The document outlines the construction plans and schedule for building the Brock Environmental Center, including safety and security measures, construction access and parking, green building processes, and the timeline of activities from site preparation through completion. Primary site access will be via Shore Drive and construction will occur Monday through Friday between 6:30am and 5:00pm. Temporary facilities include fencing, lighting, and a solar array for power. The project is scheduled to be completed by July 30, 2014.
2. CONSTRUCTION ENTRANCE AND DELIVERY
SIGN & PROJECT RENDERING
SAFETY RULES SIGN
& SECURITY GATE
SECURITY CAMERA
CONSTRUCTION PARKING
HOURIGAN & CBF
PROJECT TRAILERS
SECURED STORAGE
CONSTRUCTION-USE
SOLAR ARRAY
RECYCLE/LOADING AREA
SECURITY LIGHTING
DIRECTION OF CONSTRUCTION
SECURITY LIGHTING
SECURITY LIGHTING
EROSION AND SEDIMENT FENCE
TEMPORARY POWER/
SANITARY FACILITIES
BROCK ENVIRONMENTAL CENTER
SITE UTILIZATION PLAN
EXISTING SWING-GATE TO REMAIN
DURING CONSTRUCTION
STRUCTURAL ERECTION ROAD -
8’ STONE WITH GEO TEXTILE FABRIC
www.houriganconstruction.com www.cbf.org
3. Construction Means and Methods
www.houriganconstruction.com www.cbf.org
Noise Reduction
• Activities producing higher levels of
noise will be performed between the
hours of 9:00 am and 3:30 pm Monday
through Friday
Green Construction Processes Utilized to
Reduce Carbon Footprint
• On site water management
• No onsite construction parking
• Solar panel array for temporary construction
power
• Water well for temporary construction water
• Pollution reduction methods utilized on
equipment
• Containment areas around temporary toilets
• Minimize use of fossil fuel equipment
Public Parking and Access to Park
• Parking at the City pump house or Marlin
Bay Drive
• Access to park identified via signage
Construction Traffic
• Primary construction route: Shore Dr. to
E. Stratford
• Construction hours: Monday through
Friday 6:30 am – 5:00 pm
• Construction parking at the City pump
house
• Dust control methods
Safety & Security
• 6’ tall security fence
• Motion sensor lighting
• Web based security camera
4. Construction Schedule (as of July 16, 2013)
Brock Environmental Center
Construction Activity Start Date Completion Date
Total Construction 08/05/13 07/30/14
Fencing & Gates 08/05/13 08/16/13
Construction Trailers 08/12/13 08/16/13
Clearing & Construction Roads 08/19/13 08/30/13
Concrete Structure 08/28/13 10/18/13
Site Utilities 09/02/13 10/25/13
Steel Structure 10/28/13 11/29/13
Interior Construction 12/30/13 04/04/14
Pier 01/01/14 05/01/14
Site Work 02/17/14 04/11/14
Chesterfield Road Waterline 04/07/14 04/18/14
Marlin Bay Path 05/01/14 08/01/14
Complete Construction 07/30/14 07/30/14
CBF Occupancy Late Summer Early Fall
www.houriganconstruction.com www.cbf.org