SlideShare a Scribd company logo
1 of 4
Download to read offline
Work on the Goethals Bridge
Replacement Project is 53 percent
complete, with $497,459,365 of
construction in place, according to
Chris Jenkins, Construction Quality
Assurance Director for NYNJ Link
Developer LLC, the public-private
partnership overseeing the new
Goethals Bridge construction.
The entire eastbound approach
over the New Jersey Turnpike of the
original Goethals Bridge has been
demolished. Drilled shafts on the
New Jersey Turnpike approach to
the bridge are under construction,
with five shafts completed and
bridge column work begun. For the
New Jersey approach, bridge girder
installation that began in January
continues. In April, construction began
on the bridge deck and will continue
through the summer. The identical process is in progress on the New York approach, where girder installation also began
in January, and installation of the New York approach bridge deck began in April, and will continue through the summer. A
total of 56 eastbound, pre-stressed, precast approach girders have been erected, and approximately 150 precast, pre-stressed
panels constructed atop the girders. New Jersey and New York eastbound towers have risen up to Lift 12 (just below the cable
anchor boxes) and the corresponding westbound towers are up to Lift 8. Cable installation is anticipated to begin in May.
“It’s very rewarding to see our hard work materialize as the new bridge rises around us. Throughout the next several months,
additional elements of the bridge will be set in place, promising an exciting spring and summer,” said Lou Franco, Senior
Project Manager with The Port Authority of New York and New Jersey.
The New Goethals
Bridge Reaches
Skyward
Installation of Edge Girder on the New York Eastbound Tower
The edge girder is lifted and mated with the tower. The edge girders support the pier table
which will allow for the commencement of the erection of the cable-stayed elements of
the bridge.
Bridge
Update
Progress and
Photos
Faces of
the GBRP
Anthony Piechnik,
HNTB Corporation
Construction
Futures Program
A Kiewit
CommunityProgram
N E W S L E T T E R
VOLUME
Q2 2016
Progress on the Bridge
A view from New York Eastbound/Westbound Pier 13
Reinforcement steel and concrete will be installed between the
two girders, which connects the spans on either side of the pier.
A Close Look at New York Eastbound Span 14
Four installed girders with intermediate steel diaphragms
between each girder, which provide stability during erection.
Progress on the New Jersey Pier 1 Backspan
This view of the New Jersey eastbound tower on lift 12 is just be-
low where the bridge cables will be connected. Also shown is the
backspan falsework which supports the structural steel erection.
The New Jersey Approach Girders
This view shows three spans of girders after installation. The
next step in the construction process is to install precast panels
on top of the girders, which will allow for the pouring of the
cast-in-place deck.
Among the many components that keep The Goethals
Bridge Replacement Project (GBRP) running smoothly
is the Technical Oversight of Design and Construction
for The Port Authority of New York and New Jersey.
HNTB Corporation is the Technical Advisor to the Port
Authority of New York and New Jersey. HNTB Project
Manager and Associate Vice President Anthony (AJ)
Piechnik serves as the Technical Manager, responsible
for overseeing the technical components of the design
and construction on behalf of the Authority.
A New Jersey native and licensed Professional
Engineer, AJ received a Bachelor of Science in Physics
from Wake Forest University. Fascinated by bridges,
AJ continued his education and obtained a Master
of Science in Civil Engineering from the University
of Virginia. AJ brings significant bridge experience
to the region’s first, Public-Private Partnership (P3)
transportation infrastructure dual-span cable-stay
bridge, having previously worked on major bridge
projects such as the Central Artery Tunnel Project’s
Zakim Bridge in Boston, MA, and the 6th Street cable-
stay bridges in Milwaukee, WS.
AJ and his team have worked with Port Authority Program Director Jim Blackmore to develop the GBRP from early
concepts and environmental studies through the development of contract and technical requirements for the P3
procurement, and the current oversight of the new bridge’s design and construction phase.
Day-to-day, AJ works closely with developer NYNJ Link,
lead contractor Kiewit-Weeks-Massman, and designer
of record Parsons Corporation to ensure all technical
requirements and job specifications are fulfilled. This
includes oversight of design, construction, and contract
compliance.
What does he like best about working on the GBRP
project? “Working with an elite Authority team, a
leading contractor, designer and P3 Developer; We get
to solve and build what seems like the impossible to
most, while utilizing a new project delivery methodology
(P3) for infrastructure projects in the northeast.”
Faces of the Goethals Bridge Replacement Project
Anthony Piechnik, PE, AVP for HNTB Corporation
Kiewit, the lead contractor of the Goethals Bridge
Replacement Project’s (GBRP) joint venture companies, is
laying the groundwork for its third Building Construction
Futures Program. According to Anne Caprari, Kiewit
Compliance Manager and Equal Employment Opportunity
Officer, this daylong event brings together participants
from local community organizations such as Nontraditional
Employment for Women, a nonprofit group based out
of Manhattan which trains women to work in the skilled
construction trades, and YouthBuild Elizabeth, a nonprofit
helping low-income young people to learn construction skills.
The first two Building Construction Futures (held in August
and November 2015) organized daylong programs. Anne
Caprari delivered an overview of the Replacement Project
which included information about the parent companies
participating in the joint venture, the project itself, and the
various trades used on the Project. Some lead Foremen on
the job also came and spoke about their trades, expecta-
tions for work in the field, and answered any questions by
the participants.
“We had some of the craft Foremen come into the classroom
and speak to the attendees,” Anne noted, including Laborer
Paul Daly and Carpenter John Paradis in Construction. Each
discussed their specific trade, and what their expectations
were for the workers on their teams before we opened the
floor to questions.”
In August, attendees toured the site and participated in a
series of mock safety scenario drills. “We divided the group
into teams and brought out boxes filled with personal
protective equipment (PPE),” Anne said. “Each group was
given safety scenarios to review, after which they had to
identify the PPE appropriate to the scenario and dress one of
their members correctly. The first to dress a team member
in the correct PPE won. November’s safety activity required
the group to dress a team member in full fall protection gear,
including safety harnesses.”
It was more than fun for the attendees and the GBRP team,
Anne continued. “In many cases, this was the first time these
young people have had to set foot on a construction site and
actually picture themselves working here.”
The GBRP is Building
Construction Futures
Project Safety Manager Dan Hollis
teaches members of YouthBuild
Elizabeth to properly implement
safety harnesses for fall protection.
Contact Information
www.panynj.gov/GoethalsBridgeReplacement Follow us on Twitter @PANYNJ Email GoethalsBridge@panynj.gov
Get visual updates through our webcam: www.panynj.gov/GoethalsBridgeReplacement#webcam

More Related Content

Viewers also liked

Calendario mensal marzo
Calendario mensal marzoCalendario mensal marzo
Calendario mensal marzoheidy-o
 
Jojojo
JojojoJojojo
JojojoNoneee
 
新聞簡報
新聞簡報新聞簡報
新聞簡報a7212618
 
Boleta solicitud de levantamiento de requisitos
Boleta solicitud de levantamiento de requisitosBoleta solicitud de levantamiento de requisitos
Boleta solicitud de levantamiento de requisitosTATIANA VILLALOBOS
 
Gr+ífico diario del ibex 35 para el 09 07 2013
Gr+ífico diario del ibex 35 para el 09 07 2013Gr+ífico diario del ibex 35 para el 09 07 2013
Gr+ífico diario del ibex 35 para el 09 07 2013Experiencia Trading
 
Grafico diario del s&p 500 para el 08 07 2013
Grafico diario del s&p 500 para el 08 07 2013Grafico diario del s&p 500 para el 08 07 2013
Grafico diario del s&p 500 para el 08 07 2013Experiencia Trading
 
Systems approaches a look at the organizational system of world wrestling en...
Systems approaches  a look at the organizational system of world wrestling en...Systems approaches  a look at the organizational system of world wrestling en...
Systems approaches a look at the organizational system of world wrestling en...dkirn95
 
Sabbath school lesson 3, 4 th quarter of 2015
Sabbath school lesson 3, 4 th quarter of 2015Sabbath school lesson 3, 4 th quarter of 2015
Sabbath school lesson 3, 4 th quarter of 2015David Syahputra
 
Sabbath school lesson 1, 4th quarter of 2015
Sabbath school lesson 1, 4th quarter of 2015Sabbath school lesson 1, 4th quarter of 2015
Sabbath school lesson 1, 4th quarter of 2015David Syahputra
 

Viewers also liked (12)

Calendario mensal marzo
Calendario mensal marzoCalendario mensal marzo
Calendario mensal marzo
 
Jojojo
JojojoJojojo
Jojojo
 
123
123123
123
 
新聞簡報
新聞簡報新聞簡報
新聞簡報
 
COSMOVISIONES: 18 cosmovisiones
COSMOVISIONES: 18 cosmovisionesCOSMOVISIONES: 18 cosmovisiones
COSMOVISIONES: 18 cosmovisiones
 
La Verónica
La VerónicaLa Verónica
La Verónica
 
Boleta solicitud de levantamiento de requisitos
Boleta solicitud de levantamiento de requisitosBoleta solicitud de levantamiento de requisitos
Boleta solicitud de levantamiento de requisitos
 
Gr+ífico diario del ibex 35 para el 09 07 2013
Gr+ífico diario del ibex 35 para el 09 07 2013Gr+ífico diario del ibex 35 para el 09 07 2013
Gr+ífico diario del ibex 35 para el 09 07 2013
 
Grafico diario del s&p 500 para el 08 07 2013
Grafico diario del s&p 500 para el 08 07 2013Grafico diario del s&p 500 para el 08 07 2013
Grafico diario del s&p 500 para el 08 07 2013
 
Systems approaches a look at the organizational system of world wrestling en...
Systems approaches  a look at the organizational system of world wrestling en...Systems approaches  a look at the organizational system of world wrestling en...
Systems approaches a look at the organizational system of world wrestling en...
 
Sabbath school lesson 3, 4 th quarter of 2015
Sabbath school lesson 3, 4 th quarter of 2015Sabbath school lesson 3, 4 th quarter of 2015
Sabbath school lesson 3, 4 th quarter of 2015
 
Sabbath school lesson 1, 4th quarter of 2015
Sabbath school lesson 1, 4th quarter of 2015Sabbath school lesson 1, 4th quarter of 2015
Sabbath school lesson 1, 4th quarter of 2015
 

Similar to GoethalsNewsletter_Q2_2016_Eg

GoethalsNewsletter_Q1_2016_Eg
GoethalsNewsletter_Q1_2016_EgGoethalsNewsletter_Q1_2016_Eg
GoethalsNewsletter_Q1_2016_EgAnne Caprari
 
2014 NAT Conference Paper No 26 Manuscript_Safety NAT 1-15-14 (2)
2014 NAT Conference Paper No  26 Manuscript_Safety NAT  1-15-14 (2)2014 NAT Conference Paper No  26 Manuscript_Safety NAT  1-15-14 (2)
2014 NAT Conference Paper No 26 Manuscript_Safety NAT 1-15-14 (2)Michael Vigna, CSP
 
Building structure project 1 report
Building structure project 1 reportBuilding structure project 1 report
Building structure project 1 reportAdelinetingg
 
Frank s. chuang performed structural design of t. f. green airport approach s...
Frank s. chuang performed structural design of t. f. green airport approach s...Frank s. chuang performed structural design of t. f. green airport approach s...
Frank s. chuang performed structural design of t. f. green airport approach s...frankchuang
 
Alexander Bridge Rehab ENR 2.4.13 issue[1]
Alexander Bridge Rehab ENR 2.4.13 issue[1]Alexander Bridge Rehab ENR 2.4.13 issue[1]
Alexander Bridge Rehab ENR 2.4.13 issue[1]Manuel J. Silva, P.E.
 
EAE Newsletter - Nov - Issue #6
EAE Newsletter - Nov - Issue #6EAE Newsletter - Nov - Issue #6
EAE Newsletter - Nov - Issue #6Darcy Pearson
 
Frank s. chuang designed retaining walls along the ramps
Frank s. chuang designed retaining walls along the rampsFrank s. chuang designed retaining walls along the ramps
Frank s. chuang designed retaining walls along the rampsfrankchuang
 
A Tunnel Under Geylang River, The Story of Geylang River Diversion
A Tunnel Under Geylang River, The Story of Geylang River DiversionA Tunnel Under Geylang River, The Story of Geylang River Diversion
A Tunnel Under Geylang River, The Story of Geylang River DiversionSingapore Power Ltd
 
summer-quarterly-magazine
summer-quarterly-magazinesummer-quarterly-magazine
summer-quarterly-magazineWilson, Todd F.
 
BHI_Carolinas Region_Newsletter Summer 2016
BHI_Carolinas Region_Newsletter Summer 2016BHI_Carolinas Region_Newsletter Summer 2016
BHI_Carolinas Region_Newsletter Summer 2016Megan Sebring
 
JOINT TRANSPORTATION RESEARCH PROGRAM INDIANA DEPARTME
JOINT TRANSPORTATION RESEARCH PROGRAM INDIANA DEPARTMEJOINT TRANSPORTATION RESEARCH PROGRAM INDIANA DEPARTME
JOINT TRANSPORTATION RESEARCH PROGRAM INDIANA DEPARTMETatianaMajor22
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
Structural Synergy presentation
Structural Synergy presentationStructural Synergy presentation
Structural Synergy presentationReza Sarkhosh
 
Joseph J. Raftery - Civil Engineer, P.E.
Joseph J. Raftery - Civil Engineer, P.E.Joseph J. Raftery - Civil Engineer, P.E.
Joseph J. Raftery - Civil Engineer, P.E.Joseph Raftery
 

Similar to GoethalsNewsletter_Q2_2016_Eg (20)

GoethalsNewsletter_Q1_2016_Eg
GoethalsNewsletter_Q1_2016_EgGoethalsNewsletter_Q1_2016_Eg
GoethalsNewsletter_Q1_2016_Eg
 
2014 NAT Conference Paper No 26 Manuscript_Safety NAT 1-15-14 (2)
2014 NAT Conference Paper No  26 Manuscript_Safety NAT  1-15-14 (2)2014 NAT Conference Paper No  26 Manuscript_Safety NAT  1-15-14 (2)
2014 NAT Conference Paper No 26 Manuscript_Safety NAT 1-15-14 (2)
 
Building structure project 1 report
Building structure project 1 reportBuilding structure project 1 report
Building structure project 1 report
 
Frank s. chuang performed structural design of t. f. green airport approach s...
Frank s. chuang performed structural design of t. f. green airport approach s...Frank s. chuang performed structural design of t. f. green airport approach s...
Frank s. chuang performed structural design of t. f. green airport approach s...
 
Winter 2012 Newsletter
Winter 2012 NewsletterWinter 2012 Newsletter
Winter 2012 Newsletter
 
Alexander Bridge Rehab ENR 2.4.13 issue[1]
Alexander Bridge Rehab ENR 2.4.13 issue[1]Alexander Bridge Rehab ENR 2.4.13 issue[1]
Alexander Bridge Rehab ENR 2.4.13 issue[1]
 
EAE Newsletter - Nov - Issue #6
EAE Newsletter - Nov - Issue #6EAE Newsletter - Nov - Issue #6
EAE Newsletter - Nov - Issue #6
 
World bank project
World bank projectWorld bank project
World bank project
 
RailWorks-Today-April-2016-L
RailWorks-Today-April-2016-LRailWorks-Today-April-2016-L
RailWorks-Today-April-2016-L
 
Frank s. chuang designed retaining walls along the ramps
Frank s. chuang designed retaining walls along the rampsFrank s. chuang designed retaining walls along the ramps
Frank s. chuang designed retaining walls along the ramps
 
Final_Capstone_2016
Final_Capstone_2016Final_Capstone_2016
Final_Capstone_2016
 
WALID_TANBEDAWY_2016 R Dom Comp
WALID_TANBEDAWY_2016 R Dom CompWALID_TANBEDAWY_2016 R Dom Comp
WALID_TANBEDAWY_2016 R Dom Comp
 
A Tunnel Under Geylang River, The Story of Geylang River Diversion
A Tunnel Under Geylang River, The Story of Geylang River DiversionA Tunnel Under Geylang River, The Story of Geylang River Diversion
A Tunnel Under Geylang River, The Story of Geylang River Diversion
 
summer-quarterly-magazine
summer-quarterly-magazinesummer-quarterly-magazine
summer-quarterly-magazine
 
BHI_Carolinas Region_Newsletter Summer 2016
BHI_Carolinas Region_Newsletter Summer 2016BHI_Carolinas Region_Newsletter Summer 2016
BHI_Carolinas Region_Newsletter Summer 2016
 
JOINT TRANSPORTATION RESEARCH PROGRAM INDIANA DEPARTME
JOINT TRANSPORTATION RESEARCH PROGRAM INDIANA DEPARTMEJOINT TRANSPORTATION RESEARCH PROGRAM INDIANA DEPARTME
JOINT TRANSPORTATION RESEARCH PROGRAM INDIANA DEPARTME
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
GSG Project Experience
GSG Project ExperienceGSG Project Experience
GSG Project Experience
 
Structural Synergy presentation
Structural Synergy presentationStructural Synergy presentation
Structural Synergy presentation
 
Joseph J. Raftery - Civil Engineer, P.E.
Joseph J. Raftery - Civil Engineer, P.E.Joseph J. Raftery - Civil Engineer, P.E.
Joseph J. Raftery - Civil Engineer, P.E.
 

GoethalsNewsletter_Q2_2016_Eg

  • 1. Work on the Goethals Bridge Replacement Project is 53 percent complete, with $497,459,365 of construction in place, according to Chris Jenkins, Construction Quality Assurance Director for NYNJ Link Developer LLC, the public-private partnership overseeing the new Goethals Bridge construction. The entire eastbound approach over the New Jersey Turnpike of the original Goethals Bridge has been demolished. Drilled shafts on the New Jersey Turnpike approach to the bridge are under construction, with five shafts completed and bridge column work begun. For the New Jersey approach, bridge girder installation that began in January continues. In April, construction began on the bridge deck and will continue through the summer. The identical process is in progress on the New York approach, where girder installation also began in January, and installation of the New York approach bridge deck began in April, and will continue through the summer. A total of 56 eastbound, pre-stressed, precast approach girders have been erected, and approximately 150 precast, pre-stressed panels constructed atop the girders. New Jersey and New York eastbound towers have risen up to Lift 12 (just below the cable anchor boxes) and the corresponding westbound towers are up to Lift 8. Cable installation is anticipated to begin in May. “It’s very rewarding to see our hard work materialize as the new bridge rises around us. Throughout the next several months, additional elements of the bridge will be set in place, promising an exciting spring and summer,” said Lou Franco, Senior Project Manager with The Port Authority of New York and New Jersey. The New Goethals Bridge Reaches Skyward Installation of Edge Girder on the New York Eastbound Tower The edge girder is lifted and mated with the tower. The edge girders support the pier table which will allow for the commencement of the erection of the cable-stayed elements of the bridge. Bridge Update Progress and Photos Faces of the GBRP Anthony Piechnik, HNTB Corporation Construction Futures Program A Kiewit CommunityProgram N E W S L E T T E R VOLUME Q2 2016
  • 2. Progress on the Bridge A view from New York Eastbound/Westbound Pier 13 Reinforcement steel and concrete will be installed between the two girders, which connects the spans on either side of the pier. A Close Look at New York Eastbound Span 14 Four installed girders with intermediate steel diaphragms between each girder, which provide stability during erection. Progress on the New Jersey Pier 1 Backspan This view of the New Jersey eastbound tower on lift 12 is just be- low where the bridge cables will be connected. Also shown is the backspan falsework which supports the structural steel erection. The New Jersey Approach Girders This view shows three spans of girders after installation. The next step in the construction process is to install precast panels on top of the girders, which will allow for the pouring of the cast-in-place deck.
  • 3. Among the many components that keep The Goethals Bridge Replacement Project (GBRP) running smoothly is the Technical Oversight of Design and Construction for The Port Authority of New York and New Jersey. HNTB Corporation is the Technical Advisor to the Port Authority of New York and New Jersey. HNTB Project Manager and Associate Vice President Anthony (AJ) Piechnik serves as the Technical Manager, responsible for overseeing the technical components of the design and construction on behalf of the Authority. A New Jersey native and licensed Professional Engineer, AJ received a Bachelor of Science in Physics from Wake Forest University. Fascinated by bridges, AJ continued his education and obtained a Master of Science in Civil Engineering from the University of Virginia. AJ brings significant bridge experience to the region’s first, Public-Private Partnership (P3) transportation infrastructure dual-span cable-stay bridge, having previously worked on major bridge projects such as the Central Artery Tunnel Project’s Zakim Bridge in Boston, MA, and the 6th Street cable- stay bridges in Milwaukee, WS. AJ and his team have worked with Port Authority Program Director Jim Blackmore to develop the GBRP from early concepts and environmental studies through the development of contract and technical requirements for the P3 procurement, and the current oversight of the new bridge’s design and construction phase. Day-to-day, AJ works closely with developer NYNJ Link, lead contractor Kiewit-Weeks-Massman, and designer of record Parsons Corporation to ensure all technical requirements and job specifications are fulfilled. This includes oversight of design, construction, and contract compliance. What does he like best about working on the GBRP project? “Working with an elite Authority team, a leading contractor, designer and P3 Developer; We get to solve and build what seems like the impossible to most, while utilizing a new project delivery methodology (P3) for infrastructure projects in the northeast.” Faces of the Goethals Bridge Replacement Project Anthony Piechnik, PE, AVP for HNTB Corporation
  • 4. Kiewit, the lead contractor of the Goethals Bridge Replacement Project’s (GBRP) joint venture companies, is laying the groundwork for its third Building Construction Futures Program. According to Anne Caprari, Kiewit Compliance Manager and Equal Employment Opportunity Officer, this daylong event brings together participants from local community organizations such as Nontraditional Employment for Women, a nonprofit group based out of Manhattan which trains women to work in the skilled construction trades, and YouthBuild Elizabeth, a nonprofit helping low-income young people to learn construction skills. The first two Building Construction Futures (held in August and November 2015) organized daylong programs. Anne Caprari delivered an overview of the Replacement Project which included information about the parent companies participating in the joint venture, the project itself, and the various trades used on the Project. Some lead Foremen on the job also came and spoke about their trades, expecta- tions for work in the field, and answered any questions by the participants. “We had some of the craft Foremen come into the classroom and speak to the attendees,” Anne noted, including Laborer Paul Daly and Carpenter John Paradis in Construction. Each discussed their specific trade, and what their expectations were for the workers on their teams before we opened the floor to questions.” In August, attendees toured the site and participated in a series of mock safety scenario drills. “We divided the group into teams and brought out boxes filled with personal protective equipment (PPE),” Anne said. “Each group was given safety scenarios to review, after which they had to identify the PPE appropriate to the scenario and dress one of their members correctly. The first to dress a team member in the correct PPE won. November’s safety activity required the group to dress a team member in full fall protection gear, including safety harnesses.” It was more than fun for the attendees and the GBRP team, Anne continued. “In many cases, this was the first time these young people have had to set foot on a construction site and actually picture themselves working here.” The GBRP is Building Construction Futures Project Safety Manager Dan Hollis teaches members of YouthBuild Elizabeth to properly implement safety harnesses for fall protection. Contact Information www.panynj.gov/GoethalsBridgeReplacement Follow us on Twitter @PANYNJ Email GoethalsBridge@panynj.gov Get visual updates through our webcam: www.panynj.gov/GoethalsBridgeReplacement#webcam