SlideShare uma empresa Scribd logo
1 de 16
Baixar para ler offline
Understanding
Well Construction and
Surface Footprint
Well Construction Timeline
Well Site Planning & Preparation

Stage 1: Planning and Preparation
•	 Acquire Surface Lease
Agreement
•	 Determination of multi-well pad
or single well pad requirements
•	 Inform stakeholders of the
proposed well construction
•	 Evaluation of sour gas
probability; this will influence
equipment location, etc.
•	 Acquire Well license(s)
•	 Obtain Operation(s) permits
•	 Site Excavation and Preparation
•	 The preparation of the location
would include the drilling of
initial “rat hole/mouse hole” and
placement of conductor string/
pipe
•	 Identify safety procedures,
environmental and regulatory
requirements
•	 Outline the emergency response
plans/procedures

Drilling

Stage 2: Drilling
•	 Drilling rig and equipment
mobilization (if not used for
Surface Hole drilling)
•	 Drilling fluids/mud – testing and
recycling
•	 Blow Out Preventer (BOP)
installation
•	 Surface, and  intermediate (in
some cases) casing cemented
into the wellbore
•	 Drill cutting samples taken and
analyzed (ongoing throughout
the drilling process)
•	 Wellbore drilled to total
depth(vertical, directional or
horizontal)
•	 Potential reservoir(s) identified
and evaluated using geophysical
logging techniques

Most stages of well construction include stakeholder dialogue. Consultation
with stakeholders is the responsibility of the individual project proponent.
2
Stage 3: Casing and Cement
•	 Production casing
lowered into the well
and cemented into place
•	 Diagnostic tools are
utilized to ensure
wellbore integrity

Completion & Stimulation

Stage 4: Completion & Stimulation
•	 Drilling rig is moved offsite and
permanent wellhead installed
•	 Stimulation equipment is moved
into place
•	 Reservoir horizons are
perforated and then stimulated
•	 Stimulation equipment is moved
offsite
•	 Producing zones are tested
•	 With the drilling and completion
equipment demobilized, the
surface footprint is dramatically
reduced.

Site Maintenance

After casing, cementing  and well
stimulation activities are completed,
and assuming the well is successful,
there will be additional construction
activity on site to install surface
facilities if required, tie the well
into the pipeline infrastructure, and
contour and reclaim part of the lease
site.

This information booklet discusses well construction practices only. For more information about
the completions process, including Hydraulic Fracturing or other stimulation techniques, please
reference Understanding Hydraulic Fracturing or Understanding Water and Unconventional Resources
at www.csur.com
3

Well Construction Timeline

Casing & Cement
Well Site Planning & Preparation
Single vs. Multi-well pad
A standard single well lease site for conventional
oil or gas will typically affect a surface area
measuring 100 metres by 100 metres. The
lease site will typically hold the drilling rig and
additional equipment along with supervisory
accommodation and material storage. If multiple
wells from a single pad are planned, the surface
area of the lease site would be larger; in some
cases as much as double the size. (100 metres by
200 metres.) While a multi-well pad site will have a
larger surface area, the cumulative surface impact
of the total number of wells drilled in the project
area will be  smaller. Pad sites allow multiple
wells to be drilled from one surface lease, thereby
reducing the total surface area required for oil and  
gas development. Once drilling is completed and
the well(s) is/are connected/tied-in to the pipeline,
a portion of the lease area can be reclaimed to
minimize surface disturbance.
Surface Lease Site Agreement
A surface lease site agreement grants a company
access to drill a well(s) on land that is held either
privately, by the crown or by a  First Nation. The
agreement also specifies any conditions relating
to the commitments and responsibilities of both
the company and the landowner, including the
payment of compensation by the company to the
landowner.

License & Permit
Federal and/or Provincial and Municipal
licenses and permits are required for lease site
construction; project specific requirements will
vary depending on the location of the well.
Excavation & Leveling
To prepare for initial drilling, the lease site is
leveled, if necessary, with a bulldozer and/or
grader, with careful consideration given to buried
pipelines and utilities, as well as proximity to
surface water features. The scale and duration of
lease site preparation is site-specific. On some
drilling sites, a cellar may be excavated. This is
where the main borehole is to be drilled. A reserve
pit and settling pits may be excavated and are
used for water or drilling fluid (mud) discharges.
Often the soil layers are separated for better soil
conservation. Upon completion of the drilling, the
soils can then be restored to their original location.

Excavated lease site

4
Safety Procedures & Emergency Response Plans
All drilling sites are typically classified according
to areas of potential and/or actual exposure to
Hydrogen Sulfide (H2S).   H2S is an extremely toxic
and poisonous gas. Employers will take special
precautions when choosing equipment. Well site
employees are trained to respond accordingly should
they encounter H2S. Under these circumstances,
all employees are required to wear specially

approved masks and air supply equipment. The
recommendations and employee instruction will vary
depending on the type of area, as will the emergency
response plans (ERPs) that are in place
Environmental and Regulatory Considerations
Provincial and federal regulations, which govern
the oil and gas industry, have been in place for
many years. They have been established to ensure
that both the public and the environment are
protected throughout exploration, development and
production of hydrocarbon resources. Regulations are
also continually reviewed and revised, as required, in
response to advancements in industry technologies
and the techniques employed to extract the resource.
The fundamental regulatory basics of surface
and groundwater protection, wellbore integrity,
lease construction, for example, apply to all
types of hydrocarbon developments; including
unconventional resources. Similarly, the use of
water for drilling and completion activities require
approvals or permits from appropriate authorities.
Prior to acquisition of the surface lease site, a number
of different steps are required. Requirements will vary
depending on the location of the proposed development
and jurisdictional prerequisites.
5

Well Site Planning & Preparation

Drilling of the “Surface Hole” , etc.
As part of any oil or gas well, a conductor hole
and surface hole are required as part of the entire
wellbore. Commonly, a rathole and/or a mousehole
are drilled prior to the actual drilling of the well to
reservoir depth. A conductor hole, also referred to
as a “starter hole” is a large diameter hole, lined with
pipe which varies in depth, and is used to house the
BOP (Blow Out Preventer). A rathole is a hole lying
below the rig floor, 30 to 35 feet deep, lined with
casing into which the kelly is placed when hoisting
operations are in progress. A mousehole is a shallow
bore hole under the rig floor, usually lined with pipe,
into which joints of drill pipe are temporarily placed
during drilling operations. These are either done by
the portable rig that drills the conductor hole, or
can be done by the primary rig after rigging-up. The
surface hole is drilled and cased to isolate potential
shallow groundwater aquifers from the wellbore.
Drilling
Equipment Assembly and Placement
A site, and its access road, must accommodate a large number of
temporary and semi-permanent structures and tanks, all brought
in by truck. At a newly-prepared drill site, the stability of the well
pad is necessary to support the drilling rig and auxiliary equipment
required onsite. In some localities where the ground is unstable rig
mats are commonly used.  After the well pad is properly prepared
the drilling rig is then unloaded and assembled.
There are many rig designs, and this booklet does not cover each
type individually.  During assembly of the rig, some equipment may
be handled and set with crane, rig up trucks, or forklift, depending
on the size of the rig.
The substructure is assembled, pinned together, leveled, and tied
into other rig components. Once the substructure is set in place,
installing the power system and raising the derrick begins. Most
drilling rigs are powered by electricity that is delivered by onsite
diesel powered generators.
While one crew finishes preparing the rig floor, another crew might
be rigging up the circulating system. The mud tanks and mud
pumps are set into the predetermined location.
Once all additional drilling and auxiliary equipment are set into
place a final inspection can be done. The entire process of riggingup can take one or two days. Where multiple wells are drilled from
a single pad, commonly the drilling rig will have the ability to
move to the next location on the lease with minimal disassembly/
reassembly.
6

Source: Shale Exploration
Drilling boreholes deep into the ground
and preparing them to produce oil and
gas is a highly technical and specialized
process. Throughout the operation,
custom-designed fluids fulfill many
different roles. While drilling, these include:
lubricating the drill bit; circulating
drilled-up rock out of the hole; containing
formation fluids within the hole; and
facilitating operation of sophisticated
formation evaluation tools. Fluids may
be water-based, oil-based, or synthetic.
Step 1
Drill vertically until the wellbore
reaches a point above the
targeted reservoir.
Step 2
“Kick off” and begin to drill at an
increasing angle until the wellbore
runs horizontally through the
targeted reservoir.

Vertical vs. Horizontal
Although historically oil and gas wells have been drilled
vertically, new technologies have made it possible for
wells to be drilled horizontally. The purpose of drilling
a horizontal well is to increase amount of reservoir rock
that is intersected from the wellbore. Horizontal drilling
first entails drilling a vertical well to a predetermined
depth above the reservoir. The well is then drilled at an
increasing angle until it intersects the reservoir interval
in a horizontal plane. Once horizontal, the well is then
drilled to a selected length, which could extend to as
much as 3500m. This portion of the well, called the
horizontal leg, allows significantly increased contact of
the wellbore with the reservoir compared to a vertical
well. Upon completion of drilling, production casing
is commonly placed into the wellbore. A perforating
gun is lowered into the
wellbore and placed
in a selected interval
within the horizontal
leg. It is then activated
to create a series of
holes in the casing to
allow communication
between the reservoir
and the wellbore

Step 3
Drill horizontally to desired length.

7

Drilling

Core Samples
In some cases, a core
sample of the formation is
Example of a
taken for testing. A special
core sample.
Typically 12
core barrel is lowered to
inches in length
the bottom on the drill
and 8 inches in
diameter. The
string and is rotated to cut
pitted surface
a core from the formation. represents visible
pore space.
This core is brought to the
surface and examined in
a laboratory. Some core
Source: Kocurek Industries
or chip analysis may occur
Source: Kocurek Industries
at the temporary on-site lab while other core samples
are sealed and shipped to specialized labs for in-depth
reservoir characteristic and core analysis.
Casing and Cement
Well construction activities are engineered to ensure
that groundwater bearing horizons are isolated from
the wellbore. This process eliminates the potential for
communications and possible contamination during
subsequent drilling, completion and final production
operations. To provide the protection necessary, usually
a number of  steps are completed to isolate the wellbore
from the surrounding rock intervals that have been
penetrated during the drilling process.
Step 1 	 Once the conductor pipe has been put in
place the surface hole is drilled to the base
of groundwater protection, as defined by the
regulatory body. Surface casing is lowered into
the hole and cemented in place. At this stage,
a barrier of steel AND cement is created to
prevent the contamination of potential shallow
groundwater aquifers as well provide wellbore
stability for the remaining drill hole.

vertical) an intermediate set of casing may
be inserted into the wellbore and cemented
in place. The process of installation and
cementing of intermediate and production
casing is similar to surface casing. The decision
to install additional casing is based upon
expected reservoir conditions as well as
completion and stimulation techniques that
are to be used. This second (or third) set of
steel casing provides additional isolation of
the hydrocarbon zone from potential shallow
aquifers.

CSUR Casing Model

It is important to recognize that the oil and
gas industry uses technologically advanced
cement to construct the wellbore. Concrete
used for sidewalks is very different than the
cement used to secure surface, intermediate
and production casing in place. Cements are
tailored to formation, temperature, depth,
completion technique and other factors.

Step 2 	 The cement is allowed to set prior to
continuation of drilling and in some
jurisdictions, a “cement bond” geophysical log
is run to determine the integrity of the cement
that surrounds the surface casing.
Step 3	 The wellbore is then drilled to its total depth.
In some cases, depending on the total depth
of the well or the orientation (horizontal or
8
Sur

face

Municipal water well

Private
well

Shallow groundwater aquifer
Deep groundwater aquifer

Surface
gas-well
lease

Protective steel casing:
Steel casing and
cement provide well
control and isolate
groundwater zones

1,00

0m

Lim
esto
ne

HYDRAULIC FRACTURING

1,50

0m

2,00

Induced shale
fractures

0m

San

dsto

ne

Gas

-rich

Hor

izon

Source: Canadian Natural Gas

9

2,30

0m

sha

le

tal b

ore
Note: Buildings and
well depth not to scale

Casing and Cement

It is important to ensure that groundwater is
protected, not only in the first few stages of wellbore
construction, but also during the full life cycle of the
well. This is a regulated process whereby the owner
of the well is required to ensure that conditions
downhole do not degrade the wellbore integrity over
time. Possible well integrity concerns could arise as
a result of poor cement bond, casing shift, corrosion
of casing over time, etc. There are several diagnostic
tools utilized in industry to help promote wellbore
integrity such as cathodic protection, chemical
treatment and production packers. There are also
several tools to identify wellbore integrity issues after
they’ve occurred, for example, corrosion logs, cement
bond logs, production logs and casing patches.
Completions and Stimulation
Once the well has been drilled and cased it is now ready to
be stimulated. There are a variety of stimulation processes,
the most common of which being hydraulic fracturing.
Following the stimulation of the potential zone(s) the well
is ready to be equipped for production.
When the well is ready, hydrocarbons can be produced
either through the production casing or through tubing
inserted down the production casing. The type of
hydrocarbons produced  (oil or gas) will determine the
type of production string used.

Coil Tubing Unit

If tubing is to be used, the joints are linked together with
couplings to make up a tubing string. Tubing is run into
the well much the same as casing, but tubing is smaller in
diameter and is removable. Coiled tubing can also be used
thus eliminating  the need for tongs, slips, or elevators,
which makes it easier to install. Prior to production flow,
downhole isolation equipment such as packers or plugs
are removed and drilling fluid is flushed from the wellbore.
Hydrocarbons can now flow freely to the wellhead.

Source: Schlumberger

If the well does not flow on its own, artificial lift systems
may need to be considered, such as  a beam pumping
unit.
Beam Pumping Units.

Source: United States Department of Labour

10
The drilling of an oil or gas well requires a number of highly
trained professionals, both in the office as well as in the field.
Key personnel may include but are not limited to:  
Drilling Engineers design and implement procedures to drill
wells as safely and economically as possible, while at the
same time protecting the health and safety of workers and
other personnel  in accordance with established regulations.
Surface Land Men ensure the timely and accurate acquisition
of surface rights; coordinating the efforts of Surveyors and
Brokers. They represent the drilling company and interact
extensively with internal Business Units, public and regulatory
stakeholders. They also make sure surface acquisition and
consultation compliance meet Regulatory requirements.
Surveyors determine the precise location of the planned
well the surrounding lease  site.  He or she is licensed by the
province and work on behalf of the oil and gas company

A Construction Engineer performs engineering work in the
field to support well construction and helps in  the planning
and execution of construction work in the field.
Contractors or Sub-Contractors are employed by the oil and
gas company to perform work onsite throughout various
stages during well construction. The drilling crew, cementers,
well testers, water haulers and welders are all examples of
contractors that work on the construction site.
Well site geologists monitor the progress of the well as it
is drilled to identify the presence of oil and gas in the sub
surface. They also inform the rest of the drill team when the
well has reached the reservoir target.

11

Completions and Stimulation

Key Personnel
Site Maintenance
Footprint
Commercial production of unconventional resources often
requires numerous wells to intersect the oil and gas bearing
formation(s) in order to be economic. The technologies
of horizontal drilling and multi-stage fracture stimulation
coupled with multiple wells from a single pad have enabled
the cumulative surface footprint to be minimized.
Companies can  drill multiple wells from a single-pad location
and extract the hydrocarbons from as much as 10 sq km.
While the size of a  multi-well pad is slightly larger than
a regular oil and gas lease the cumulative footprint for
a development is much smaller than it would be with
conventional development using vertical wells. Fewer access
roads and the concentration of facilities and pipelines within
the pad footprint minimize the surface disturbance of a
development.

Construction vs. Production
Once the well is completed and fully moved through to
production, the footprint of the lease site is greatly reduced.

Multi-well pad during construction and completions activity

During the actual drilling and hydraulic stimulation
procedures for unconventional resource development,
there is a concentration of heavy equipment on site. Water
requirements for both drilling and fracturing can be large and
commonly a lined reservoir pit or tanks are used for storage.
In some cases, if the water source is nearby, temporary
pipelines are constructed to transport the water rather than
using tanker trucks. Upon completion of the drilling activities,
all of the heavy equipment is removed and permanent
surface facilities are constructed. In most cases, the footprint
Horizontal multi-well pad in production
of the wells and surface facilities is much smaller than the
Source: Trident Exploration
original drilling footprint
12
Site Maintenance

Well Control
Properly trained personnel are essential for well control
activities. Well control consists of two basic components: an
active component consisting of  specialized drilling fluids
and pressure control to minimize the potential inflow of
hydrocarbons or groundwater fluids and a passive component
that consists of  monitoring equipment that responds if a inflow
or pressure kick occurs. The Blowout Preventer (BOP) is an
integral part of the monitoring and well control equipment.
The first line of defense in well control is to have sufficient
drilling fluid pressure in the wellbore. In the subsurface,
underground fluids such as gas, water or oil  are under pressure
(formation pressure). The column of drilling fluid in the
well creates a pressure (mud pressure)  that counteracts the
formation pressure. If the formation pressure is greater than the
mud pressure, there is the possibility of a blowout.

Blowout Preventer (BOP)

The blowout preventer (BOP), accumulator and choke
manifold are installed by the rig crew after the surface casing is
set and cemented. The choke line valve is used to redirect the
mud from the well bore to the choke manifold should a pressure
event occur.  If an event does occur, the BOP is activated,
containing the pressure and avoiding a blowout.
The BOPs, accumulators, and choke manifold need to be
properly maintained and  are tested on a regular basis

Choke Manifold

13
Glossary and Terminology
Accumulator: A device used in a hydraulic system to store
energy or, in some applications, dampen pressure fluctuations.
Well pressure-control systems typically incorporate sufficient
accumulator capacity to enable the blowout preventer to be
operated with all other power shut down.

Cellar:  A dug-out area, possibly lined with wood, cement or very
large diameter  pipe, located below the rig. The cellar serves as
a cavity in which the casing spool and casing head reside. On
smaller rigs, the cellar also serves as the place where the lower
part of the BOP stack resides.

Aquifers: Any water-bearing formation encountered while
drilling. Drillers often are concerned about aquifers and
are required to take special precautions in the design and
execution of the well plan to protect fresh water aquifers from
contamination by wellbore fluids.

Cement Bond Logs: A representation of the integrity of the
cement, used in casing of the well.
Choke Manifold: A set of high-pressure valves and associated
piping that usually includes at least two adjustable chokes,
arranged such that one adjustable choke may be isolated and
taken out of service for repair and refurbishment while well flow
is directed through the other one.

Beam Pumping Unit: An artificial-lift pumping system using a
surface power source to drive a downhole pump assembly.
BOP (Blow Out Preventer): A large valve at the top of a well that
may be closed if the drilling crew loses control of formation fluids.
By closing this valve (usually operated remotely via hydraulic
actuators), the drilling crew can regain control of the reservoir.
Casing: Large-diameter pipe lowered into an openhole and
cemented in place. The well designer must design casing to
withstand a variety of forces, such as collapse, burst, and tensile
failure, as well as chemically aggressive brines.

Drill Bit: The tool used to crush or cut rock. Everything on a
drilling rig directly or indirectly assists the bit in crushing or
cutting the rock.
Drilling Fluid:  Any of a number of liquid and gaseous fluids and
mixtures of fluids and solids (as solid suspensions, mixtures and
emulsions of liquids, gases and solids) used in operations to drill
boreholes into the earth.
Drill String: A pipe made of lengths of steel tubing that is
attached to the drilling tool and rotates during drilling. The
drilling fluid passes through the centre of the drill string through
the bit which is attached at the end.

Cathodic Protection: A technique used to minimize the rate
of corrosion of a structure. It does not eliminate corrosion, it
transfers corrosion from the structure under protection to a
known location where artificial anodes (plates or metal bars) are
placed and could be replaced easily.

14
Formation Fluids: Any fluid that occurs in the pores of a rock. Strata
containing different fluids, such as various saturations of oil, gas and
water, may be encountered in the process of drilling an oil or gas
well. Fluids found in the target reservoir formation are referred to as
reservoir fluids.  
Formation Pressure: The pressure of fluids within the pores of a
reservoir, normally hydrostatic pressure, or the pressure exerted by a
column of water from the formation’s depth to sea level.
Geophysical Logs: A log of elemental concentrations from which the
geochemistry of the formation may be derived.
Hydrogen Sulfide (H2S): An extraordinarily poisonous gas with a
molecular formula of H2S. At low concentrations, H2S has the odor of
rotten eggs, but at higher, lethal concentrations, it is odorless. H2S is
hazardous to workers and a few seconds of exposure at relatively low
concentrations can be lethal, but exposure to lower concentrations
can also be harmful. The effect of H2S depends on duration,
frequency and intensity of exposure as well as the susceptibility of
the individual.

Kelly: A long square or hexagonal steel bar with a hole drilled
through the middle for a fluid path. The kelly is used to transmit
rotary motion from the rotary table or kelly bushing to the drillstring,
while allowing the drillstring to be lowered or raised during rotation.
Mud Pressure: The pressure of the column of drilling fluid in the
wellbore.
Packer: A device that can be run into a wellbore with a smaller initial
outside diameter that then expands externally to seal the wellbore.
Perforating Gun: A device used to perforate oil and gas wells in
preparation for production.
Rigging-up: To make ready for use. Equipment must typically be
moved onto the rig floor, assembled and connected to power
sources or pressurized piping systems.
Rig Mat: A portable platform used to support equipment for
construction and resource-based activities including drilling rigs,
camps, tanks, helipads, etc. It also includes a structural roadway to
provide passage over unstable ground, pipelines and more.

15

Glossary and Terminology

Formation Evaluation Tools: The tools used for the measurement
and analysis of formation and fluid properties. Formation evaluation
is performed to assess the quantity and producibility of fluids from
a reservoir. Formation evaluation guides wellsite decisions, such
as placement of perforations and hydraulic fracture stages, and
reservoir development and production planning.
Canadian Society for Unconventional Resources (CSUR)
Suite 420, 237 - 8th Avenue SE
Calgary, AB T2G 5C3
Phone: 403-233-9298; Toll Free: 1-855-833-9298
Email: info@csur.com; Web: www.csur.com

Mais conteúdo relacionado

Mais procurados

Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015Terry Aylward
 
Construction Dewatering PowerPoint
Construction Dewatering PowerPointConstruction Dewatering PowerPoint
Construction Dewatering PowerPointTerry Aylward
 
OFFSHORE GEOTECHNICAL INTRODUCTION
OFFSHORE GEOTECHNICAL INTRODUCTIONOFFSHORE GEOTECHNICAL INTRODUCTION
OFFSHORE GEOTECHNICAL INTRODUCTIONNardipta Pratama
 
Hydraulic Fracturing: Importance to the Industry
Hydraulic Fracturing: Importance to the IndustryHydraulic Fracturing: Importance to the Industry
Hydraulic Fracturing: Importance to the IndustryPorts-To-Plains Blog
 
Exploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well TechnologyExploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well TechnologyAbhinav Bisht
 
Petroleum well completion overview
Petroleum well completion overviewPetroleum well completion overview
Petroleum well completion overviewAndi Anriansyah
 
Wel Planing
Wel PlaningWel Planing
Wel Planingsaqib129
 
Extreme oil rig
Extreme oil rigExtreme oil rig
Extreme oil rigabhidude25
 
Dam safety & Safety Devices
Dam safety & Safety DevicesDam safety & Safety Devices
Dam safety & Safety DevicesTushar Dholakia
 
Trenchless technologies comparing thrust boring with horizontal directional ...
Trenchless technologies  comparing thrust boring with horizontal directional ...Trenchless technologies  comparing thrust boring with horizontal directional ...
Trenchless technologies comparing thrust boring with horizontal directional ...Tobiloba Omitola
 

Mais procurados (20)

Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015
 
Backhoe Dredger
Backhoe Dredger Backhoe Dredger
Backhoe Dredger
 
Construction Dewatering PowerPoint
Construction Dewatering PowerPointConstruction Dewatering PowerPoint
Construction Dewatering PowerPoint
 
Dredging
DredgingDredging
Dredging
 
OFFSHORE GEOTECHNICAL INTRODUCTION
OFFSHORE GEOTECHNICAL INTRODUCTIONOFFSHORE GEOTECHNICAL INTRODUCTION
OFFSHORE GEOTECHNICAL INTRODUCTION
 
Construction dewatering technology data sheet
Construction dewatering technology data sheetConstruction dewatering technology data sheet
Construction dewatering technology data sheet
 
Cutter Suction Dredger
Cutter Suction DredgerCutter Suction Dredger
Cutter Suction Dredger
 
Hydraulic Fracturing: Importance to the Industry
Hydraulic Fracturing: Importance to the IndustryHydraulic Fracturing: Importance to the Industry
Hydraulic Fracturing: Importance to the Industry
 
Exploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well TechnologyExploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well Technology
 
Petroleum well completion overview
Petroleum well completion overviewPetroleum well completion overview
Petroleum well completion overview
 
Mine dewatering technology data sheet
Mine dewatering technology data sheetMine dewatering technology data sheet
Mine dewatering technology data sheet
 
Dredging psa 22
Dredging psa 22Dredging psa 22
Dredging psa 22
 
TCD2011 - Kunne bedre kompetanse avverget Macondo-ulykken i Mexico-gulfen? v/...
TCD2011 - Kunne bedre kompetanse avverget Macondo-ulykken i Mexico-gulfen? v/...TCD2011 - Kunne bedre kompetanse avverget Macondo-ulykken i Mexico-gulfen? v/...
TCD2011 - Kunne bedre kompetanse avverget Macondo-ulykken i Mexico-gulfen? v/...
 
Hydraulic Fracturing 101
Hydraulic Fracturing 101Hydraulic Fracturing 101
Hydraulic Fracturing 101
 
DREDGING
DREDGINGDREDGING
DREDGING
 
Offshore drilling in petroleum
Offshore drilling in petroleumOffshore drilling in petroleum
Offshore drilling in petroleum
 
Wel Planing
Wel PlaningWel Planing
Wel Planing
 
Extreme oil rig
Extreme oil rigExtreme oil rig
Extreme oil rig
 
Dam safety & Safety Devices
Dam safety & Safety DevicesDam safety & Safety Devices
Dam safety & Safety Devices
 
Trenchless technologies comparing thrust boring with horizontal directional ...
Trenchless technologies  comparing thrust boring with horizontal directional ...Trenchless technologies  comparing thrust boring with horizontal directional ...
Trenchless technologies comparing thrust boring with horizontal directional ...
 

Destaque

Namami gange by mndp poonia pdf
Namami gange by mndp poonia pdfNamami gange by mndp poonia pdf
Namami gange by mndp poonia pdfmndp_slide
 
NON CONVENTIONAL SOURCES OF ENERGY
NON CONVENTIONAL SOURCES OF ENERGYNON CONVENTIONAL SOURCES OF ENERGY
NON CONVENTIONAL SOURCES OF ENERGYNishkarsh Gupta
 
Well design and construction i
Well design and construction iWell design and construction i
Well design and construction iYalçın Dalgıç
 
Non conventional energy
Non conventional energyNon conventional energy
Non conventional energyArgha Paul
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipmentsAshish Parihar
 

Destaque (6)

Namami gange by mndp poonia pdf
Namami gange by mndp poonia pdfNamami gange by mndp poonia pdf
Namami gange by mndp poonia pdf
 
NON CONVENTIONAL SOURCES OF ENERGY
NON CONVENTIONAL SOURCES OF ENERGYNON CONVENTIONAL SOURCES OF ENERGY
NON CONVENTIONAL SOURCES OF ENERGY
 
Well design and construction i
Well design and construction iWell design and construction i
Well design and construction i
 
Non conventional energy
Non conventional energyNon conventional energy
Non conventional energy
 
Non conventional sources of energy
Non conventional sources of energyNon conventional sources of energy
Non conventional sources of energy
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 

Semelhante a Hydraulic Fracturing Understanding well construction

overview of DRILLING OPERATION.pptx
overview of DRILLING OPERATION.pptxoverview of DRILLING OPERATION.pptx
overview of DRILLING OPERATION.pptxTemitopeBello6
 
A Landowner’s Guide to Understanding Recommended Pipeline Standards and Const...
A Landowner’s Guide to Understanding Recommended Pipeline Standards and Const...A Landowner’s Guide to Understanding Recommended Pipeline Standards and Const...
A Landowner’s Guide to Understanding Recommended Pipeline Standards and Const...Marcellus Drilling News
 
Subsea field development
Subsea field developmentSubsea field development
Subsea field developmentHamid S
 
Coffer dams 01
Coffer dams 01Coffer dams 01
Coffer dams 01juwes
 
Semester Assignment Drilling, Reservoir & Well Engineering Study
Semester Assignment Drilling, Reservoir & Well Engineering StudySemester Assignment Drilling, Reservoir & Well Engineering Study
Semester Assignment Drilling, Reservoir & Well Engineering StudyNikolaos Felessakis
 
Construction equipments By T.Ravi Prakash
Construction equipments By T.Ravi PrakashConstruction equipments By T.Ravi Prakash
Construction equipments By T.Ravi Prakashravicivil
 
Subsea completion and control system
Subsea completion and control systemSubsea completion and control system
Subsea completion and control systemAmit Nitharwal
 
Introduction to Drilling Engineering
Introduction to Drilling EngineeringIntroduction to Drilling Engineering
Introduction to Drilling EngineeringM.T.H Group
 
Construction manual chapter 2
Construction manual chapter 2Construction manual chapter 2
Construction manual chapter 2vps1968
 
deep-foundation-selection-driven-pile-or-drilled good for presentation.pptx
deep-foundation-selection-driven-pile-or-drilled good for presentation.pptxdeep-foundation-selection-driven-pile-or-drilled good for presentation.pptx
deep-foundation-selection-driven-pile-or-drilled good for presentation.pptxvalter gentile
 
Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101SHAZEBALIKHAN1
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstructionvietcgxd
 
Well completion d.pptx
Well completion d.pptxWell completion d.pptx
Well completion d.pptxAihamAltayeh1
 

Semelhante a Hydraulic Fracturing Understanding well construction (20)

Petroleum drilling fundamentals
Petroleum drilling fundamentalsPetroleum drilling fundamentals
Petroleum drilling fundamentals
 
overview of DRILLING OPERATION.pptx
overview of DRILLING OPERATION.pptxoverview of DRILLING OPERATION.pptx
overview of DRILLING OPERATION.pptx
 
A Landowner’s Guide to Understanding Recommended Pipeline Standards and Const...
A Landowner’s Guide to Understanding Recommended Pipeline Standards and Const...A Landowner’s Guide to Understanding Recommended Pipeline Standards and Const...
A Landowner’s Guide to Understanding Recommended Pipeline Standards and Const...
 
Subsea field development
Subsea field developmentSubsea field development
Subsea field development
 
Defining Well completion
Defining Well completionDefining Well completion
Defining Well completion
 
Casing design
Casing designCasing design
Casing design
 
Coffer dams 01
Coffer dams 01Coffer dams 01
Coffer dams 01
 
Jom 06 02_001
Jom 06 02_001Jom 06 02_001
Jom 06 02_001
 
Semester Assignment Drilling, Reservoir & Well Engineering Study
Semester Assignment Drilling, Reservoir & Well Engineering StudySemester Assignment Drilling, Reservoir & Well Engineering Study
Semester Assignment Drilling, Reservoir & Well Engineering Study
 
Construction equipments By T.Ravi Prakash
Construction equipments By T.Ravi PrakashConstruction equipments By T.Ravi Prakash
Construction equipments By T.Ravi Prakash
 
20405_merged.pdf
20405_merged.pdf20405_merged.pdf
20405_merged.pdf
 
Subsea completion and control system
Subsea completion and control systemSubsea completion and control system
Subsea completion and control system
 
Introduction to Drilling Engineering
Introduction to Drilling EngineeringIntroduction to Drilling Engineering
Introduction to Drilling Engineering
 
Construction manual chapter 2
Construction manual chapter 2Construction manual chapter 2
Construction manual chapter 2
 
deep-foundation-selection-driven-pile-or-drilled good for presentation.pptx
deep-foundation-selection-driven-pile-or-drilled good for presentation.pptxdeep-foundation-selection-driven-pile-or-drilled good for presentation.pptx
deep-foundation-selection-driven-pile-or-drilled good for presentation.pptx
 
Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstruction
 
Drilling imp
Drilling impDrilling imp
Drilling imp
 
Summer training
Summer trainingSummer training
Summer training
 
Well completion d.pptx
Well completion d.pptxWell completion d.pptx
Well completion d.pptx
 

Mais de Andy Varoshiotis

Covid 19 DAN recommendations for Dive Centers
Covid 19 DAN recommendations for Dive CentersCovid 19 DAN recommendations for Dive Centers
Covid 19 DAN recommendations for Dive CentersAndy Varoshiotis
 
Scuba Diving Ear Equlization
Scuba Diving Ear Equlization Scuba Diving Ear Equlization
Scuba Diving Ear Equlization Andy Varoshiotis
 
Solarus Powercollectors Technical Brochure
Solarus Powercollectors Technical BrochureSolarus Powercollectors Technical Brochure
Solarus Powercollectors Technical BrochureAndy Varoshiotis
 
Solarus thermal-heating-system
Solarus thermal-heating-systemSolarus thermal-heating-system
Solarus thermal-heating-systemAndy Varoshiotis
 
Cyprus Oil & Gas Association May 2017
Cyprus Oil & Gas Association May 2017Cyprus Oil & Gas Association May 2017
Cyprus Oil & Gas Association May 2017Andy Varoshiotis
 
Cyprus Oil & Gas Association AGM agenda official
Cyprus Oil & Gas Association AGM agenda officialCyprus Oil & Gas Association AGM agenda official
Cyprus Oil & Gas Association AGM agenda officialAndy Varoshiotis
 
Solar PV Net meetering explained
Solar PV Net meetering explainedSolar PV Net meetering explained
Solar PV Net meetering explainedAndy Varoshiotis
 
Power for all, Renewable Energy Declaration and statement
Power for all, Renewable Energy Declaration and statement Power for all, Renewable Energy Declaration and statement
Power for all, Renewable Energy Declaration and statement Andy Varoshiotis
 
Fidel Castro Khrushchev correspondence
Fidel Castro Khrushchev correspondenceFidel Castro Khrushchev correspondence
Fidel Castro Khrushchev correspondenceAndy Varoshiotis
 
Emergency FIrst Responder Presentation I Dive
Emergency FIrst Responder Presentation I Dive Emergency FIrst Responder Presentation I Dive
Emergency FIrst Responder Presentation I Dive Andy Varoshiotis
 
I Dive Tec Rec Centers Plc, Scuba Diving Protaras - Ayia Napa
I Dive Tec Rec Centers Plc, Scuba Diving Protaras - Ayia Napa I Dive Tec Rec Centers Plc, Scuba Diving Protaras - Ayia Napa
I Dive Tec Rec Centers Plc, Scuba Diving Protaras - Ayia Napa Andy Varoshiotis
 
Harvard University Preventing nuclear terrorism
Harvard University Preventing nuclear terrorism Harvard University Preventing nuclear terrorism
Harvard University Preventing nuclear terrorism Andy Varoshiotis
 
Irena cyprus roadmap report
Irena cyprus roadmap reportIrena cyprus roadmap report
Irena cyprus roadmap reportAndy Varoshiotis
 
Harvard University Maugeri Global oil 2016
Harvard University Maugeri Global oil 2016Harvard University Maugeri Global oil 2016
Harvard University Maugeri Global oil 2016Andy Varoshiotis
 
Harvard University The energy implications of a nuclear deal between the p51 ...
Harvard University The energy implications of a nuclear deal between the p51 ...Harvard University The energy implications of a nuclear deal between the p51 ...
Harvard University The energy implications of a nuclear deal between the p51 ...Andy Varoshiotis
 

Mais de Andy Varoshiotis (20)

Covid 19 DAN recommendations for Dive Centers
Covid 19 DAN recommendations for Dive CentersCovid 19 DAN recommendations for Dive Centers
Covid 19 DAN recommendations for Dive Centers
 
Scuba Diving Ear Equlization
Scuba Diving Ear Equlization Scuba Diving Ear Equlization
Scuba Diving Ear Equlization
 
Solarus Powercollectors Technical Brochure
Solarus Powercollectors Technical BrochureSolarus Powercollectors Technical Brochure
Solarus Powercollectors Technical Brochure
 
Solarus thermal-heating-system
Solarus thermal-heating-systemSolarus thermal-heating-system
Solarus thermal-heating-system
 
Solarus Brochure 2017
Solarus Brochure 2017Solarus Brochure 2017
Solarus Brochure 2017
 
Cyprus Oil & Gas Association May 2017
Cyprus Oil & Gas Association May 2017Cyprus Oil & Gas Association May 2017
Cyprus Oil & Gas Association May 2017
 
COGA sponsorship pack agm
COGA sponsorship pack agmCOGA sponsorship pack agm
COGA sponsorship pack agm
 
Cyprus Oil & Gas Association AGM agenda official
Cyprus Oil & Gas Association AGM agenda officialCyprus Oil & Gas Association AGM agenda official
Cyprus Oil & Gas Association AGM agenda official
 
Solar PV Net meetering explained
Solar PV Net meetering explainedSolar PV Net meetering explained
Solar PV Net meetering explained
 
Power for all, Renewable Energy Declaration and statement
Power for all, Renewable Energy Declaration and statement Power for all, Renewable Energy Declaration and statement
Power for all, Renewable Energy Declaration and statement
 
Harvest 4 Energy Ltd
Harvest 4 Energy LtdHarvest 4 Energy Ltd
Harvest 4 Energy Ltd
 
Nsp brochure
Nsp brochureNsp brochure
Nsp brochure
 
Fidel Castro Khrushchev correspondence
Fidel Castro Khrushchev correspondenceFidel Castro Khrushchev correspondence
Fidel Castro Khrushchev correspondence
 
Idive guide to_diving
Idive guide to_divingIdive guide to_diving
Idive guide to_diving
 
Emergency FIrst Responder Presentation I Dive
Emergency FIrst Responder Presentation I Dive Emergency FIrst Responder Presentation I Dive
Emergency FIrst Responder Presentation I Dive
 
I Dive Tec Rec Centers Plc, Scuba Diving Protaras - Ayia Napa
I Dive Tec Rec Centers Plc, Scuba Diving Protaras - Ayia Napa I Dive Tec Rec Centers Plc, Scuba Diving Protaras - Ayia Napa
I Dive Tec Rec Centers Plc, Scuba Diving Protaras - Ayia Napa
 
Harvard University Preventing nuclear terrorism
Harvard University Preventing nuclear terrorism Harvard University Preventing nuclear terrorism
Harvard University Preventing nuclear terrorism
 
Irena cyprus roadmap report
Irena cyprus roadmap reportIrena cyprus roadmap report
Irena cyprus roadmap report
 
Harvard University Maugeri Global oil 2016
Harvard University Maugeri Global oil 2016Harvard University Maugeri Global oil 2016
Harvard University Maugeri Global oil 2016
 
Harvard University The energy implications of a nuclear deal between the p51 ...
Harvard University The energy implications of a nuclear deal between the p51 ...Harvard University The energy implications of a nuclear deal between the p51 ...
Harvard University The energy implications of a nuclear deal between the p51 ...
 

Último

ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxChelloAnnAsuncion2
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomnelietumpap1
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptxmary850239
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 

Último (20)

ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choom
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 

Hydraulic Fracturing Understanding well construction

  • 2. Well Construction Timeline Well Site Planning & Preparation Stage 1: Planning and Preparation • Acquire Surface Lease Agreement • Determination of multi-well pad or single well pad requirements • Inform stakeholders of the proposed well construction • Evaluation of sour gas probability; this will influence equipment location, etc. • Acquire Well license(s) • Obtain Operation(s) permits • Site Excavation and Preparation • The preparation of the location would include the drilling of initial “rat hole/mouse hole” and placement of conductor string/ pipe • Identify safety procedures, environmental and regulatory requirements • Outline the emergency response plans/procedures Drilling Stage 2: Drilling • Drilling rig and equipment mobilization (if not used for Surface Hole drilling) • Drilling fluids/mud – testing and recycling • Blow Out Preventer (BOP) installation • Surface, and intermediate (in some cases) casing cemented into the wellbore • Drill cutting samples taken and analyzed (ongoing throughout the drilling process) • Wellbore drilled to total depth(vertical, directional or horizontal) • Potential reservoir(s) identified and evaluated using geophysical logging techniques Most stages of well construction include stakeholder dialogue. Consultation with stakeholders is the responsibility of the individual project proponent. 2
  • 3. Stage 3: Casing and Cement • Production casing lowered into the well and cemented into place • Diagnostic tools are utilized to ensure wellbore integrity Completion & Stimulation Stage 4: Completion & Stimulation • Drilling rig is moved offsite and permanent wellhead installed • Stimulation equipment is moved into place • Reservoir horizons are perforated and then stimulated • Stimulation equipment is moved offsite • Producing zones are tested • With the drilling and completion equipment demobilized, the surface footprint is dramatically reduced. Site Maintenance After casing, cementing and well stimulation activities are completed, and assuming the well is successful, there will be additional construction activity on site to install surface facilities if required, tie the well into the pipeline infrastructure, and contour and reclaim part of the lease site. This information booklet discusses well construction practices only. For more information about the completions process, including Hydraulic Fracturing or other stimulation techniques, please reference Understanding Hydraulic Fracturing or Understanding Water and Unconventional Resources at www.csur.com 3 Well Construction Timeline Casing & Cement
  • 4. Well Site Planning & Preparation Single vs. Multi-well pad A standard single well lease site for conventional oil or gas will typically affect a surface area measuring 100 metres by 100 metres. The lease site will typically hold the drilling rig and additional equipment along with supervisory accommodation and material storage. If multiple wells from a single pad are planned, the surface area of the lease site would be larger; in some cases as much as double the size. (100 metres by 200 metres.) While a multi-well pad site will have a larger surface area, the cumulative surface impact of the total number of wells drilled in the project area will be smaller. Pad sites allow multiple wells to be drilled from one surface lease, thereby reducing the total surface area required for oil and gas development. Once drilling is completed and the well(s) is/are connected/tied-in to the pipeline, a portion of the lease area can be reclaimed to minimize surface disturbance. Surface Lease Site Agreement A surface lease site agreement grants a company access to drill a well(s) on land that is held either privately, by the crown or by a First Nation. The agreement also specifies any conditions relating to the commitments and responsibilities of both the company and the landowner, including the payment of compensation by the company to the landowner. License & Permit Federal and/or Provincial and Municipal licenses and permits are required for lease site construction; project specific requirements will vary depending on the location of the well. Excavation & Leveling To prepare for initial drilling, the lease site is leveled, if necessary, with a bulldozer and/or grader, with careful consideration given to buried pipelines and utilities, as well as proximity to surface water features. The scale and duration of lease site preparation is site-specific. On some drilling sites, a cellar may be excavated. This is where the main borehole is to be drilled. A reserve pit and settling pits may be excavated and are used for water or drilling fluid (mud) discharges. Often the soil layers are separated for better soil conservation. Upon completion of the drilling, the soils can then be restored to their original location. Excavated lease site 4
  • 5. Safety Procedures & Emergency Response Plans All drilling sites are typically classified according to areas of potential and/or actual exposure to Hydrogen Sulfide (H2S). H2S is an extremely toxic and poisonous gas. Employers will take special precautions when choosing equipment. Well site employees are trained to respond accordingly should they encounter H2S. Under these circumstances, all employees are required to wear specially approved masks and air supply equipment. The recommendations and employee instruction will vary depending on the type of area, as will the emergency response plans (ERPs) that are in place Environmental and Regulatory Considerations Provincial and federal regulations, which govern the oil and gas industry, have been in place for many years. They have been established to ensure that both the public and the environment are protected throughout exploration, development and production of hydrocarbon resources. Regulations are also continually reviewed and revised, as required, in response to advancements in industry technologies and the techniques employed to extract the resource. The fundamental regulatory basics of surface and groundwater protection, wellbore integrity, lease construction, for example, apply to all types of hydrocarbon developments; including unconventional resources. Similarly, the use of water for drilling and completion activities require approvals or permits from appropriate authorities. Prior to acquisition of the surface lease site, a number of different steps are required. Requirements will vary depending on the location of the proposed development and jurisdictional prerequisites. 5 Well Site Planning & Preparation Drilling of the “Surface Hole” , etc. As part of any oil or gas well, a conductor hole and surface hole are required as part of the entire wellbore. Commonly, a rathole and/or a mousehole are drilled prior to the actual drilling of the well to reservoir depth. A conductor hole, also referred to as a “starter hole” is a large diameter hole, lined with pipe which varies in depth, and is used to house the BOP (Blow Out Preventer). A rathole is a hole lying below the rig floor, 30 to 35 feet deep, lined with casing into which the kelly is placed when hoisting operations are in progress. A mousehole is a shallow bore hole under the rig floor, usually lined with pipe, into which joints of drill pipe are temporarily placed during drilling operations. These are either done by the portable rig that drills the conductor hole, or can be done by the primary rig after rigging-up. The surface hole is drilled and cased to isolate potential shallow groundwater aquifers from the wellbore.
  • 6. Drilling Equipment Assembly and Placement A site, and its access road, must accommodate a large number of temporary and semi-permanent structures and tanks, all brought in by truck. At a newly-prepared drill site, the stability of the well pad is necessary to support the drilling rig and auxiliary equipment required onsite. In some localities where the ground is unstable rig mats are commonly used. After the well pad is properly prepared the drilling rig is then unloaded and assembled. There are many rig designs, and this booklet does not cover each type individually. During assembly of the rig, some equipment may be handled and set with crane, rig up trucks, or forklift, depending on the size of the rig. The substructure is assembled, pinned together, leveled, and tied into other rig components. Once the substructure is set in place, installing the power system and raising the derrick begins. Most drilling rigs are powered by electricity that is delivered by onsite diesel powered generators. While one crew finishes preparing the rig floor, another crew might be rigging up the circulating system. The mud tanks and mud pumps are set into the predetermined location. Once all additional drilling and auxiliary equipment are set into place a final inspection can be done. The entire process of riggingup can take one or two days. Where multiple wells are drilled from a single pad, commonly the drilling rig will have the ability to move to the next location on the lease with minimal disassembly/ reassembly. 6 Source: Shale Exploration Drilling boreholes deep into the ground and preparing them to produce oil and gas is a highly technical and specialized process. Throughout the operation, custom-designed fluids fulfill many different roles. While drilling, these include: lubricating the drill bit; circulating drilled-up rock out of the hole; containing formation fluids within the hole; and facilitating operation of sophisticated formation evaluation tools. Fluids may be water-based, oil-based, or synthetic.
  • 7. Step 1 Drill vertically until the wellbore reaches a point above the targeted reservoir. Step 2 “Kick off” and begin to drill at an increasing angle until the wellbore runs horizontally through the targeted reservoir. Vertical vs. Horizontal Although historically oil and gas wells have been drilled vertically, new technologies have made it possible for wells to be drilled horizontally. The purpose of drilling a horizontal well is to increase amount of reservoir rock that is intersected from the wellbore. Horizontal drilling first entails drilling a vertical well to a predetermined depth above the reservoir. The well is then drilled at an increasing angle until it intersects the reservoir interval in a horizontal plane. Once horizontal, the well is then drilled to a selected length, which could extend to as much as 3500m. This portion of the well, called the horizontal leg, allows significantly increased contact of the wellbore with the reservoir compared to a vertical well. Upon completion of drilling, production casing is commonly placed into the wellbore. A perforating gun is lowered into the wellbore and placed in a selected interval within the horizontal leg. It is then activated to create a series of holes in the casing to allow communication between the reservoir and the wellbore Step 3 Drill horizontally to desired length. 7 Drilling Core Samples In some cases, a core sample of the formation is Example of a taken for testing. A special core sample. Typically 12 core barrel is lowered to inches in length the bottom on the drill and 8 inches in diameter. The string and is rotated to cut pitted surface a core from the formation. represents visible pore space. This core is brought to the surface and examined in a laboratory. Some core Source: Kocurek Industries or chip analysis may occur Source: Kocurek Industries at the temporary on-site lab while other core samples are sealed and shipped to specialized labs for in-depth reservoir characteristic and core analysis.
  • 8. Casing and Cement Well construction activities are engineered to ensure that groundwater bearing horizons are isolated from the wellbore. This process eliminates the potential for communications and possible contamination during subsequent drilling, completion and final production operations. To provide the protection necessary, usually a number of steps are completed to isolate the wellbore from the surrounding rock intervals that have been penetrated during the drilling process. Step 1 Once the conductor pipe has been put in place the surface hole is drilled to the base of groundwater protection, as defined by the regulatory body. Surface casing is lowered into the hole and cemented in place. At this stage, a barrier of steel AND cement is created to prevent the contamination of potential shallow groundwater aquifers as well provide wellbore stability for the remaining drill hole. vertical) an intermediate set of casing may be inserted into the wellbore and cemented in place. The process of installation and cementing of intermediate and production casing is similar to surface casing. The decision to install additional casing is based upon expected reservoir conditions as well as completion and stimulation techniques that are to be used. This second (or third) set of steel casing provides additional isolation of the hydrocarbon zone from potential shallow aquifers. CSUR Casing Model It is important to recognize that the oil and gas industry uses technologically advanced cement to construct the wellbore. Concrete used for sidewalks is very different than the cement used to secure surface, intermediate and production casing in place. Cements are tailored to formation, temperature, depth, completion technique and other factors. Step 2 The cement is allowed to set prior to continuation of drilling and in some jurisdictions, a “cement bond” geophysical log is run to determine the integrity of the cement that surrounds the surface casing. Step 3 The wellbore is then drilled to its total depth. In some cases, depending on the total depth of the well or the orientation (horizontal or 8
  • 9. Sur face Municipal water well Private well Shallow groundwater aquifer Deep groundwater aquifer Surface gas-well lease Protective steel casing: Steel casing and cement provide well control and isolate groundwater zones 1,00 0m Lim esto ne HYDRAULIC FRACTURING 1,50 0m 2,00 Induced shale fractures 0m San dsto ne Gas -rich Hor izon Source: Canadian Natural Gas 9 2,30 0m sha le tal b ore Note: Buildings and well depth not to scale Casing and Cement It is important to ensure that groundwater is protected, not only in the first few stages of wellbore construction, but also during the full life cycle of the well. This is a regulated process whereby the owner of the well is required to ensure that conditions downhole do not degrade the wellbore integrity over time. Possible well integrity concerns could arise as a result of poor cement bond, casing shift, corrosion of casing over time, etc. There are several diagnostic tools utilized in industry to help promote wellbore integrity such as cathodic protection, chemical treatment and production packers. There are also several tools to identify wellbore integrity issues after they’ve occurred, for example, corrosion logs, cement bond logs, production logs and casing patches.
  • 10. Completions and Stimulation Once the well has been drilled and cased it is now ready to be stimulated. There are a variety of stimulation processes, the most common of which being hydraulic fracturing. Following the stimulation of the potential zone(s) the well is ready to be equipped for production. When the well is ready, hydrocarbons can be produced either through the production casing or through tubing inserted down the production casing. The type of hydrocarbons produced (oil or gas) will determine the type of production string used. Coil Tubing Unit If tubing is to be used, the joints are linked together with couplings to make up a tubing string. Tubing is run into the well much the same as casing, but tubing is smaller in diameter and is removable. Coiled tubing can also be used thus eliminating the need for tongs, slips, or elevators, which makes it easier to install. Prior to production flow, downhole isolation equipment such as packers or plugs are removed and drilling fluid is flushed from the wellbore. Hydrocarbons can now flow freely to the wellhead. Source: Schlumberger If the well does not flow on its own, artificial lift systems may need to be considered, such as a beam pumping unit. Beam Pumping Units. Source: United States Department of Labour 10
  • 11. The drilling of an oil or gas well requires a number of highly trained professionals, both in the office as well as in the field. Key personnel may include but are not limited to: Drilling Engineers design and implement procedures to drill wells as safely and economically as possible, while at the same time protecting the health and safety of workers and other personnel in accordance with established regulations. Surface Land Men ensure the timely and accurate acquisition of surface rights; coordinating the efforts of Surveyors and Brokers. They represent the drilling company and interact extensively with internal Business Units, public and regulatory stakeholders. They also make sure surface acquisition and consultation compliance meet Regulatory requirements. Surveyors determine the precise location of the planned well the surrounding lease site. He or she is licensed by the province and work on behalf of the oil and gas company A Construction Engineer performs engineering work in the field to support well construction and helps in the planning and execution of construction work in the field. Contractors or Sub-Contractors are employed by the oil and gas company to perform work onsite throughout various stages during well construction. The drilling crew, cementers, well testers, water haulers and welders are all examples of contractors that work on the construction site. Well site geologists monitor the progress of the well as it is drilled to identify the presence of oil and gas in the sub surface. They also inform the rest of the drill team when the well has reached the reservoir target. 11 Completions and Stimulation Key Personnel
  • 12. Site Maintenance Footprint Commercial production of unconventional resources often requires numerous wells to intersect the oil and gas bearing formation(s) in order to be economic. The technologies of horizontal drilling and multi-stage fracture stimulation coupled with multiple wells from a single pad have enabled the cumulative surface footprint to be minimized. Companies can drill multiple wells from a single-pad location and extract the hydrocarbons from as much as 10 sq km. While the size of a multi-well pad is slightly larger than a regular oil and gas lease the cumulative footprint for a development is much smaller than it would be with conventional development using vertical wells. Fewer access roads and the concentration of facilities and pipelines within the pad footprint minimize the surface disturbance of a development. Construction vs. Production Once the well is completed and fully moved through to production, the footprint of the lease site is greatly reduced. Multi-well pad during construction and completions activity During the actual drilling and hydraulic stimulation procedures for unconventional resource development, there is a concentration of heavy equipment on site. Water requirements for both drilling and fracturing can be large and commonly a lined reservoir pit or tanks are used for storage. In some cases, if the water source is nearby, temporary pipelines are constructed to transport the water rather than using tanker trucks. Upon completion of the drilling activities, all of the heavy equipment is removed and permanent surface facilities are constructed. In most cases, the footprint Horizontal multi-well pad in production of the wells and surface facilities is much smaller than the Source: Trident Exploration original drilling footprint 12
  • 13. Site Maintenance Well Control Properly trained personnel are essential for well control activities. Well control consists of two basic components: an active component consisting of specialized drilling fluids and pressure control to minimize the potential inflow of hydrocarbons or groundwater fluids and a passive component that consists of monitoring equipment that responds if a inflow or pressure kick occurs. The Blowout Preventer (BOP) is an integral part of the monitoring and well control equipment. The first line of defense in well control is to have sufficient drilling fluid pressure in the wellbore. In the subsurface, underground fluids such as gas, water or oil are under pressure (formation pressure). The column of drilling fluid in the well creates a pressure (mud pressure) that counteracts the formation pressure. If the formation pressure is greater than the mud pressure, there is the possibility of a blowout. Blowout Preventer (BOP) The blowout preventer (BOP), accumulator and choke manifold are installed by the rig crew after the surface casing is set and cemented. The choke line valve is used to redirect the mud from the well bore to the choke manifold should a pressure event occur. If an event does occur, the BOP is activated, containing the pressure and avoiding a blowout. The BOPs, accumulators, and choke manifold need to be properly maintained and are tested on a regular basis Choke Manifold 13
  • 14. Glossary and Terminology Accumulator: A device used in a hydraulic system to store energy or, in some applications, dampen pressure fluctuations. Well pressure-control systems typically incorporate sufficient accumulator capacity to enable the blowout preventer to be operated with all other power shut down. Cellar: A dug-out area, possibly lined with wood, cement or very large diameter pipe, located below the rig. The cellar serves as a cavity in which the casing spool and casing head reside. On smaller rigs, the cellar also serves as the place where the lower part of the BOP stack resides. Aquifers: Any water-bearing formation encountered while drilling. Drillers often are concerned about aquifers and are required to take special precautions in the design and execution of the well plan to protect fresh water aquifers from contamination by wellbore fluids. Cement Bond Logs: A representation of the integrity of the cement, used in casing of the well. Choke Manifold: A set of high-pressure valves and associated piping that usually includes at least two adjustable chokes, arranged such that one adjustable choke may be isolated and taken out of service for repair and refurbishment while well flow is directed through the other one. Beam Pumping Unit: An artificial-lift pumping system using a surface power source to drive a downhole pump assembly. BOP (Blow Out Preventer): A large valve at the top of a well that may be closed if the drilling crew loses control of formation fluids. By closing this valve (usually operated remotely via hydraulic actuators), the drilling crew can regain control of the reservoir. Casing: Large-diameter pipe lowered into an openhole and cemented in place. The well designer must design casing to withstand a variety of forces, such as collapse, burst, and tensile failure, as well as chemically aggressive brines. Drill Bit: The tool used to crush or cut rock. Everything on a drilling rig directly or indirectly assists the bit in crushing or cutting the rock. Drilling Fluid: Any of a number of liquid and gaseous fluids and mixtures of fluids and solids (as solid suspensions, mixtures and emulsions of liquids, gases and solids) used in operations to drill boreholes into the earth. Drill String: A pipe made of lengths of steel tubing that is attached to the drilling tool and rotates during drilling. The drilling fluid passes through the centre of the drill string through the bit which is attached at the end. Cathodic Protection: A technique used to minimize the rate of corrosion of a structure. It does not eliminate corrosion, it transfers corrosion from the structure under protection to a known location where artificial anodes (plates or metal bars) are placed and could be replaced easily. 14
  • 15. Formation Fluids: Any fluid that occurs in the pores of a rock. Strata containing different fluids, such as various saturations of oil, gas and water, may be encountered in the process of drilling an oil or gas well. Fluids found in the target reservoir formation are referred to as reservoir fluids. Formation Pressure: The pressure of fluids within the pores of a reservoir, normally hydrostatic pressure, or the pressure exerted by a column of water from the formation’s depth to sea level. Geophysical Logs: A log of elemental concentrations from which the geochemistry of the formation may be derived. Hydrogen Sulfide (H2S): An extraordinarily poisonous gas with a molecular formula of H2S. At low concentrations, H2S has the odor of rotten eggs, but at higher, lethal concentrations, it is odorless. H2S is hazardous to workers and a few seconds of exposure at relatively low concentrations can be lethal, but exposure to lower concentrations can also be harmful. The effect of H2S depends on duration, frequency and intensity of exposure as well as the susceptibility of the individual. Kelly: A long square or hexagonal steel bar with a hole drilled through the middle for a fluid path. The kelly is used to transmit rotary motion from the rotary table or kelly bushing to the drillstring, while allowing the drillstring to be lowered or raised during rotation. Mud Pressure: The pressure of the column of drilling fluid in the wellbore. Packer: A device that can be run into a wellbore with a smaller initial outside diameter that then expands externally to seal the wellbore. Perforating Gun: A device used to perforate oil and gas wells in preparation for production. Rigging-up: To make ready for use. Equipment must typically be moved onto the rig floor, assembled and connected to power sources or pressurized piping systems. Rig Mat: A portable platform used to support equipment for construction and resource-based activities including drilling rigs, camps, tanks, helipads, etc. It also includes a structural roadway to provide passage over unstable ground, pipelines and more. 15 Glossary and Terminology Formation Evaluation Tools: The tools used for the measurement and analysis of formation and fluid properties. Formation evaluation is performed to assess the quantity and producibility of fluids from a reservoir. Formation evaluation guides wellsite decisions, such as placement of perforations and hydraulic fracture stages, and reservoir development and production planning.
  • 16. Canadian Society for Unconventional Resources (CSUR) Suite 420, 237 - 8th Avenue SE Calgary, AB T2G 5C3 Phone: 403-233-9298; Toll Free: 1-855-833-9298 Email: info@csur.com; Web: www.csur.com