Process Design and Facility Layout
Chapter 6
Process Design
and
Facility Layout
6-2
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Process Selection and System Design
Forecasting
Product and
service design
Capacity
planning
Facilities and
Equipment
Layout
Work
design
Process
selection
Technological
change
6-3
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Introduction
• Outsourcing, trend, reasons
• Make or Buy?
– Available capacity
– Expertise
– Quality Consideration
– The nature of demand
– Cost
6-4
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
• Variety
– How much
• Flexibility
– What degree
• Volume
– Expected output
• The key trade-off
Process Selection
6-5
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Process Types
• Projects
• Job Shops
• Batch Processing
• Repetitive/Assembly
• Continuous Processing
6-6
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Figure 3.6
Product-Process Matrix for Processes
(1) (2) (3) (4) (5)
One of a kind Low volume, Multiple Few major High volume
products, made low products products, high
to customer standardization moderate higher standardization,
order volume volume commodity
products
Process
Characteristics
(1)
Complex and
highly customized
process, unique
sequence of tasks
(2)
Jumbled flows,
complex work with
many exceptions
(3)
Disconnected line
flows, moderately
complex work
(4)
Connected line,
routine work
(5)
Continuous
flows, highly
repetitive work
LessComplexity,LessDivergence,MoreLineFlows
Less Customization and Higher Volume
Product Design
Continuous
process
Project
process
Line
process
Batch
process
Job
process
6-7
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Product-Process Matrix
Flexibility-Quality Dependability-Cost
Continuous
Flow
Assembly
Line
Batch
Job
Shop
Low
Volume
One of a
Kind
Multiple
Products,
Low
Volume
Few
Major
Products,
Higher
Volume
High
Volume,
High
Standard-
ization
Commercial
Printer
Heavy
Equipment
Automobile
Assembly
Sugar
Refinery
Flexibility-
Quality
Dependability
Cost
6-8
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
• Automation: Machinery that has
sensing and control devices that
enables it to operate
Automation
6-9
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Automation
• Numerically controlled (NC) machines
• Robot
• Computer-aided design and
manufacturing systems (CAD/CAM)
• Flexible manufacturing systems
• Computer-integrated manufacturing
(CIM)
6-10
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
• Layout: the configuration of
departments, work centers, and
equipment, with particular emphasis
on movement of work (customers or
materials) through the system
Layout
6-11
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
• Requires substantial investments of
money and effort
• Involves long-term commitments
• Has significant impact on cost and
efficiency of short-term operations
Importance of Layout Decisions
6-12
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Basic Layout Types
• Product Layouts
• Process Layouts
• Fixed-Position
• Combination Layouts
6-13
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Basic Layout Types
• Product Layout
– Layout that uses standardized processing
operations to achieve smooth, rapid, high-
volume flow
– Group equipments according to the sequential
steps of operations of a specific product
• Process Layout
– Layout that can handle varied processing
requirements
– Group equipments according to their functions
6-14
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
A Flow Line for Production or Service
Flow Shop or Assembly Line Work Flow
Raw
materials
or customer
Finished
item
Station
2
Station
3
Station
4
Material
and/or
labor
Statio
n
1
Material
and/or
labor
Material
and/or
labor
Material
and/or
labor
6-15
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Process Layout
Process Layout - work travels
to dedicated process centers
Milling
Assembly
& Test
Grinding
Drilling Plating
6-16
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Functional Layout
Gear
cutting
Mill Drill
Lathes
Grind
Heat
treat
Assembly
111
333
222
444
222
111
444
111 333
1111 2222
222
3333
111
444
111
6-17
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Basic Layout Formats
• Group Technology Layout
• Cellular Layout
• Fixed Position Layout
– e.g. Shipbuilding
Part Family W Part Family X
Part Family Y Part Family Z
6-18
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Cellular Layouts
• Cellular Manufacturing
– Layout in which machines are grouped into
a cell that can process items that have
similar processing requirements
• Group Technology
– The grouping into part families of items with
similar design or manufacturing
characteristics
6-19
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
A U-Shaped Production Line
1 2 3 4
5
6
78910
In
Out
Workers
6-20
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Cellular Manufacturing Layout
-1111 -1111
222222222 - 2222
Assembly
3333333333 - 3333
44444444444444 - 4444
Lathe
Lathe
Mill
Mill
Mill
Mill
Drill
Drill
Drill
Heat
treat
Heat
treat
Heat
treat
Gear
cut
Gear
cut
Grind
Grind
6-21
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Design Product Layouts: Line Balancing
Line Balancing is the process of assigning
tasks to workstations in such a way that
the workstations have approximately
equal time requirements.
6-22
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Cycle Time
Cycle time is the maximum time
allowed at each workstation to
complete its set of tasks on a unit.
6-23
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Determine Maximum Output
Output capacity =
OT
CT
OT operating time per day
D = Desired output rate
CT = cycle time =
OT
D
6-24
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Determine the Minimum Number
of Workstations Required: Efficiency
N =
(D)( t)
OT
t = sum of task times
6-25
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Precedence Diagram
Precedence diagram: Tool used in line balancing
to display elemental tasks and sequence
requirements
A Simple Precedence
Diagrama b
c d e
0.1 min.
0.7 min.
1.0 min.
0.5 min. 0.2 min.
6-26
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Example 1: Assembly Line Balancing
• Arrange tasks shown in the previous
slide into workstations.
– Use a cycle time of 1.0 minute
– Assign tasks in order of the most number of
followers
6-27
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Solution to Example 1
Work-
Station
Time
Remaining Eligible
Assign
Task
Station
Idle Time
1 1.0
.9
.2
a
c
none
a
c
- .2
2 1.0
0
b
none
b
- 0
3 1.0
.5
.3
d
e
-
d
e
- .3
.5
6-28
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Calculate Percent Idle Time
Percent idle time =
Idle time per cycle
(N)(CT)
6-29
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Line Balancing Rules
• Assign tasks in order of most
following tasks.
• Assign tasks in order of greatest
positional weight.
– Positional weight is the sum of each
task’s time and the times of all
following tasks.
Some Heuristic (intuitive) Rules:
6-30
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Solution to Example 2
Station 1 Station 2 Station 3 Station 4
a b e
f
d
g h
c
6-31
McGraw-Hill/Irwin
Operations Management, Seventh Edition, by William J. Stevenson
Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Process Design and Facility Layout
Parallel Workstations
1 min.2 min.1 min.1 min.
30/hr. 30/hr. 30/hr. 30/hr.
1 min.
1 min.
1 min.1 min.
60/hr.
30/hr. 30/hr.
60/hr.
1 min.
30/hr.
30/hr.
Bottleneck
Parallel Workstations

Mais conteúdo relacionado

Mais procurados

Process And Layout Strategies
Process And Layout StrategiesProcess And Layout Strategies
Process And Layout StrategiesJoanmaines
 
Operations Strategy
Operations StrategyOperations Strategy
Operations StrategyJoanmaines
 
Introduction to Operations Management by Stevenson
Introduction to Operations Management by StevensonIntroduction to Operations Management by Stevenson
Introduction to Operations Management by StevensonWafeeqa Wafiq
 
Operations And Productivity
Operations And ProductivityOperations And Productivity
Operations And ProductivityJoanmaines
 
location strategy, operation management
location strategy, operation managementlocation strategy, operation management
location strategy, operation managementFAST NUCES
 
5.Production Scheduling and Sequencing.pptx
5.Production Scheduling and Sequencing.pptx5.Production Scheduling and Sequencing.pptx
5.Production Scheduling and Sequencing.pptxvirshit
 
Process layout
Process layoutProcess layout
Process layoutno
 
Ch 1 introduction_om
Ch 1 introduction_omCh 1 introduction_om
Ch 1 introduction_omitzmeyash
 
Operations management
Operations managementOperations management
Operations managementSumit Singh
 
Facility layout ppt
Facility layout pptFacility layout ppt
Facility layout pptAnju Rana
 
Operations management location strategies (lecture)
Operations management location strategies  (lecture)Operations management location strategies  (lecture)
Operations management location strategies (lecture)Jun Gonzales
 
operation management chapter 2
operation management chapter 2operation management chapter 2
operation management chapter 2jhoy1221
 
Capacity planning ppt
Capacity planning pptCapacity planning ppt
Capacity planning pptGagan bhati
 
Process selection, design & analysis
Process selection, design & analysisProcess selection, design & analysis
Process selection, design & analysisNoopur Koli
 

Mais procurados (20)

Process And Layout Strategies
Process And Layout StrategiesProcess And Layout Strategies
Process And Layout Strategies
 
Operations Strategy
Operations StrategyOperations Strategy
Operations Strategy
 
Introduction to Operations Management by Stevenson
Introduction to Operations Management by StevensonIntroduction to Operations Management by Stevenson
Introduction to Operations Management by Stevenson
 
Operations And Productivity
Operations And ProductivityOperations And Productivity
Operations And Productivity
 
location strategy, operation management
location strategy, operation managementlocation strategy, operation management
location strategy, operation management
 
Chapter 9 layout strategies
Chapter 9 layout strategiesChapter 9 layout strategies
Chapter 9 layout strategies
 
operations management
operations managementoperations management
operations management
 
5.Production Scheduling and Sequencing.pptx
5.Production Scheduling and Sequencing.pptx5.Production Scheduling and Sequencing.pptx
5.Production Scheduling and Sequencing.pptx
 
Process layout
Process layoutProcess layout
Process layout
 
Ch 1 introduction_om
Ch 1 introduction_omCh 1 introduction_om
Ch 1 introduction_om
 
Operations management
Operations managementOperations management
Operations management
 
Layout strategies
Layout strategiesLayout strategies
Layout strategies
 
Facility layout ppt
Facility layout pptFacility layout ppt
Facility layout ppt
 
Operations Management
Operations ManagementOperations Management
Operations Management
 
CAPACITY PLANNING
CAPACITY PLANNINGCAPACITY PLANNING
CAPACITY PLANNING
 
Operations management location strategies (lecture)
Operations management location strategies  (lecture)Operations management location strategies  (lecture)
Operations management location strategies (lecture)
 
Operation management
Operation managementOperation management
Operation management
 
operation management chapter 2
operation management chapter 2operation management chapter 2
operation management chapter 2
 
Capacity planning ppt
Capacity planning pptCapacity planning ppt
Capacity planning ppt
 
Process selection, design & analysis
Process selection, design & analysisProcess selection, design & analysis
Process selection, design & analysis
 

Destaque

Facility Layout in production management
Facility Layout in production managementFacility Layout in production management
Facility Layout in production managementJoshua Miranda
 
Production and Operations Management- Chapters 1-8
Production and Operations Management- Chapters 1-8Production and Operations Management- Chapters 1-8
Production and Operations Management- Chapters 1-8vc_santos
 
MRP Systems
MRP SystemsMRP Systems
MRP SystemsNsbmUcd
 
Process dsign and facility layout
Process dsign and facility layoutProcess dsign and facility layout
Process dsign and facility layoutNsbmUcd
 
Chapter 1 introduction to production management
Chapter 1  introduction to production managementChapter 1  introduction to production management
Chapter 1 introduction to production managementalpha flores
 
Managing production across supply chain
Managing production across supply chainManaging production across supply chain
Managing production across supply chainSushant Kumar Sinha
 
Production and Operations Management
Production and Operations ManagementProduction and Operations Management
Production and Operations ManagementRoyce G Chua
 
Aggregat planning stevenson
Aggregat planning stevensonAggregat planning stevenson
Aggregat planning stevensonPiyush Vanjani
 
International logistics & global scm
International logistics & global scmInternational logistics & global scm
International logistics & global scmVishal Kaushik
 
Pengenalan kepada autocad
Pengenalan kepada autocadPengenalan kepada autocad
Pengenalan kepada autocadmohdfadil112279
 
Solution to chapter 04: Reliability
Solution to chapter 04: Reliability Solution to chapter 04: Reliability
Solution to chapter 04: Reliability Sazedul Ekab
 
Facility Capacity & Layout Planning
Facility Capacity & Layout PlanningFacility Capacity & Layout Planning
Facility Capacity & Layout PlanningNishant Agrawal
 
Automated Material Handling System
Automated Material Handling SystemAutomated Material Handling System
Automated Material Handling SystemRakesh Raki
 
Industrial Engineering unit 5. Facility Design Notes by badebhau.
Industrial Engineering unit 5. Facility Design Notes by badebhau.Industrial Engineering unit 5. Facility Design Notes by badebhau.
Industrial Engineering unit 5. Facility Design Notes by badebhau.Er. Bade Bhausaheb
 
Bài 7: Luồng công việc – Workflow
Bài 7: Luồng công việc – WorkflowBài 7: Luồng công việc – Workflow
Bài 7: Luồng công việc – WorkflowMasterCode.vn
 
Operations strategy and competitiveness
Operations strategy and competitivenessOperations strategy and competitiveness
Operations strategy and competitivenessArun Kandukuri
 
MRP, MPS, Bill of Material, Numericals
MRP, MPS, Bill of Material, NumericalsMRP, MPS, Bill of Material, Numericals
MRP, MPS, Bill of Material, NumericalsSana Fatima
 

Destaque (20)

Chap003 Forecasting
Chap003    ForecastingChap003    Forecasting
Chap003 Forecasting
 
Facility Layout in production management
Facility Layout in production managementFacility Layout in production management
Facility Layout in production management
 
Production and Operations Management- Chapters 1-8
Production and Operations Management- Chapters 1-8Production and Operations Management- Chapters 1-8
Production and Operations Management- Chapters 1-8
 
MRP Systems
MRP SystemsMRP Systems
MRP Systems
 
Process dsign and facility layout
Process dsign and facility layoutProcess dsign and facility layout
Process dsign and facility layout
 
Chapter 1 introduction to production management
Chapter 1  introduction to production managementChapter 1  introduction to production management
Chapter 1 introduction to production management
 
Managing production across supply chain
Managing production across supply chainManaging production across supply chain
Managing production across supply chain
 
Production and Operations Management
Production and Operations ManagementProduction and Operations Management
Production and Operations Management
 
Aggregat planning stevenson
Aggregat planning stevensonAggregat planning stevenson
Aggregat planning stevenson
 
International logistics & global scm
International logistics & global scmInternational logistics & global scm
International logistics & global scm
 
Pengenalan kepada autocad
Pengenalan kepada autocadPengenalan kepada autocad
Pengenalan kepada autocad
 
Solution to chapter 04: Reliability
Solution to chapter 04: Reliability Solution to chapter 04: Reliability
Solution to chapter 04: Reliability
 
Facility Capacity & Layout Planning
Facility Capacity & Layout PlanningFacility Capacity & Layout Planning
Facility Capacity & Layout Planning
 
Automated Material Handling System
Automated Material Handling SystemAutomated Material Handling System
Automated Material Handling System
 
Industrial Engineering unit 5. Facility Design Notes by badebhau.
Industrial Engineering unit 5. Facility Design Notes by badebhau.Industrial Engineering unit 5. Facility Design Notes by badebhau.
Industrial Engineering unit 5. Facility Design Notes by badebhau.
 
Chain conveyor
Chain conveyorChain conveyor
Chain conveyor
 
Bài 7: Luồng công việc – Workflow
Bài 7: Luồng công việc – WorkflowBài 7: Luồng công việc – Workflow
Bài 7: Luồng công việc – Workflow
 
Operations strategy and competitiveness
Operations strategy and competitivenessOperations strategy and competitiveness
Operations strategy and competitiveness
 
Reverse Logistics
Reverse LogisticsReverse Logistics
Reverse Logistics
 
MRP, MPS, Bill of Material, Numericals
MRP, MPS, Bill of Material, NumericalsMRP, MPS, Bill of Material, Numericals
MRP, MPS, Bill of Material, Numericals
 

Semelhante a S ch6

OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGEOPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGEyosefhadiwibowo
 
Karl Zemlin resume 2017
Karl Zemlin resume 2017Karl Zemlin resume 2017
Karl Zemlin resume 2017Karl Zemlin
 
Craig Smith resume
Craig Smith resumeCraig Smith resume
Craig Smith resumeCraig Smith
 
Airtronics Metal Products Overview - Precision Sheet Metal Manufacturer/Desig...
Airtronics Metal Products Overview - Precision Sheet Metal Manufacturer/Desig...Airtronics Metal Products Overview - Precision Sheet Metal Manufacturer/Desig...
Airtronics Metal Products Overview - Precision Sheet Metal Manufacturer/Desig...guest1f814
 
Krontime overview may2013_en-ali_accio10
Krontime overview may2013_en-ali_accio10Krontime overview may2013_en-ali_accio10
Krontime overview may2013_en-ali_accio10Gokcin
 
A&M Tool-2016-Capabilities
A&M Tool-2016-CapabilitiesA&M Tool-2016-Capabilities
A&M Tool-2016-CapabilitiesAndrew Rogier
 
system analysis and design Chap009
 system analysis and design  Chap009 system analysis and design  Chap009
system analysis and design Chap009Nderitu Muriithi
 
Rick Hatlen Resume Oct 2016 A
Rick Hatlen Resume Oct 2016 ARick Hatlen Resume Oct 2016 A
Rick Hatlen Resume Oct 2016 ARick Hatlen
 
Prince Industries Inc
Prince Industries IncPrince Industries Inc
Prince Industries IncRick
 
Collaborative Discrete Automation Systems Define the Factory of the Future
Collaborative Discrete Automation Systems Define the Factory of the FutureCollaborative Discrete Automation Systems Define the Factory of the Future
Collaborative Discrete Automation Systems Define the Factory of the FutureARC Advisory Group
 

Semelhante a S ch6 (20)

OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGEOPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
 
Precinmac
PrecinmacPrecinmac
Precinmac
 
chap012.ppt
chap012.pptchap012.ppt
chap012.ppt
 
Karl Zemlin resume 2017
Karl Zemlin resume 2017Karl Zemlin resume 2017
Karl Zemlin resume 2017
 
Craig Smith resume
Craig Smith resumeCraig Smith resume
Craig Smith resume
 
Airtronics Metal Products Overview - Precision Sheet Metal Manufacturer/Desig...
Airtronics Metal Products Overview - Precision Sheet Metal Manufacturer/Desig...Airtronics Metal Products Overview - Precision Sheet Metal Manufacturer/Desig...
Airtronics Metal Products Overview - Precision Sheet Metal Manufacturer/Desig...
 
Krontime overview may2013_en-ali_accio10
Krontime overview may2013_en-ali_accio10Krontime overview may2013_en-ali_accio10
Krontime overview may2013_en-ali_accio10
 
jim. resume2015
jim. resume2015jim. resume2015
jim. resume2015
 
A&M Tool-2016-Capabilities
A&M Tool-2016-CapabilitiesA&M Tool-2016-Capabilities
A&M Tool-2016-Capabilities
 
system analysis and design Chap009
 system analysis and design  Chap009 system analysis and design  Chap009
system analysis and design Chap009
 
Process development
Process developmentProcess development
Process development
 
IS-Machinist2
IS-Machinist2IS-Machinist2
IS-Machinist2
 
SMT Sales 2011
SMT Sales 2011SMT Sales 2011
SMT Sales 2011
 
SMT 2011
SMT  2011SMT  2011
SMT 2011
 
SMT 2011
SMT 2011SMT 2011
SMT 2011
 
Rick Hatlen Resume Oct 2016 A
Rick Hatlen Resume Oct 2016 ARick Hatlen Resume Oct 2016 A
Rick Hatlen Resume Oct 2016 A
 
Chap006 (1) (1).ppt
Chap006 (1) (1).pptChap006 (1) (1).ppt
Chap006 (1) (1).ppt
 
Prince Industries Inc
Prince Industries IncPrince Industries Inc
Prince Industries Inc
 
CAD CAM CAE
CAD CAM CAECAD CAM CAE
CAD CAM CAE
 
Collaborative Discrete Automation Systems Define the Factory of the Future
Collaborative Discrete Automation Systems Define the Factory of the FutureCollaborative Discrete Automation Systems Define the Factory of the Future
Collaborative Discrete Automation Systems Define the Factory of the Future
 

Último

Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in PhilippinesDavidSamuel525586
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditNhtLNguyn9
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 

Último (20)

Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in Philippines
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal audit
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 

S ch6

  • 1. 6-1 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Chapter 6 Process Design and Facility Layout
  • 2. 6-2 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Process Selection and System Design Forecasting Product and service design Capacity planning Facilities and Equipment Layout Work design Process selection Technological change
  • 3. 6-3 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Introduction • Outsourcing, trend, reasons • Make or Buy? – Available capacity – Expertise – Quality Consideration – The nature of demand – Cost
  • 4. 6-4 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout • Variety – How much • Flexibility – What degree • Volume – Expected output • The key trade-off Process Selection
  • 5. 6-5 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Process Types • Projects • Job Shops • Batch Processing • Repetitive/Assembly • Continuous Processing
  • 6. 6-6 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Figure 3.6 Product-Process Matrix for Processes (1) (2) (3) (4) (5) One of a kind Low volume, Multiple Few major High volume products, made low products products, high to customer standardization moderate higher standardization, order volume volume commodity products Process Characteristics (1) Complex and highly customized process, unique sequence of tasks (2) Jumbled flows, complex work with many exceptions (3) Disconnected line flows, moderately complex work (4) Connected line, routine work (5) Continuous flows, highly repetitive work LessComplexity,LessDivergence,MoreLineFlows Less Customization and Higher Volume Product Design Continuous process Project process Line process Batch process Job process
  • 7. 6-7 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Product-Process Matrix Flexibility-Quality Dependability-Cost Continuous Flow Assembly Line Batch Job Shop Low Volume One of a Kind Multiple Products, Low Volume Few Major Products, Higher Volume High Volume, High Standard- ization Commercial Printer Heavy Equipment Automobile Assembly Sugar Refinery Flexibility- Quality Dependability Cost
  • 8. 6-8 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout • Automation: Machinery that has sensing and control devices that enables it to operate Automation
  • 9. 6-9 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Automation • Numerically controlled (NC) machines • Robot • Computer-aided design and manufacturing systems (CAD/CAM) • Flexible manufacturing systems • Computer-integrated manufacturing (CIM)
  • 10. 6-10 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout • Layout: the configuration of departments, work centers, and equipment, with particular emphasis on movement of work (customers or materials) through the system Layout
  • 11. 6-11 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout • Requires substantial investments of money and effort • Involves long-term commitments • Has significant impact on cost and efficiency of short-term operations Importance of Layout Decisions
  • 12. 6-12 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Basic Layout Types • Product Layouts • Process Layouts • Fixed-Position • Combination Layouts
  • 13. 6-13 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Basic Layout Types • Product Layout – Layout that uses standardized processing operations to achieve smooth, rapid, high- volume flow – Group equipments according to the sequential steps of operations of a specific product • Process Layout – Layout that can handle varied processing requirements – Group equipments according to their functions
  • 14. 6-14 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout A Flow Line for Production or Service Flow Shop or Assembly Line Work Flow Raw materials or customer Finished item Station 2 Station 3 Station 4 Material and/or labor Statio n 1 Material and/or labor Material and/or labor Material and/or labor
  • 15. 6-15 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Process Layout Process Layout - work travels to dedicated process centers Milling Assembly & Test Grinding Drilling Plating
  • 16. 6-16 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Functional Layout Gear cutting Mill Drill Lathes Grind Heat treat Assembly 111 333 222 444 222 111 444 111 333 1111 2222 222 3333 111 444 111
  • 17. 6-17 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Basic Layout Formats • Group Technology Layout • Cellular Layout • Fixed Position Layout – e.g. Shipbuilding Part Family W Part Family X Part Family Y Part Family Z
  • 18. 6-18 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Cellular Layouts • Cellular Manufacturing – Layout in which machines are grouped into a cell that can process items that have similar processing requirements • Group Technology – The grouping into part families of items with similar design or manufacturing characteristics
  • 19. 6-19 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout A U-Shaped Production Line 1 2 3 4 5 6 78910 In Out Workers
  • 20. 6-20 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Cellular Manufacturing Layout -1111 -1111 222222222 - 2222 Assembly 3333333333 - 3333 44444444444444 - 4444 Lathe Lathe Mill Mill Mill Mill Drill Drill Drill Heat treat Heat treat Heat treat Gear cut Gear cut Grind Grind
  • 21. 6-21 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Design Product Layouts: Line Balancing Line Balancing is the process of assigning tasks to workstations in such a way that the workstations have approximately equal time requirements.
  • 22. 6-22 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Cycle Time Cycle time is the maximum time allowed at each workstation to complete its set of tasks on a unit.
  • 23. 6-23 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Determine Maximum Output Output capacity = OT CT OT operating time per day D = Desired output rate CT = cycle time = OT D
  • 24. 6-24 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Determine the Minimum Number of Workstations Required: Efficiency N = (D)( t) OT t = sum of task times
  • 25. 6-25 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Precedence Diagram Precedence diagram: Tool used in line balancing to display elemental tasks and sequence requirements A Simple Precedence Diagrama b c d e 0.1 min. 0.7 min. 1.0 min. 0.5 min. 0.2 min.
  • 26. 6-26 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Example 1: Assembly Line Balancing • Arrange tasks shown in the previous slide into workstations. – Use a cycle time of 1.0 minute – Assign tasks in order of the most number of followers
  • 27. 6-27 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Solution to Example 1 Work- Station Time Remaining Eligible Assign Task Station Idle Time 1 1.0 .9 .2 a c none a c - .2 2 1.0 0 b none b - 0 3 1.0 .5 .3 d e - d e - .3 .5
  • 28. 6-28 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Calculate Percent Idle Time Percent idle time = Idle time per cycle (N)(CT)
  • 29. 6-29 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Line Balancing Rules • Assign tasks in order of most following tasks. • Assign tasks in order of greatest positional weight. – Positional weight is the sum of each task’s time and the times of all following tasks. Some Heuristic (intuitive) Rules:
  • 30. 6-30 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Solution to Example 2 Station 1 Station 2 Station 3 Station 4 a b e f d g h c
  • 31. 6-31 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved. Process Design and Facility Layout Parallel Workstations 1 min.2 min.1 min.1 min. 30/hr. 30/hr. 30/hr. 30/hr. 1 min. 1 min. 1 min.1 min. 60/hr. 30/hr. 30/hr. 60/hr. 1 min. 30/hr. 30/hr. Bottleneck Parallel Workstations