Discussion

• Chart Cumulative Delays




    Period of possible concurrent submittal problems




                                                33
Cumulative Delay Discussion

• Chart Cumulative Delays – Note any delays/production issues




             Shows two schedules with same data date & different EF dates




   Could be acceleration or mistake, but worthy of investigation during triage?


                                                   34
Cumulative Delay Discussion
• Chart Cumulative Delays – Identify specific delay  or acceleration 
  concerns



     No overall delay due to IT design




                                              35
Cumulative Delay Discussion

• Chart Cumulative Delays – Identify specific delay or acceleration 
  concerns



               Period of possible concurrent production problems




                                                 36
Cumulative Delay Discussion

• Annotate Cumulative Delays



                       Period of possible concurrent production problems
    No overall delay due to IT design

    Period of possible
    concurrent submittal
    problems


            Shows two schedules with same data date & different EF dates




                                               37
Cumulative Delay Discussion

 • Annotated Cumulative Delay Chart




                                      38
Actual/Original Duration

 • TPR ‐ Time Performance Ratio – AD/OD
    – Shows performance slips




                                          39
TPR/Resource Analysis

 • Show Activity Duration impact on delays




                                             40
As‐Built 

  • As‐Built documentation
     – This provides solid documentation of what 
       happened
     – Collected from project records – validated
     – Documented in form for use in meeting 
       with contractor
  • Next step – As‐Planned documentation




                                           41
As‐Planned

• As‐Planned documentation
   – Create separate set of schedules incorporating revisions to 
     correct discrepancies
       • Document how discrepancies are incorporated
   – Identify analysis differences between submitted schedules 
     and revised schedules
   – Analyze resource (crew) needs for next period work
       • Review for reasonableness (compare to actual)
   – Compare that ASLP/CP to the previous period revised 
     analysis, record differences, and analyze
   – Generally it should align fairly well – while the contractor’s 
     schedule will not
   – Meet with Contractor – present results of ABLP/CP, 
     resource analysis
       • Intent is to show how revised analysis (incorporating 
         discrepancy revisions aligns with actual project data in 
         DSAB/ABLP

                                                  42
As‐Planned

 • Show As‐Planned differences




                                 43
Present Resource Plan

 • Planned Resource Histogram




                                44
Present Resource Plan

 • Resources – Daily Plan




                            45
Conclusions

 • These steps will put the Owner in a strong position even 
   without approvable schedules
 • The goal is to use the data to meet with the Contractor
     – Convince them to cooperate and fix 
       schedules
     – Convince them that documentation rebut 
       loose/inaccurate claims
     – Convince them that the Owner’s analysis 
       process is accurate and convincing
 • Ideally this process will influence the Contractor to raise 
   the quality of their schedules
 • Bingo; approvable schedules


                                              46
Other Opportunities

 • General industry actions that can be taken to increase 
   opportunities to approve schedules
    – Providing free training in the industry to improve the quality 
      of schedules
    – Refer contractors to quality scheduling consultants
    – Industry involvement to define and raise the level of good 
      practices for scheduling
    – Helping the Owner to develop a schedule‐driven culture
    – Conference participation:
        •   ConstructionCPM
        •   AACE International
        •   PMI SCoP
        •   CMAA



                                                47
Dealing with Schedules That Cannot be Approved
  Questions? Comments?



               Chris Carson, PSP, CCM, PMP
  Corporate Director of Project Controls, Alpha Corporation
            Chris.carson@alphacorporation.com
                        757-342-5524

                                     48
Separator Page




                 49

Mais conteúdo relacionado

Mais procurados

Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationChris Carson
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMIChris Carson
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedulesHatem Hegazi
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMIChris Carson
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesThe Vertex Companies, LLC
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricksp6academy
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedMichael Pink
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2Abdelhay Ghanem
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 

Mais procurados (20)

Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMI
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 

Semelhante a Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting

PMI-ACP Domain V: Adaptive Planning v1.0
PMI-ACP Domain V: Adaptive Planning v1.0PMI-ACP Domain V: Adaptive Planning v1.0
PMI-ACP Domain V: Adaptive Planning v1.0PhuocNT (Fresher.VN)
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptxProfDrAnbalaganChinn
 
Project Auditing
Project AuditingProject Auditing
Project AuditingSalih Islam
 
Price.rick
Price.rickPrice.rick
Price.rickNASAPMC
 
Price.rick
Price.rickPrice.rick
Price.rickNASAPMC
 
Fleming.jon
Fleming.jonFleming.jon
Fleming.jonNASAPMC
 
Planning for adverse weather in Construction Projects
Planning for adverse weather in Construction ProjectsPlanning for adverse weather in Construction Projects
Planning for adverse weather in Construction Projectshilalitani
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse WeatherChris Carson
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptTecnicoItca
 
project-management.pdf
project-management.pdfproject-management.pdf
project-management.pdfSAMPREET3
 
Projects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFailProjects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFailBarbara Franks
 
Time & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionTime & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionGalala University
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminChris Carson
 

Semelhante a Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting (20)

PMI-ACP Domain V: Adaptive Planning v1.0
PMI-ACP Domain V: Adaptive Planning v1.0PMI-ACP Domain V: Adaptive Planning v1.0
PMI-ACP Domain V: Adaptive Planning v1.0
 
Chapter 03
Chapter 03Chapter 03
Chapter 03
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx
 
Project Auditing
Project AuditingProject Auditing
Project Auditing
 
Price.rick
Price.rickPrice.rick
Price.rick
 
Price.rick
Price.rickPrice.rick
Price.rick
 
Fleming.jon
Fleming.jonFleming.jon
Fleming.jon
 
Chap04
Chap04Chap04
Chap04
 
Sysdev
SysdevSysdev
Sysdev
 
Planning for adverse weather in Construction Projects
Planning for adverse weather in Construction ProjectsPlanning for adverse weather in Construction Projects
Planning for adverse weather in Construction Projects
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse Weather
 
EpM
EpMEpM
EpM
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.ppt
 
project-management.pdf
project-management.pdfproject-management.pdf
project-management.pdf
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
Chap04.ppt
Chap04.pptChap04.ppt
Chap04.ppt
 
Projects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFailProjects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFail
 
Time & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionTime & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and Inspection
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
 
Mpug 111208 generic
Mpug 111208 genericMpug 111208 generic
Mpug 111208 generic
 

Mais de Chris Carson

Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop ConferenceChris Carson
 
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesChris Carson
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpChris Carson
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry SchedulingChris Carson
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodChris Carson
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion SchedulesChris Carson
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotChris Carson
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesChris Carson
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...Chris Carson
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesChris Carson
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful MediationChris Carson
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule RevisionsChris Carson
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex ProjectChris Carson
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesChris Carson
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - AirportChris Carson
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony MistakesChris Carson
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor SchedulingChris Carson
 

Mais de Chris Carson (20)

Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop Conference
 
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls Pp
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry Scheduling
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis Method
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel Schedules
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful Mediation
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony Mistakes
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor Scheduling
 

Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting

  • 1. Dealing with Schedules That  Cannot be Approved Chris Carson, PSP, CCM, PMP Corporate Director of Project Controls, Alpha Corporation Chris.carson@alphacorporation.com 757-342-5524 1
  • 2. Chris Carson Corporate Director of Project Controls, Alpha Corporation • Responsible for standards, processes, and procedures for a team of schedulers, analysts, and project managers in multiple office locations, as well as analysis, work product, testimony, and marketing • Developed and manages the in-house project controls training program at Alpha • Certifications: PSP, CCM, PMP • University: University of Virginia, Mechanical Engineering, 1968-1972 • Professional Field: 38 years of experience in Construction Management Services specializing in Scheduling, Schedule Analysis, Estimating, Claims • Active in AACE (Association for the Advancement of Cost Estimating International) • Author & reviewer of Recommended Practices in Scheduling & Forensic Schedule Analysis RP • Active in PMI (Project Management Institute) Scheduling Community of Practice • Managing Director for SEI (Scheduling Excellence Initiative) writing Best Practices and Guidelines for Scheduling and Schedule Impact Analysis • Active in CMAA (Construction Management Association of America) • Served on committee revising Time Management Chapter • Chosen as one of National CCM Trainers • Active in Planning Planet & the International Guild of Project Controls • Chief Editor for US, developing accreditations for project controls Something you do not know about me: I’m Irish-American so I’ve likely told everything to everyone (my wife can vouch) 2
  • 3. Unapprovable Schedules • It is in best interests of the project to get an approvable  schedule in place early • Necessary for: – Planning – Management – Analysis – Documentation • As‐planned portion must model Contractor’s means and  methods • As‐built portion must accurately represent history • Schedule should represent reasonable approach for all  tasks that could affect the project 3
  • 4. • If schedule does not support these goals, likely does not  meet industry practices • Owner will likely be taking on risks from the schedule • Schedule Review – Process designed to improve quality of schedule – Protects Owner from illegitimate EoT requests – Protects Contractor by “proving” entitlement to EoT – But be reasonable! 4
  • 5. • Too many projects start without approved schedules – Increases risks to Owner and Contractor – However, if risks of approval are greater than risks of  rejection, rejection is better option • This session should:  – Offer suggestions as to ways to increase ability to approve  schedules – Provide guidance for what to do if schedule cannot be  approved 5
  • 6. • Outline – Risks of approval of “bad” schedule – Reasons why schedules cannot be approved – Suggestions for scheduling requirements to increase ability  to approve schedule – Project controls actions when schedules cannot be  approved – General project actions that can be taken to increase  opportunities to approve schedules – General industry actions that can be taken to increase  opportunities to approve schedules 6
  • 7. • Risks of approval of “bad” schedule – Owner • Opportunities for claims positioning from manipulation • Reduced ability to analyze delay  • Reduced ability to predict completion • Could commit Owner to high resource need for submittals and  paperwork • Poor logic makes Total float values less meaningful • Increased chances that trades and spaces will overload near end of  project – Risk of delay and disruption – Risk of reduced quality (Dick Faris – Q x S = T x C) 7
  • 8. • Risks of approval of “bad” schedule – Contractor • No approved basis from which to measure delays • Owner has not accepted Owner‐responsible work integration into the  schedule • inability to prove Owner caused delays or disruption • Planning is probably not sufficient • Subcontractor input probably not sufficient • Total Float values not legitimate or useful – No early warning of problems – No ability to correct course before wasting money 8
  • 9. • Reasons why baseline or as‐planned schedules  cannot be approved – Incomplete schedule – Poor modeling of scope and plan – Misalignment between schedule and narrative (plan not  evident in schedule) – Missing narrative – Missing scope of work – Uneven development of trade scope – Inappropriate Critical Paths – Problems with logic relationships – Failure to plan for resources – Schedule component problems (lags, constraints, calendars,  dangling or open activities, cost loading) 9
  • 10. • Reasons why update schedules cannot be approved – Poor continuing modeling of scope and plan – Unexplained revisions – Missing narrative (to explain revisions) – Out of sequence work (affecting Critical Path) – Inappropriate Critical Paths – Addition of delay events not approved by Owner – Inaccurate as‐built data – Inadequate resource planning – Cost loading errors 10
  • 11. • Suggestions for scheduling requirements to increase  ability to approve schedule – Require bid or tender schedule to qualify for award – Time for planning – Contract should precede NTP – Specify scheduler requirements (PSP, experience) – Use two stage schedule submission • Preliminary or Initial – short interim planning • Detailed or Initial – full schedule – Clarification of level of detail requirements – Elaboration of written narrative requirement – Requirement for crew resource loading – Higher retainage costs for submission of approvable  schedule 11
  • 12. • Suggestions for scheduling meetings to increase ability to  approve schedule: – Preliminary schedule review feedback – Risk workshop – Scheduling planning presentation meeting – Presentation of Time Impact Analyses for EoTs – Presentation of disputed issue analyses 12
  • 15. • Project controls actions when schedules cannot be  approved – Identification of major discrepancies – Careful documentation of all discrepancies • Point out reason for discrepancies • Summarized list – Separate impacts absorbed into the  schedule/project from those that are not • Absorbed impacts require a forensic analysis • Impacts not yet absorbed require a Prospective TIA 15
  • 17. • Project controls actions when schedules cannot be  approved – Project requires a much higher level of documentation of  as‐built data • Daily recordkeeping is necessary – Deal with as‐built portion of the schedule separately from  as‐planned • Similar to impact analysis – As‐built has absorbed delays – As‐planned has not absorbed delays 17
  • 18. • As‐Built Documentation – When schedule discrepancies are severe, develop  Daily Specific As‐Built (DSAB) Schedule to document  actual conditions – Document actual resources, ideally crews/equipment – Perform resource analysis to validate what drove  schedule performance – Perform identification of As‐Built Longest Path (or  ABCP as noted in AACE International’s FSA RP) – Maintain cumulative delay chart from revised  schedules, annotate delay chart with impacts/low  productivity – Schedule Log (RP upcoming) – Capture Time Performance Ratio or Missed S/F 18
  • 20. AB Forensic Schedule Development • Retrospective As‐Built Schedule Development – 2005 AACE International Transactions CDR.12 by Dr. Anamaria Popescu and Andrew Avalon 20
  • 21. DSAB Performed during Project • Daily Specific As‐Built schedule development – Significantly easier than in forensic application 21
  • 22. DSAB Procedure • DSAB development – capture daily data into spreadsheet  – Each line item is a 1 day resource 22
  • 23. DSAB Procedure • DSAB – identify field data for each line item, align with schedule  • These “activity codes” allow for filtering, sorting 23
  • 25. Actual Resource Collection – by Crews • Resource collection by crews  – Show planned crew loads (from contractor’s schedules to make a point) – Collect count of actual crews 25
  • 27. Identify ABLP for Negotiations • Presentation of ABLP analysis – alone or as AP vs. AB – Use resource analysis to help establish ABLP – Use ABLP to confirm validity of corrected schedules 27
  • 28. As‐Built Longest Path • As‐Built Longest Path (ABLP) presentation 2004 2005 2006 Location Work Description A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Mobilization SBW 5 Clearing and Grubbing Demolition, Asphalt Placement, Erosion SBW 4 and Sediment Control 38 CD B603 Electrical Conduit, Demolition Demolition, Formwork, Rebar, Deck 13 CD B601 Concrete Placement 19 CD Formwork, Rebar, Deck Concrete B602 Placement 37 CD Formwork, Rebar, Footer & Wingwall Placement, Precast Concrete Wall 99 CD SBW 5 Erection, Asphalt Placement, Guardrail 90 CD Installation SBW 6 Precast Concrete Wall Erection 361 CD Electrical, Clearing & Grubbing, SBW 5 Excavation & Backfill 20 CD Excavation & Backfill, Asphalt Placement, SBW 6 Guardrail Installation 11 CD B602 Concrete decks, Curb and Gutter 39 CD B601 Demolition, Demobilization 3 CD Concrete sidewalk placement, Demolition, 4 CD B603 Demobilization 27 CD 28
  • 29. Cumulative Delay Discussion • Schedule Log to generate cumulative delay chart Chron Activity Critical Update Window Project Duration Remain. Time File Name Start Date Data Date Early Finish Cum Delay Notes Order Count Activities Size (cd) (cd) (cd) 6-Jul-09 15-Apr-09 15-Apr-09 26-Jul-10 578 29 0 N/A 467 467 baseline DC 2003 580 83 0 N/A 6-Jul-09 15-Apr-09 15-Apr-09 26-Jul-10 467 467 revised baseline DC Hodges 03 578 61 92 16-Jul-08 15-Apr-09 16-Jul-09 10-Aug-10 10 482 390 Revised baseline (Zero Progress) 9-Mar-09 50 0 N/A 15-Apr-09 15-Apr-09 26-Jul-10 571 467 467 Baseline Revisions DC 03 50 0 N/A 1 15-Apr-09 15-Apr-09 15-Apr-09 26-Jul-10 571 467 467 Baseline Final #VALUE! 16 DESIGN 15-Apr-09 1-May-09 N/A 8 8 #VALUE! Design Issues Schedule 19-Oct-09 19-Oct-09 29-Sep-10 112 65 171 2 15-Apr-09 571 532 345 Update October 19, 2009 4-Dec-09 4-Dec-09 91 46 3 15-Apr-09 25-Oct-10 571 133 558 325 Update December 04, 2009 4-Dec-09 15-Apr-09 4-Dec-09 9-Dec-10 571 221 136 0 603 370 Update December 04, 2009, with Glenwood 3 21-Jan-10 21-Jan-10 15-Dec-10 212 142 48 4 15-Apr-09 571 609 328 January Update 2010 154 41 5 3-Mar-10 15-Apr-09 3-Mar-10 27-Dec-10 571 213 621 299 February Update 2010 154 77 6 19-May-10 15-Apr-09 19-May-10 27-Dec-10 571 127 621 222 May update 2010 133 44 7 2-Jul-10 15-Apr-09 2-Jul-10 6-Dec-10 571 134 600 157 June Update 2010 144 26 8 28-Jul-10 15-Apr-09 28-Jul-10 17-Dec-10 571 185 611 142 July Update 2010 172 0 IT 15-Apr-09 28-Jul-10 14-Jan-11 577 185 639 170 IT Claim with July Update 199 65 9 1-Oct-10 15-Apr-09 1-Oct-10 10-Feb-11 571 113 534 266 September Update 2010 227 2 TANK 15-Apr-09 3-Oct-10 10-Mar-11 576 114 694 158 Day Tank Claim with Sept Update 213 31 10 3-Nov-10 15-Apr-09 3-Nov-10 24-Feb-11 571 82 680 113 October Update 2010 219 37 11 10-Dec-10 15-Apr-09 10-Dec-10 2-Mar-11 571 62 686 82 November Update 2010 210 67 12 15-Feb-11 15-Apr-09 15-Feb-11 21-Feb-11 571 18 677 6 January Update 2011 256 31 15-Apr-09 571 723 21 13 18-Mar-11 18-Mar-11 8-Apr-11 6 295 39 29 February Update 2011 14 26-Apr-11 15-Apr-09 26-Apr-11 17-May-11 571 6 762 21 March/April Update 2011
  • 33. Cumulative Delay Discussion • Chart Cumulative Delays Period of possible concurrent submittal problems 33
  • 34. Cumulative Delay Discussion • Chart Cumulative Delays – Note any delays/production issues Shows two schedules with same data date & different EF dates Could be acceleration or mistake, but worthy of investigation during triage? 34
  • 37. Cumulative Delay Discussion • Annotate Cumulative Delays Period of possible concurrent production problems No overall delay due to IT design Period of possible concurrent submittal problems Shows two schedules with same data date & different EF dates 37
  • 39. Actual/Original Duration • TPR ‐ Time Performance Ratio – AD/OD – Shows performance slips 39
  • 41. As‐Built  • As‐Built documentation – This provides solid documentation of what  happened – Collected from project records – validated – Documented in form for use in meeting  with contractor • Next step – As‐Planned documentation 41
  • 42. As‐Planned • As‐Planned documentation – Create separate set of schedules incorporating revisions to  correct discrepancies • Document how discrepancies are incorporated – Identify analysis differences between submitted schedules  and revised schedules – Analyze resource (crew) needs for next period work • Review for reasonableness (compare to actual) – Compare that ASLP/CP to the previous period revised  analysis, record differences, and analyze – Generally it should align fairly well – while the contractor’s  schedule will not – Meet with Contractor – present results of ABLP/CP,  resource analysis • Intent is to show how revised analysis (incorporating  discrepancy revisions aligns with actual project data in  DSAB/ABLP 42
  • 46. Conclusions • These steps will put the Owner in a strong position even  without approvable schedules • The goal is to use the data to meet with the Contractor – Convince them to cooperate and fix  schedules – Convince them that documentation rebut  loose/inaccurate claims – Convince them that the Owner’s analysis  process is accurate and convincing • Ideally this process will influence the Contractor to raise  the quality of their schedules • Bingo; approvable schedules 46
  • 47. Other Opportunities • General industry actions that can be taken to increase  opportunities to approve schedules – Providing free training in the industry to improve the quality  of schedules – Refer contractors to quality scheduling consultants – Industry involvement to define and raise the level of good  practices for scheduling – Helping the Owner to develop a schedule‐driven culture – Conference participation: • ConstructionCPM • AACE International • PMI SCoP • CMAA 47
  • 48. Dealing with Schedules That Cannot be Approved Questions? Comments? Chris Carson, PSP, CCM, PMP Corporate Director of Project Controls, Alpha Corporation Chris.carson@alphacorporation.com 757-342-5524 48